11. Approving Change Order No. 1 to the Broadway Wastewater Treatment Plant
Improvements for a deductive amount of $7,052.50 under the value
Engineering Incentive Procedures section of the City's contract with
J. D. Construction and Refinery Maintenance Company. This change order
provides for an alternate method of installing sludge lines under two
50 -foot diameter clarifier tanks at the Broadway Treatment Plant at a net
savings of $14,105. Under the Value Engineering Incentive provisions of
this contract, the contractor is entitled to 50% of these savings, thus,
resulting in a net savings to the City of $7,052.50.