5. Approving the following actions on the Water Distribution Pumping Station
Supervisory Control Rehabilitation project:
a. Granting the contractor a 56 day time extension to supplement the
allotted 45 working days due to material delivery delays beyond the
contractor's control.
b. Accepting the project and authorizing final payment of $7,395.13, for
a total construction cost of $51,065.33, to Schuette Electric Company.
As a result of this project, which included the installation of electrical
modifications and circuitry needed to install previously purchased
instruments and telemetering equipment, all water pumping operations can
now be controlled from the 0. N. Stevens Water Filtration Plant.
M85 -0369