HomeMy WebLinkAboutM1985-0274 - 05/28/1985• MOTIONS - 5/28/85 •
11. The fallowing actions be taken in connection with the Oso Wastewater
Treatment Plant Contract 4:
a. The contract with Permian Constructors, Inc., and Republic Mechanical
Corporation, a joint venture, providing for first phase expansion of
the Oso Wastewater Treatment Plant, be accepted, subject to claims and
defenses in pending litigation.
b. The contractor be assessed $87,300 liquidated damages for a contract
time overrun of 873 days at $100 per day.
C. Retainage of $372,845.73 be withheld until litigation between
Permian /Republic and the City is resolved.
d. Deducting $54,394.17 for repairs performed on the traveling clarifier
bridges in order to bring them into acceptable condition for
installation by contractor on Contract 5. Permian /Republic refused to
make these repairs, thus, making it necessary for the City to have the
work done by the contractor on Contract 5.
Construction costs for this project totalled $7,456,914.67.
M85 -0274