HomeMy WebLinkAboutM1985-0306 - 06/25/19850 0 MOTIONS - 6/25/85 6. The following actions be taken relative to the Chaparral Apron and Northwest Hangar Site Improvement project at Corpus Christi International Airport: a. The contractor be granted a 21 day time extension for extra work authorized by Change Orders #1 and #2 and not be charged liquidated damages for the remaining 42 days of a 63 day time overrun in exchange for the contractor not pursuing the claim against the City for delays which occurred on lime stabilized base reworking operations. b. The project be accepted and final payment in the amount of $147,315.50 be authorized to South Texas Construction Company. This 1982 Airport Bond project provided for the expansion of the Chaparral Apron, the extension of Taxiway 'P', the construction of a service road, and utility installations for future hangar lease sites. The total cost of this work is $893,004.01, all of which, except the water and sewer line installations, is funded by a 90% FAA grant and the remaining by local funds. M85 -0306