Loading...
HomeMy WebLinkAboutM1984-1208 - 11/13/19840 0 MOTIONS - 11/13/84 4. The following actions be taken on the Marina L -Head Ramp Expansion project: a. The contractor be granted a 10 -day time extension against a 17 -day time overrun due to design modifications and material delivery delays, which were beyond the contractor's control, and that he be charged liquidated damages for the remaining 7 days at a rate of $45 per day for a total of $315. The project be accepted and final payment of $10,551.30 be authorized to Black Brothers Construction, Inc. The total cost of this work was $41,143.20, which was funded by the Corpus Christi Reinvestment Zone No. 1 and Frontier Enterprises, the lessee for the L -Head floating restaurant. M84 -1208