HomeMy WebLinkAboutC2005-003 - 1/11/2005 - ApprovedCHANGE ORDER
CHANGE ORDER NO
Operating Deparlment:
Name of Project:
Contractor:
CHANGE
Department of Englneenng Services
City of Corpus Christi, Texas
14 PROJECT NO 1019 CONTRACT TIME:_ 365 Calendar Days
Corpus Christi Department of Avia[ion DATE __ January 3, 2005
Corpus Christi International Airport -Roadways and Parkinq Lot Improvements
Bay, Ltd.
ART PARKING ROADWAY
1 East Parking lot revisions not covered in C O #7
2 F~re Hydrant extension
3 Parking Lot elevation control
4 Add overhead sign light supports
5 Additional HMAC for parking lot
6 Adjust 16 inlet tops
7 Remove stockpile of material from east access road
8 Blast and paint old overhead sign suppod
9 Add elecldcal disconnect at fountain
10 Add arm and fixture to north parking Io[ lights
11 Add lights to old overhead sign
12 Revise structure on all overhead signs
13 Granite walkway
14 Mill transition between old and new pavements on
International Drive
15 Concrete median barriers
16 Domestic water line on east side International Drive
17 Signalure fueling slab
18 Guard rail on west access road
19Add sod and irrigation
20 ADA striping rewsions
21 5KVA Power center enclosure
22 Line Item adjustments for base material HMAC
$ 131145
3,840 00
$1,76806
$ 4OO 00
$ 6,00000
$ 1,01800
$ 36,483.11
$ 12,350.00
$ 3,59846 $ 3,598.46
$ 4,34575
S 578970
$ 2,955 00
S 5,17482
($14,50949)
$ 6,250 00
$14,355 00
$ 2,000.00
$ 1,400.14
$ 3,252.95
$ 3,543 75
$ 1,979 25
TERMINAL
$ 3.598.46
$19,49713
$5,151.45 $59,609.66 $42,143.30
Totals $130,000.00
Why wasthis change necessa~?(Ifle~ offthe plans and specifications, explain why)
_ 1 See a~ached
$23,095.59
How can similar changes be avoided in the Iuture?
1 See attached
Bay, Ltd.
A CONTRACT PRICE ................................... $ 6,5411301.99
B TOTAL CHANGE ORDER(inc current) $ 1,283,75485
C NEW CONTRACT PRICE $ 7,825,05684
D THIS CHANGE ORDER $ 130,000.00
E PERCENT TOTAL CHANGE (B/A) 17 6 %
F PREVIOUS ADDN'L TIME AUTHORIZED 0_ c d
G ADDN'L CONTRACT TIME THIS CHANGE ORDER 0 c d
H TOTAL ADDITIONAL TIME 0 c d
CITY OF ,~/~)RPUS CHRISTI, TEXAS
/ /C~b/Engineer
CONT~.,~R: Bay, Ltd.
Tide: ~ '
APPROVED ,~..~0~~ Operating De padment
,¢,~}~.~/~f~l~ ~'t. ,I Managemen(/Budget Department
v ~.-~...~ ~, ¢,,.2~.~,..~Legal Department --
2005-003
01/11/05
M2005-013
Change Order 14 Project 1019 December 11, 2004
CHANGE
1. East Parking lot revisions not covered in C.O, 7
Why was this change necessary? (If left off the plans and specifications, explain why)
Change in entrance configuration
How can similar changes be avoided in the future?
Better plan review
2. Fire Hydrant Extension
Why was this change necessary? (If left off the plans and specifications, explain why)
Elevations changes to provide drainage on the roadway north of the toll plaza.
How can similar changes be avoided in the future?
Unavoidable
3. Parking Lot Elevation Control
Why was this change necessary? (If left off the plans and specifications, explain why)
To correct uneven existing surface
How can similar changes be avoided in the future?
