7. The following actions be taken on the Purdue Road Improvements, Phase I
project:
a. The contractor be granted a 15 day time extension against a 29 day
time overrun due to material delivery problems and he be charged
liquidated damages for the remaining 14 days at a rate of $100 per day
for a total of $1,400.
b. The project be accepted and remaining funds of $29,610.55 be
authorized to King Construction Company.
The total cost of this 1982 bond project, which provided for the
construction of Purdue Road from Debra Lane to Laguna Shores Road, was
$156,014.29.