The following actions be taken in connection with the new City Warehouse at
the Municipal Service Center:
a. The project be accepted.
b. Black Brothers Construction, Inc., who provided the building slab,
site work and utilities at a total cost of $226,186, be granted a
12 -day time extension to supplement the 90 working days authorized in
their contract because of additional work added by change order, and
remaining funds of $29,954.79 be paid this firm.
J. H. Chapman Construction Co., Inc., who furnished and erected the
pre- engineered steel building at a cost of $70,789 be paid remaining
funds of $16,635.42.
This project provides a new 14,400 square foot Warehouse to serve City
operations with the present Warehouse building on Sam Rankin Street
scheduled for demolition as part of the new City Hall project in that area.