MOTIONS - 7/30/85
9. Authorizing the following actions be taken on the West Oso High School
Tennis Court Rehabilitation and Lighting Improvement project:
a. The contractor be granted a 29 -day time extension to supplement the 30
working days allotted for this work due to delays beyond the
contractor's control in extending electrical service to the new tennis
court lighting system.
b. The project be accepted and final payment of $22,771.80 be authorized
to Black Brothers Construction, Inc.
The total cost of this work, which is funded by Park Bond Funds, is
$61,704.
M85 - 0360