Design change
4. Add overhead sign light supporLs
Why was this change necessary? (If left off the plans and specifications, explain why)
Specified lights did not match design of support structure
How can similar changes be avoided in the future?
Better plan review
5. Additional HHAC for parking lot
Why was this change necessary? (If left off the plans and specifications, explain why)
HMAC overrun due to change in grade control
How can similar changes be avoided in the future?
Design change
6. Adjust 16 inlet tops
Why was this change necessary? (If left off the plans and specifications, explain why)
The inlets were in the main parking lot and were adjusted to provide a transition between new pavement overlay
and existing inlet.
How can similar changes be avoided in the future?
Require more detailed field surveys from Designers
7. Remove stockpile of material from east access road
Why was this change necessary? (If left off the plans and specifications, explain why)
Change in site conditions
How can similar changes be avoided in the future?
Better coordination between separate contract drawings
8. Blast and paint old overhead sign support
Why was this change necessary? (If left off the plans and specifications, explain why)
Existing overhead sign required rework to match new signs
How can similar changes be avoided in the future?
Better Plan review
9. Add electrical disconnect at fountain
Why was this change necessary? (If left off the plans and specifications, explain why)
Fountain added under separate contract that did not require electrical service
How can similar changes be avoided in the future?
Better contract coordination
10. Add arm and fixture to notth parking lot lights
Why was this change necessary? (if left off the plans and specifications, explain why)
Lighting required on added parking spaces
How can similar changes be avoided in the future?
Unavoidable
11. Add lights to old overhead sign
Why was this change necessary? (If left off the plans and specifications, explain why)
Existing lights were inoperable
How can similar changes be avoided in the future?
Unavoidable
12. Revise structure on all overhead signs
Why was this change necessary? (If left off the plans and specifications, explain why)
Specified signs were not comparable to support design
How can similar changes be avoided in the future?
Better plan review
13. Granite Walkway
Why was this change necessary? (If left off the plans and specifications, explain why)
Fountain added to site by separate contract required walkway
How can similar changes be avoided in the future?
Unavoidable
14. Mill transition between old and new pavements on International Drive
Why was this change necessary? (if left off the plans and specifications, explain why)
Unforseen condition
How can similar changes be avoided in the future?
Unavoidable
15. Concrete median Barriers
Why wae this change necessary? (If left off the plans and specifications, explain why)
Required to direct traffic
How can similar changes be avoided in the future?
Unavoidable
16. Domestic water line on east side I'nternational Drive
Why was this change necessary? (If left off the plans and specifications, explain why)
Replacement of old existing main left structures without water service
How can similar changes be avoided in the future?
Plan review
17. Signature fueling slab
Why was this change necessary? (if left off the plans and specifications, explain why)
Changed conditions required replacement of slabs
How can similar changes be avoided in the future?
Unavoidable
~_8. Guard rail on west access road.
Why was this change necessary? (If left off the plans and specifications, explain why)
Rails required for safety
How can similar changes be avoided in the future?
Unavoidable
;[9. Add Sod and irrigation
Why was this change necessary? (If left off the plans and specifications, explain why)
Discrepancies be[ween two separate contracts
How can similar changes be avoided in the future?
Better coordination between Design Contractors (Plan Review)
20. ADA Striping revisions
Why was this change necessary? (If left off the plans and specifications, explain why)
Change in requirements
How can similar changes be avoided in the future?
Unavoidable
21. 5KVA Power Center enclosure
Why was this change necessary? (If left off the plans and specifications, explain why)
Design discrepancy
How can similar changes be avoided in the future?
Better design review
22. Line Item adjustments for base material and HMAC.
Why was this change necessary? (If left off the plans and specifications, explain why)
Differences between specified and actual in-place Quantities.
4 PG 02 PAVEMENT DEMOLITION
5PG02 PAVEMENT DEMOLITION
How can similar changes be avoided in the future?
Unavoidable
Total $130,000.00