Loading...
HomeMy WebLinkAboutM1986-0324 - 07/01/1986• Motions - 7/1/86 • 8. Accepting the Ocean Drive Sidewalk /Bikeway project and authorizing final payment of $11,466.35 to A. Ortiz Construction and Paving, Inc. Approxi- mately 2,300 linear feet of 7 -foot wide sidewalk was constructed along Ocean Drive from the Holiday Inn entrance at Buford Street to the north end of Cole Park. The project also included the planting of 31 new palm trees, the installation of a small irrigation system, and the construction of a timber railing. The total cost of the work performed, which is being funded by Park and Street Bond Funds, is $94,949.45. M86 -0324