12. Approving the following actions on the Wilmot Park Site Development, Phase
I project:
a. The contractor be granted a 39 -day time extension due to additional
work authorized by change order and other delays beyond the
contractor's control.
b. The project be accepted and remaining funds of $11,512.62 be
authorized to the contractor, Richard L. Brown.
The total cost of this Community Development Block Grant project is
$98,018.05.
M85 -0465