HomeMy WebLinkAboutM1985-0395 - 08/27/1985ft MOTIONS - 8/27/85 Go 10. Accepting the Saratoga Fence Relocation project and authorizing final payment of $4,717.96 to Allied Steel and Wood Fence Company. It is recommended that the contractor be granted a 4 -day time extension to supplement the 30 working days allowed in the contract. The Navy recently dedicated a 10 -foot strip of land along Cabaniss Field for the upcoming widening of Saratoga Boulevard, and this project provided for the con- struction of a new fence along the new right -of -way line as a result of the dedication. The total coast for this work is $25,047.69, of which the Navy paid $9,428.74 towards the cost of the new fence. M85 -0395