HomeMy WebLinkAboutM1984-1262 - 12/11/1984MOTIONS - 12/11/84
12. The Hillcrest Park Improvement project be accepted and remaining funds of
$22,789.17 be authorized to Mehne Construction, Inc. It is further
recommended that the contractor be granted a 43 day time extension to
supplement the 60 working days allotted for the work because of material
delivery delays beyond the contractor's control. The total cost of this
9th Year Community Development Block Grant project is $59,185.77.
M84 -1262