HomeMy WebLinkAboutM1984-1259 - 12/11/1984MOTIONS - 12/11/84
9. The N.A.S. Drive Landscaping project be accepted and final payment of
$6,213.19 be authorized to Curries, Inc. It is further recommended that
the contractor be charged liquidated damages for a 21 day time overrun at
the rate of $45.00 per day for a total of $945.00. The total cost of this
8th Year Community Development Block Grant project was $26,349.45.
M84 -1259