8. Approving the following actions on the Artesian Park and Temple Park
Improvement project:
a. The contractor be granted an 18 -day time extension to supplement the
40 working days allotted to complete the project due to late delivery
of materials and minor utility delays which were beyond the
contractor's control.
b. The project be accepted and remaining funds of $31,095.50 be
authorized to Black Brothers Construction, Inc.
The total cost of the work performed, which is funded by 10th and 11th Year
Community Development Block Grant funds, is $84,087.50.
M86 - 0008