The following actions be taken on the Minor Storm Sewer Improvements, Phase
1 project:
a. The contractor be granted a 4 -day time extension against a 48 day time
overrun due to additional work added by change order and that he be
charged liquidated damages for the remaining 44 days at the rate of
$100 per day for a total of $4,400.
The project be accepted and final payment of $24,989.03 be authorized
to Ibanez Construction Company.
The total cost of this 1982 bond project is $190,295.94.