HomeMy WebLinkAboutM1985-0274 - 05/28/1985• MOTIONS - 5/28/85 • 11. The fallowing actions be taken in connection with the Oso Wastewater Treatment Plant Contract 4: a. The contract with Permian Constructors, Inc., and Republic Mechanical Corporation, a joint venture, providing for first phase expansion of the Oso Wastewater Treatment Plant, be accepted, subject to claims and defenses in pending litigation. b. The contractor be assessed $87,300 liquidated damages for a contract time overrun of 873 days at $100 per day. C. Retainage of $372,845.73 be withheld until litigation between Permian /Republic and the City is resolved. d. Deducting $54,394.17 for repairs performed on the traveling clarifier bridges in order to bring them into acceptable condition for installation by contractor on Contract 5. Permian /Republic refused to make these repairs, thus, making it necessary for the City to have the work done by the contractor on Contract 5. Construction costs for this project totalled $7,456,914.67. M85 -0274