HomeMy WebLinkAboutM1985-0394 - 08/27/1985ft MOTIONS - 8/27/85 a
9. Approving Change Order No. 2 in the amount of $5,798 to the Exposition Hall
Demolition project. The Change Order provides for key - controlled light and
A/C switches, relocation of electric panel and motor starter, heavy -duty
gate, and restroom ceiling material substitution. All items pertain to
maintenance considerations and control of equipment installed in the
present contract. Funds for this work are available in the original
contingency appropriation for the project.
M85 -0394