HomeMy WebLinkAboutC2006-267 - 7/18/2006 - Approved CHANGE ORDER Department of Engineering Services City of Corpus Christi, Texas CHANGE ORDER NO: PROJECT NO. 8416 CONTRACT TIME: 180 C.D. Operating Department: lJater DATE: July 10, 2006 Name of Project: Rincon Bayou Diversion Project Intake Pump Station, Diversion Pipeline And Discharge Structure Hondo Creek Bridge Replacement Contractor:~amo~_!ndust:.ri~~ Inc. CHANGE ADD DEDUCT DEJ)UCT 1) Credit for not providing Field Office as required of the specifications 2) Credit for not providing project photography for the first three months of the project as required by the specifications. ($12,000.00) ($1,200.00) ADD 3) Modifications to the Electrical Building 4) Delete Meter Vault and 60" Ultrasonic Meter Replace with 3-36" Magnetic Meters. Provide pressure transmitters and Puap/Valve control programmable logic controllers (PLCs). $38,412.00 $52,731.00 TOTAL ADD AND DEDUCT TOTAL NET CHANGE (DEDUCT) 91,143.00 (13,200.00) 77,943.00 Why was this change necessary? (If left off the plans and specifications, explain why) 1) Contractor did not provide the construction project office as required of the specifications 2) Contractor has not taken the monthly project progress photographs as required of the specifications. 3) City staff have reviewed this facility and determined that a fully enclosed structure would provide greater protection from the elements and a more secure facility than the open alr roofed facility presently in the contract. 4) City problems ~..: ., staf f expressed concern about the potential for the vault flooding and with maintaining the meter in the below ground vault. The above grade meters ~he pressure transmitters and PLCs were inadvertently left 2006-267 07/18/06 \12006-221 Ramos I ndustrie, ~-,..,""ifIiIJ' off the plans and not included in an Addendum. How can similar changes be avolded In the future? 1 and 2) Be more aggressive in enforcing all contract provisions. 3 and 4) Closer coordination with operating department personnel as to their desires and preferences. Closer attention to all control details. A. CONTRACT PRICE. . . . B . TOTAL CHANGE ORDER C. NEW COBTRACT PRICE D. THIS CHANGE ORDER. (inc. current) $ 7,223,581.00 L 77 I 943 .00 ~~.'?~,301, 524.00 ~_ 7_2L943 . 00 -P$/ E. PERCBNT TOTAL CHANGE (B/A) ..... . . . 1.08% F. PREVIOUS ADDN' L TIME AUTHORIZED, . . 0 C. D. -..-.-..-.-- G. ADDN'L CONTRACT TIME THIS CHANGE ORDER 48 C.D. ----_._-~ H. TOTAL ADDITIONAL TIME........ 48 C.D. Project Engineer CITY OF CORPUS CHRISTI, TEXAS By u~~R f;;4-4'"", -W"'~ ~ineer ~) --) CONT~CTOR ~I By: ~ v{..~~ ?~,// Title: APPROVZD: Ope:raL~.i"'~ DcJ:'a..L L.w.c,II.L 7c Jl . 7/('.il a, rIJ' ~1Il~ ::0 ~ Director of Manag......nt " Budget . ~P~U0 lbAuL Legal Department 't" 't( ti't' .n:lza~~L AU IHllkll.t' "/lk{C'/- BY OOU,.C&t .__..fl.L_. _.:L ..... ..........t.1:L: SECIETA~ if..- Git} 11Q,...&g,~'4I'iiiiir ,. ~._~ ?1 i'/ . J:'_ City Secretary 'I I.f /0 '- e"'" t- i I).?~'(I. .jtrr _.v,j" ~,.-