HomeMy WebLinkAboutM1985-0128 - 03/12/1985• MOTIONS - 3/12/85 • 9. Approving Change Order No. 1 in the amount of $7,824.94 to the Allison Wastewater Treatment Plant Final Improvements project. Change Order No. 1 provides for the relocation of an existing sludge line which runs through the proposed location of a new concrete digester basin and grit removal basin. The sludge line was installed by City crews and was not originally shown on construction plans. Required funds are available under the project's contingency account. M85 -0128