HomeMy WebLinkAboutM1985-0258 - 05/21/1985• MOTIONS - 5/21/85 S 9. The following actions be taken on the New City Hall Site Building Demolition project: a. The contractor be granted a 12 day time extension against a 32 day time overrun, and he be charged liquidated damages for the remaining 20 days at the rate of $100 per day for a total of $2,000. b. The project be accepted and final payment of $13,650.25 be authorized to Sunbelt Constructing & Demolishing Corp. The total cost of this demolition work, which included the removal of buildings, parking lots, and foundations at the new City Hall site, is $112,896.76. M85 -0258