HomeMy WebLinkAboutM1984-1189 - 10/30/1984MOTIONS - 10/30/84
7. A contract in the amount of $24,700 be awarded to Mendez Construction
Company for General Construction (slab, utilities, paving) for the
Maintenance Services Building project. Should the Mendez firm; however,
decline to accept the award, then a contract be awarded to A -1 General
Contractors in the amount of $30,800. An award for this work was made to
Hunt Construction Company on October 18, 1984, but this firm did not accept
the award and forfeited their 5% bid security. The Mendez firm is the
second low bidder and the A -1 firm is the third low bidder on this project,
for which seven bids were submitted.
M84 -1189