HomeMy WebLinkAboutC2005-002 - 1/11/2005 - Approved CHANGE ORDER No. 11
Department of Engineering Services
City of Corpus Christi, Texas
CHANGE ORDER NO: 11
FUNDING SOURCE: 550910-3181-00000-110710
Operating Department: Department of Enqineerinq Services
Name of Project: Convention Center Expansion/Renovation #4198
Contractor: Moorhouse/Beecroft Joint Venture, LLC
DATE: December 10, 2004
CONTRACT TIME: 670 C.D.
CHANGE AS FOLLOWS:
Provide each of the following revisions (Items "a" through "bb") as identified on the a[tached Pages 2 of
5 through 5 of 5 in accordance with the requirements outlined in the Contract Documents.
Total Add - Lump Sum: $388,749.00
Why were these changes necessary? (If left off the plans and specifications, explain why)
The maiodty of the attached proposed revisions include work as required to modify or complete the current set of
Desiqn Documents.
How can similar changes be avoided in the future? Many of these items could have been included in the oriqinal
scope of work if additional information would have been available at the time the conb'act amount was aqreed upon.
A. CONTRACT PRICE ............................................... $
B. TOTAL CHANGE ORDERS (inc. current) ............ $
C. NEW CONTRACT PRICE .....................................$
D. THIS CHANGE ORDER ........................................ $
E. PERCENT TOTAL CHANGE (B/A) .......................
F. PREVIOUS ADDN'L TIME AUTHORIZED ............
G. ADDN'L CONTRACT TIME THIS CHANGE ORDER
H. TOTAL ADDITIONAL TIME ..................................
24,614,045.00
2,868,472.00
27,482,517.00
388,749.00
11.65%
0CD
0 CD
0 CD
Pro
CITY OF CORPUS CHRISTI, TEXAS
~fE::jfy Engineer ~,
APPROVED/: ~'~:~ (,~/O~e r a ti n~ D e p t.
CONTRA~_R
By: -
Title/¢~;2 ~'~.~'
¢~Directolof Management
~ ~O ~r~, Legal Department
2005-002
01/11/05
M2005-010
Moorhouse/Beecroft Joint Venture
CHANGE ORDER No. 11
CONVENTION CENTER EXPANSION
Department of Engineering Services
City of Corpus Christi, Texas
a.)
b.)
c.)
d.)
e.)
g.)
PCO/CR No, 43 - Provide additional under floor lighting in the crawl space. All additional work shall
be performed in accordance with the letter from Rabalais Constructors dated December 8, 2004.
Also refer to the Moorhouse/Beecroft Change Proposal No. 46 dated December 8, 2004.
Add = $2,961.00
PCO/CR N o. 6 6 - Remove and replace the wet roof insulation pdor to installation of new
replacement roof. Also, provide new electrical power to the roof top air handling units. All additional
work shall be performed in accordance with the Moorhouse/Beecroft Change Proposal No. 74
dated November 19, 2004.
Add = $150,123 00
PCO/CR No. 78 - Provide revisions [o the ceiling heights at the operable wall partitions in the
Ballroom. All additional work shall be performed in accordance with the responses to the Request
for Information No. 248, 251 and 252. Moorhouse/Beecroft Change Proposal No. 112 dated
December 3, 2004.
Add = $45,959.00
PCO/CR No. 118 - Provide additional steel support bracing required above the ballroom ceiling. All
additional work shall be performed in accordance with the response to the Request for Information
No. 322-R1 dated January 23, 2004. Moorhouse/Beecroft Change Proposal No. 136 dated
December 5, 2004.
Add = $12,346.00
PCO/CR No, 141 - Provide additional XMA-3 light fixtures at the exterior columns. All additional
work shall be performed in accordance with the Proposal Request No. 43 issued by'f'VS/Gignac
dated May 5, 2004. Moorhouse/Beecroft Change Proposal No. 164 dated November 15, 2004.
