9. The following actions be taken on the New City Hall Site Building
Demolition project:
a. The contractor be granted a 12 day time extension against a 32 day
time overrun, and he be charged liquidated damages for the remaining
20 days at the rate of $100 per day for a total of $2,000.
b. The project be accepted and final payment of $13,650.25 be authorized
to Sunbelt Constructing & Demolishing Corp.
The total cost of this demolition work, which included the removal of
buildings, parking lots, and foundations at the new City Hall site, is
$112,896.76.