HomeMy WebLinkAboutM1985-0177 - 04/02/1985• MOTIONS - 4/2/85 0 13. The following actions be taken on the Bowie - Crockett - Larcade Street Improvement project: a. The contractor be granted a 19 -day time extension against a 41 -day time overrun due to utility and testing delays beyond the contractor's control, and he be charged liquidated damages for the remaining 22 days at the rate of $100 per day for a total of $2,200. b. The project be accepted and final payment of $28,047.57 be authorized to Maverick Construction Company. The total cost of this 1982 Voluntary Paving Street Reconstruction Project was $198,790.85. (SIX AFFIRMATIVE VOTES REQUIRED TO PASS) M85 -0177