HomeMy WebLinkAboutM1985-0479 - 10/22/1985• MOTIONS — 10/22/85 •
8. Approving the following actions on the Los Encinos Park Improvement
project:
a. The contractor be granted an 18 —day time extension against a 29 —day
time overrun due to problems encountered during the construction of
the gazebo, and that he be charged liquidated damages for the
remaining 11 days at the rate of $45 per day for a total of $495.
b. The project be accepted and remaining funds of $7,848.42 be authorized
to Fraton, Inc.
The total cost of this 10th Year Community Development Block Grant project
is $36,998.54.
M85 -0479