Loading...
HomeMy WebLinkAboutM1985-0245 - 05/14/1985• MOTIONS - 5/14/85 • 6. Accepting the Broadway Wastewater Treatment Plant Minor Improvements project and authorizing final payment of $8,021.97 to J. D. Construction and Refinery Maintenance, Inc. It is further recommended that the contractor be granted a 17 -day time extension due to material delivery delays beyond his control. Improvements in this project, which had a total cost of $80,219.70, included the replacement of sludge lines in two clarifiers, the installation of electronic metering and recording equipment, the installation of approximately 1,000 feet of perimeter security fence and the installation of an effluent meter to meet Department of Water Resources' requirements. M85 -0245