4. The following actions be taken on the Marina L -Head Ramp Expansion project:
a. The contractor be granted a 10 -day time extension against a 17 -day
time overrun due to design modifications and material delivery delays,
which were beyond the contractor's control, and that he be charged
liquidated damages for the remaining 7 days at a rate of $45 per day
for a total of $315.
The project be accepted and final payment of $10,551.30 be authorized
to Black Brothers Construction, Inc.
The total cost of this work was $41,143.20, which was funded by the Corpus
Christi Reinvestment Zone No. 1 and Frontier Enterprises, the lessee for
the L -Head floating restaurant.
M84 -1208