Add = $9,346.00
PCO/CR No. 144- Provide additional work as required to paint the metal panels in the curtainwall
shadowboxes. All additional work shall be performed in accordance with the response to the
Request for Information No. 393 dated May 13, 2004. Also refer to the Moorhouse/Beecroft
Change Proposal No. 159 dated May 11, 2004.
Add -- $16,507.00
PCO/CR No. 148 - Provide modifications to the drywall around the glass handrails in the Selena
Auditorium. All additional work shall be performed in accordance with the response to the Request
for Information No. 308 and 358. Also refer to the Moorhouse/Beecroft Change Proposal No. 152
dated June 3, 2004.
Add = $9,561.00
h.) PCO/CR No. 1'~0 - Provide revisions to the control sequence at the automatic doors. All additional
work shall be performed in accordance with the responses to RFI's No. 417 dated July 14, 2004.
Moorhouse/Beecroft Change Proposal No. 192 dated August 20, 2004.
Add -- $660.00
Page 2 or5
CHANGE ORDER No. 11
CONVENTION CENTER EXPANSION
Department or Engineering Services
City of Corpus Christi, Texas
i.)
PCO/CR No. 173 - Provide flowable fill at the Barge Dock flapper valve as required to fill the void
between the paving slab and the manhole. All additional work shall be performed in accordance
with the Moorhouse/Beecroft Change Proposal No. 185 dated August 30, 2004.
Add = $915.00
j.)
PCO/CR No. 174 - Provide two coats of paint on the floor of the Rehearsal Hall in the Selena
Auditorium. All additional work shall be provided in accordance with the Moorhouse/Beecroft
Change Proposal No. 197 dated August 25, 2004.
Add = $2,744.00
k.)
PCO/CR No. 175 - Provide Siemon Cat 6 patch panels to replace the telephone punch down
panels. This change was requested by the City MIS Department All additional work shall be
performed in accordance with the MB-JV Change Proposal No. 198 dated September 1, 2004.
Add : $5,481.00
PCO/CR No. 176 - Provide an additional Type "A" inputJoutput plate on the east wall of Ballroom
"B". All additional work shall be performed in accordance with the response to the Request for
Information No. 421-R1. Moorhouse/Beecroft Change Proposal No. 201 dated September 2, 2004.
Add = $2,466.00
m.)
PCO/CR No. 177 - Provide electrical power to the new American Bank Center signs at the south
and west sides of the building. All additional work shall be performed in accordance with Drawing 2
of 5 issued by Chandler Signs dated July 19, 2004. Moorhouse/Beecroft Change Proposal No. 206
dated October 12, 2004.
Add = $4,164.00
n.) PCO/CR No. 179 - Provide revisions to the Kitchen Area as required to add a new account clerk
office, cash room and a room with a counter. All additional work shall be performed in accordance
with the Proposal Request No. 45 issued by TVS/ Gignac dated September 28, 2004.
Moorhouse/Beecroft Change Proposal No. 215 dated November 16, 2004.
Add = $21,770.00
o.) PCO/CR No. 182 - Remove and replace the broken escalator glass rail thatwas damaged during
an event. All additional work shall be performed in accordance with the Moorhouse/Beecroft
Change Proposal No. 209 dated November 15, 2004.
Add = $4,224.00
p.)
PCO/CR No. 184 - Provide all additional work associated with adding an expansion joint in the
stone pavers between the Main Lobby Entry and the existing Prefunction Area. All additional work
shall be performed in accordance with the response to the Request for Information No. 397 dated
July 1,2004. Moorhouse/Beecroft Change Proposal No. 213 dated November 15, 2004.
Add = $2,479.00
3of5
CHANGE ORDER No. ll
CONVENTION CENTER EXPANSION
DepadmentofEngineeringSe~ices
Ci~orCorpusChristi, Texas
q.)
r.)
s.)
t.)
u.)
v.)
w.)
x.)
