HomeMy WebLinkAboutC2005-225 - 5/10/2005 - Approved AMENDMENT NO. 2 TO
SANITARY SEWER TRUNK SANITARY SEWER TRUNK FORCE MAiN AND LIFT STATION
CONSTRUCTION AND REIMBURSEMENT AGREEMENT
THE STATE OF TEXAS
COUNTY OFNUECES
This agreement amends the Sanitary Sewer Trunk Sanitary Sewer Trunk Force Main and Lift
Station Construction and Reimbursement Agreement (~Agreement") between the City of Corpus
Christi ("City"), A Texas Home-Rule Municipal Corporation, P.O. Box 9277, Corpus Christi, Texas
78469-9277 and Hogan Development Company, L.P., ("Developer"), a Texas Domestic Limited
Partnership, 801 N. Shoreline Drive, Suite 350 South, Corpus Christi, Texas 78401, that was executed
on February 17, 2004 and amended on August 12, 2004.
A. Section 2.a.(2). of the first Amendment to the Agreement is revised to read as follows:
"(2) SANITARY SEWER TRUNK FORCE MAIN
"(a) Install approximately 4,950 linear feet of 12-inch sanitary sewer trunk line and 4,565 linear feet of
16-inch sanitary sewer trunk line.
"(b) The 12-inch force main will begin at the new Lift Station #11, described in Section 2.a(1) of this
agreement and ex'tend west along Wooldddge Road for approximately 4,950 linear feet to a point on
the east side of Rodd Field Road. The 12-inch force main will be increased in size to a 16-inch force
main and will continue from said point on the east side of Rodd Field Road approximately 4,585 linear
feet and end at the Wooldndge Road Lift Station #2. The size of the force main will be dictated by 30
TAC Chapters 290 and 317.
"(c) The plans and specifications for the Lift Station must comply with 30 TAC Chapters 290 and 317."
B. Section 6 of the first Amendment to the Agreement is revised as follows:
~6. REIMBURSEMENT
"a. The City will reimburse the Developer 100% of the reasonable cost, but not to exceed $1,402,860,
of the Sanitary Sewer Trunk Force Main and Lift Station #11 within 30 days of invoicing by the
Developer, if the work has been completed and has been inspected and accepted by the City. The
City agrees to conduct pededic inspections of the progress of the work at key points dudng the
construction.
1. The City will reimburse the Developer for the construction cost of the Master Lift Station #11
and the 4,950 linear feet of 12-inch force main completed to the temporary tie In at the
manhole located east of Rodd Field Road within 30 days of invoicing by the Developer, if
the work has been completed, inspected, and accepted by the City pdor to the construction
and acceptance of the complete project as described in Section 2(a)(1) and 2(a)(2).
"e. By Amendment No.2, the City will reimburse the Developer 100% of the reasonable cost, but not to
exceed $319,360 that consists of the following:
1. Construction cost to increase the size of the 12-inch force main to a 16-inch from just east
of R,3rld Fi~l~l I~r~H tO Lift Station No.2 on Wooldddge Road, 4,565 linear feet;
2005-225
05/10/05 Page 1 of 3
M2005-140
Hogan Development Company
2. Additional costs for plan revisions due to the increased size of the Force Main and for
extending to the Lift Station No, 2.
3. Cost of a pipe section to provide for a wye connection to the new additional 12-inch Force
Main to the Greenfields by the Bay Lift Station."
C. Exhibit 2 is amended by substituting a revised Section V11, Project Probable Construction Cost,
which is attached to and incorporated into this amendment to the Agreement, for the Section VII of
Exhibit 2 that was attached to and incorporated into the Agreement.
D. This Amendment No. 2 to the Agreement shall become effective and shall be binding upon and
shall insure to the benefit of the parties hereto and their respective heirs, successors, and assigns
from and after the date of execution.
Page 2 of 3
EXECUTED IN TRIPLICATE originals, this day of
DEVELOPER: Hogan Development Company, L.P.
,2005
By:
Neill F. Amsler, III
Manager, Seabreeze, Ltd. Co.
