HomeMy WebLinkAboutM1984-1191 - 10/30/1984MOTIONS - 10/30/84 The following actions be taken on the Minor Storm Sewer Improvements, Phase 1 project: a. The contractor be granted a 4 -day time extension against a 48 day time overrun due to additional work added by change order and that he be charged liquidated damages for the remaining 44 days at the rate of $100 per day for a total of $4,400. The project be accepted and final payment of $24,989.03 be authorized to Ibanez Construction Company. The total cost of this 1982 bond project is $190,295.94. M84 -1191