HomeMy WebLinkAboutM1985-0243 - 05/14/1985• MOTIONS - 5/14/85 0
4. The Maintenance Services Building projects be accepted as complete and the
following action be taken on the two contracts:
a. Mendez Construction Company, whose contract totaled $27,747, be
granted a 12 -day time extension against an 18 -day contract overrun,
liquidated damages at the rate of $45 per day be charged for the
remaining 6 days, for a total of $270, and final payment of $3,462.30
be authorized.
Black Brothers Construction Company, Inc., whose contract totaled
$8,657, be granted a 7 -day time extension to supplement 20 working
days allotted because of delays beyond the contractor's control and
final payment of $865.70 be authorized.
This project provided for dismantling a 4,000 square foot pre- engineered
steel building located on the new City Hall site at Leopard Street and
transporting and re- erecting this building at the City Service Center.
M85 -0243