Loading...
HomeMy WebLinkAboutM1985-0479 - 10/22/1985• MOTIONS — 10/22/85 • 8. Approving the following actions on the Los Encinos Park Improvement project: a. The contractor be granted an 18 —day time extension against a 29 —day time overrun due to problems encountered during the construction of the gazebo, and that he be charged liquidated damages for the remaining 11 days at the rate of $45 per day for a total of $495. b. The project be accepted and remaining funds of $7,848.42 be authorized to Fraton, Inc. The total cost of this 10th Year Community Development Block Grant project is $36,998.54. M85 -0479