Its General Partner
THE STATE OF TEXAS
COUNTY OF NUECES
This instrument was acknowledged before me on the 5 ~ day of ~!d;~1
2005, by Neill F. Amsler, III, Manager, Seabreeze, Ltd. Co., a Texas limitedbilitC'lia company,
acting as General Partner of Hogan Development Company, L. P., a Texas domestic limited
partnership, on behalf of the partnership,
Notary Cu'blic, State of Texas
ATTEST:
Armand~
City Secretary
APPROVED: ~'"(~ day of ,/~(¢~¢-
City Attorney
THE STATE OF TEXAS
CITY
,2005
CORPUS CHRISTI
eorge K. Noe
Manager
~f (~UIIiCiL ..___
COUNTY OF NUECES
This instrument was acknowledged before me on
by George K. Noe, City Manager, City of Corpus Christi, Texas/~ Texas
Notary
Public,
State
of
Texas
AI.~fHO~IZL~
home rule municipal
Page 3 of 3
REVISED ESTIMATE FOR MASTER PLAN LIFT STATION NO. 11 AND FORCE MAIN EAST OF RODD FIELD
RD AND SOUTH OF HOLLY RD. Job No. 38072.00.00
hem Description I Quantity + Unit
ORIGINAL CONTRACT SECTION 'A'
i1 0tos,^45+25
Tie to Exist. Manhole and Rehab. 1
2.o siteR pa T c
3 Dewatering/S WP 3/Misc. ~ 1
5 Comb/Air Release Valve 13, i E~
(As manuf. By ARi or app__roved equal)
~112" DJ. 45 De~ree M.J. ~3~nds 18
71OSHA Trench PrOtectiOn 3,585 LF~
Unit Price I Tolml Amount
5/4/2005
$7,500.00 t-- -- $7,500.00
$30,000 00 I $30,000.00
5;6,000.00 [ $6,000.00
$42.00 I $139,146.00
$5,400.00
$6oo.oo ' 81o,800.00
$2.00 I $7,170.00
~9 Open ~ut Case McChan - ~i i07 ~ $12070~_ I $12,840.00
10~and Case Rodd Field 140 ~ $400.00 $56,000.00
~ i $285,056.00
] SUB-TOTAL SECTION A~
A (REVISED) ITEMS STA 0+00 TO STA 45+25~ I
~Revised Contract to Change Force Main from 12" to I~" and Extend from
_l~Ai STA 11+00 to Wooldridge Lift Station STA 0+0~
~ncased ~way B~rr~ i 7 I L.~ $30,000.00
3~ SWP3/Tmffic Con~-ol -' 1 EA[ $10,000.00
4] 16" PVC b~ 18 C-90~ '
4565 LF ',
5',Comb. Air/ReleaseValve ' EA I
7 16 x 12 D I Red-ucer ~ 1 ] EA~
8[16" Gal~Valve- EA I
$69.00
$2,500.00
OSHA Trench Safety
10 5' Dia. MH
1
4565
, 4
$1,000.00
$900.00
$4,300.00
LF ] $2.00
EA $3,400.00
11 MC Channel 3,0" Case Open Cut ] 120 LF [ $147.00
12 r~dei~ld30' Bore&Ca~se ~ 226 ~ LF7 $690.00
13 16xl6xl2W~yeP401Lined ~ I EA ] $1,825.00
14 16~ Res~'aint i ~ ~ $460.00
15 12' Plug 1 ~ EA $270.00
16i12" Megalug ~ ~ i EA I $100.00
17iThrust Block ~1 } ~'i~} $406.00
i I
S T'0Si
~[S¢nqUERNG cUARGE~Tdm~VlSE ~LAS~ ~ ~
TA l l~ TO STA 45+2~ A~D ADD 16" FM ~0 STA 0+0~0
~D1FFERENCE~ BETWEEN ORIGINAL & REVISED SECrTION A
I REVISED ESTIMATE OF PROJECT PROBABLE CON,ST. COST
REVISED TOTAL; = q
I
COST ESTIMATE
Current Terminus
$11,000.00
$30,000.00
$10,000.00
$314,985.00
$10,000.00
$22,000.00
$4,300.00
$9,130.00
$13,600.00
$17,640.00
$151,800.0~
$1,825.00
$460.00
$270.00
$100.00
$406.00
$598,416.00
$6,000.00
$604,416.00
$319,360.00
$1,083,500.00
$319,360.00
$1,402,860.00
Exhibit 2
Page I of 1