HomeMy WebLinkAboutM1986-0235 - 05/20/1986• Motions - 5/20/86 • 4. Approving the following actions on the IH -37 Utility Adjustments, Phase A project: a. Change Order No. 5 in the amount of $30,656.36 be approved which reconciles final unit bid item quantities, authorizes hydromulch seeding of property where easements were acquired, and authorizes payment of $12,074 as settlement of two claims submitted by the contractor for extra work. b. The project be accepted and final payment of $100,708.33 be authorized to Claude Chapman Construction Co., Inc. The total cost of this project, which provided for the relocation of 12" and 36" water lines crossing IH -37 near Sharpsburg Road to clear future interstate highway construction, is $841,834.11. The cost of the work is reimbursable by the State of Texas. M86 -0235