Loading...
HomeMy WebLinkAboutM1985-0369 - 08/06/1985• MOTIONS - 8/6/85 • 5. Approving the following actions on the Water Distribution Pumping Station Supervisory Control Rehabilitation project: a. Granting the contractor a 56 day time extension to supplement the allotted 45 working days due to material delivery delays beyond the contractor's control. b. Accepting the project and authorizing final payment of $7,395.13, for a total construction cost of $51,065.33, to Schuette Electric Company. As a result of this project, which included the installation of electrical modifications and circuitry needed to install previously purchased instruments and telemetering equipment, all water pumping operations can now be controlled from the 0. N. Stevens Water Filtration Plant. M85 -0369