PCO/CR No. 186 - Provide additional fireproofing at the structural steel tube members that were
exposed during demolition. All additional work shall be performed in accordance with the
Moorhouse/Beecroff Change Proposal No. 211 dated November 15, 2004.
Add = ,'~,756.00
PCO/CR No. 187 - Provide additional thin set slate pavers at the entrance of the Selena
Auditorium. All additional work shall be performed in accordance with the response to the Request
for Information No. 431 dated August 19, 2004. Also refer to the Moorhouse/Beecroft Change
Proposal No. 195 dated November 15, 2004.
Add = $2,325.00
PCO/CR No. 188 - Provide various electrical revisions in the Kitchen including additional
powedtelecom to the CheFs Office, power for the additional Ansul [ire suppression system at the
popcorn popper vent hood, additional electrical ceiling drops for the portable warming cads. All
additional work shall be performed in accordance with the Moorhouse/Beecroft Change Proposal
No. 204 dated November 15, 2004.
Add = $17,001.00
PCO/CR No. 189 - Provide all additional work associated with relocating the fire alarm devices in
stone walls and metal wall panels. All additional work shall be performed in accordance with the
response to the Request for Information No. 394. Moorhouse/Beecroft Change Proposal No. 171
dated November 19, 2004.
Add -- $22,277.00
PCO/CR No. 190 - Provide additional sprinkler heads at each of the skylights. All additional work
shall be per[ormed in accordance with the request for the Corpus Chdsti Fire Marshal and the
Moorhouse/Beecro[t Change Proposal No. 186 dated August 26, 2004.
Add = $8,131.00
PCO/CR No. 191 - Provide additional overflow drains at the section of root along the east side of
the Prefunction Area. All additional work shall be performed in accordance with the Moorhouse/
Beecroft Change Proposal No. 172 dated November 18, 2004.
Add -- $4,357.00
PCO/CR No. 192 - Provide revisions to the height of the glass doors in the Administration Area.
All additional work shall be performed in accordance with the response to the Request for
In[ormation No. 388 dated May 24, 2004. Moorhouse/Beecroft Change Proposal No. 170 dated
November 18, 2004.
Add = $2,265.00
PCO/CR No. 193 - Provide structural steel framing revisions above the existing stair at Column
Line 10. All additional work shall be performed in accordance with the MEI Govind SKI-11-17-03,
SK2-11-17-03 and SK3-11-17-03. Also refer Io the Moorhouse/Beecroft Change Proposal No. 100
dated November 18, 2004.
Add -- $6,872.00
4 of 5
CHANGE ORDER No. 11
CONVENTION CENTER EXPANSION
Department of Engineering Services
CiLy of Corpus Christi, Texas
y.)
z.)
aa.)
bb.)
PCO/CR No. 194 - Provide revisions to the structural support members at the escalator. Also
revise the drywall framing around the escalator. All additional work shall be performed in
accordance with the response to the Request for Information No. 273 dated January 15, 2004 and
RFI No. 273-R1 dated January 30, 2004. Moorhouse/Beecroft Change Proposal No. 86 dated
November 18, 2004.
Add = $4,788.00
PCO/CR No. 195 - Provide new diffusers in the meeting room corddor ceilings as required to
allow the diffusers to line up with the light fixtures. All additional work shall be performed in
accordance with the Moorhouse/Beecroft Change Proposal No. 160 dated December 5, 2004.
Add = $3,352.00
PCO/CR No. 196 - Provide revisions to the roof above the Main Lobby Area. All additional work
shall be performed in accordance with the response to [he Request for Information No. 351 dated
Apdl 2, 2004. Moorhouse/Beecroft Change Proposal No. 148 dated December 5, 2004.
Add = $19,206.00
PCO/CR No. 197 - Provide a chase wall around the gas line in Stair E-2. All additional chase wall
work shall be performed in accordance with the response to the Request for Information No. 377
dated May 27, 2004. Moorhouse/Beecroft Change Proposal No. 210 dated December 5, 2004.
Add = $1,691.00