Loading...
HomeMy WebLinkAboutM1985-0482 - 10/22/1985• MOTIONS - 10/22/85 11. Approving the following actions on the Seawall Overlook Park project: a. The contractor be granted a 67 -day time extension to supplement the 75 working days allotted for the project due to the sizeable amount of additional work authorized by change order. b. The project be accepted and remaining funds of $26,542.20 be authorized to the Goldston Corporation. The total cost of the work performed by Goldston is $248,119.50. This project is funded with a matching grant from the Texas Park and Wildlife Department, 9th Year Community Development Block Grant funds, Reinvestment Zone funds, and budgeted Marina operating funds. M85 -0482