HomeMy WebLinkAboutM1985-0243 - 05/14/1985• MOTIONS - 5/14/85 0 4. The Maintenance Services Building projects be accepted as complete and the following action be taken on the two contracts: a. Mendez Construction Company, whose contract totaled $27,747, be granted a 12 -day time extension against an 18 -day contract overrun, liquidated damages at the rate of $45 per day be charged for the remaining 6 days, for a total of $270, and final payment of $3,462.30 be authorized. Black Brothers Construction Company, Inc., whose contract totaled $8,657, be granted a 7 -day time extension to supplement 20 working days allotted because of delays beyond the contractor's control and final payment of $865.70 be authorized. This project provided for dismantling a 4,000 square foot pre- engineered steel building located on the new City Hall site at Leopard Street and transporting and re- erecting this building at the City Service Center. M85 -0243