HomeMy WebLinkAboutM1985-0271 - 05/28/1985• MOTIONS - 5128/85 •
8. The following actions be taken on the Greenwood Park /Garcia School
Multipurpose Court project:
a. The contractor be granted a 14 -day time extension to supplement 25
working days allotted for the project due to excessive delays and
reworking as a result of extreme wet weather conditions.
b. The project be accepted and final payment of $11,677 be authorized to
Black Brothers Construction, Inc.
The total cost of this project, which is funded with 1977 Park Bond Funds
as part of the Tennis Improvement Program, is $33,925.
M85 -0271