HomeMy WebLinkAboutM1985-0441 - 10/01/1985• MOTIONS - 10/1/85 0 10. Approving the following actions on the Sunnybrook Drainage Improvement project: a. The contractor be granted an 11 -day time extension against a 16 -day time overrun due to delays beyond his control and liquidated damages be charged for the remaining 5 days at the rate of $100 per day for a total of $500. b. The project be accepted and remaining funds of $11,490.40 be author- ized to the contractor, Richard L. Brown and Stanley R. Brown, a Joint Venture. The total cost of this 1982 bond project is $114,903.95. M85 -0441