5. The following actions be taken on the San Juan /San Carlos Water Line
Improvement project:
a. The contractor be granted a 2 day time extension against a 57 day time
overrun due to additional work added by change order and he be charged
liquidated damages for the remaining 55 days at a rate of $100 per day
for a total of $5,500.
b. The project be accepted and remaining funds of $23,598.04 be
authorized to Goldston Corporation.
This 9th Year Community Development Block Grant project provided for the
installation of new 6" and 12" diameter water lines and additional fire
hydrants in the San Juan and San Carlos areas to increase water pressure
and improve fire protection. The total cost of this work was $251,143.84.