HomeMy WebLinkAboutM1985-0074 - 02/12/1985• MOTIONS - 2/12/85 C] 5. Change Order No. 4 to the Seawall Overlook project in the amount of $22,933 be approved which provides for the installation of 24 timber piling in the Marina at both T -Heads and the L -Head location. This work is provided for in the 1984 -85 Marina Operating Budget; and as the Coldston firm has pile driving equipment on site and their contract contains a very competitive unit price for this type of work, it is recommended that this work be done by change order at this time. A separate appropriation is not required for this budgeted work. M85 -0074