HomeMy WebLinkAboutM1985-0214 - 04/23/19850 MOTIONS - 4/23/85 • 17. Ibanez Construction Company be determined to be in default on a contract to construct golf cart paths at Gabe Lozano, Sr. Golf Center and a contract to complete the work be awarded to M & M Construction Company in the amount of $15,250.00. The Ibanez firm was awarded this $37,285.82 contract in August, 1984 and was allotted 20 working days to complete the work. The M & M firm, a subcontractor on the project, can complete the work with remaining funds from the original contract award. M85 -0214