13. The following actions be taken on the Bowie - Crockett - Larcade Street
Improvement project:
a. The contractor be granted a 19 -day time extension against a 41 -day
time overrun due to utility and testing delays beyond the contractor's
control, and he be charged liquidated damages for the remaining 22
days at the rate of $100 per day for a total of $2,200.
b. The project be accepted and final payment of $28,047.57 be authorized
to Maverick Construction Company.
The total cost of this 1982 Voluntary Paving Street Reconstruction Project
was $198,790.85. (SIX AFFIRMATIVE VOTES REQUIRED TO PASS)