HomeMy WebLinkAboutM1984-1181 - 10/23/1984• • MOTIONS - 10/23/84 7. The following actions be taken on the Purdue Road Improvements, Phase I project: a. The contractor be granted a 15 day time extension against a 29 day time overrun due to material delivery problems and he be charged liquidated damages for the remaining 14 days at a rate of $100 per day for a total of $1,400. b. The project be accepted and remaining funds of $29,610.55 be authorized to King Construction Company. The total cost of this 1982 bond project, which provided for the construction of Purdue Road from Debra Lane to Laguna Shores Road, was $156,014.29. M84 -1181