HomeMy WebLinkAboutC2006-485 - 10/31/2006 - Approved CHANGE ORDER Department of Engineering Senices City of Corpus Christi, Texas CHANGE ORDER NO~ PROJECT NO: 7302 CONTRACT TIME: 360 C.D. Operating Department: Was1ewater Department DATE: October 24,2006 Name of Project: Antelope & 'lalt Flats\rea 36"'48" Wastewater Gravity Line Contractor: George ConstructIon, Inc. CHANGE ADD DEDUCT See <\ttached Wh) was this change necessary" (If left off the plans and specifications, explain why) On Doddridge.. recent cleaning and televising revealed a section of 8" sanitary sewer that has the potential for munedlate failure. At the Howard Street bore, obstructions were encountered that required extra work for removal. How can similar changes be avoided in the future? ! Jnav01dable Neither of the aforesaid circumstances could have been seen or anticipated in advance. A. CONTRACT PRICE........."............... ........... ........................ $ B. TOTAL CHANGE ORDER (inc. current) ........................... $ C NEW CONTRACT PRICE .................................................. $ D. THIS CHANGE ORDER ...................................................... $ E. PERCENT TOTAL CHANGE (BfA) ................................... F. PREVIOUS ADDN'L TIME AUTHORIZED ...................... G. ADDN'L CONTRACT TIME THIS CHA.""IGE ORDER.... H. rOTAL ADDITIO!\AL TIME ................. . "..................... 8.614.720.50 1.567 934.45 10.182.654.95 122.126.38 18.20% 180 C.D. 15 C.D. 195 C.D. CITY OF/"CORPUS CHRISTI. TEXAS By 1;4? ~- , City Engineer I /~/.zi4b ~N~ By, ') -,. i Title: '- c;"... J. f .\PPROVED: \/tj.~t"l- /~It.. '...1/ / (;/26:< It-toperating Department 4- I htJ4'vtl'- ~caPital Budget Officer ~ . kfi~ r~ -'--7"y-- -.L.;;.. " ,.. C/ lM-\""D('~--- .... ..-.--. "'Y S,c~ 'T4.r'{ j A 11JDro...'b5L... ~Ulh\J".~ " .....~.- Sfctir~ A TTF~I 2006-485 10/31/06 "12006-351 George ("onstruction ADD DEDUCT .\. Add the following bid items to the contract: Doddridge Point Repair C 1. Mobilization - 1 L.S. @ $10.000.00 L.S C2 Traffic Control 1 [ S. ill $lS.000/LS G3. Controlling Ground Water [ LS @ $16,000.0(I/L.S G4. Remove & Dispose ()fFxisting 8" Plpe ~- 2' L.F @ $350.001 o.F. G5. 8" PVC Samtary Se\ver 23 LF. @ $382.00/1 F G6. 8" Sanitary Sewer Connectiom- 2 ea. ?i2 $3S00.00 each G 7 Cement Stahilized Backfill - 1 L.S @ $S.200.00/L.S G8. Trench Safety -- 23 1 F. @ $12.00/L F. G9. Asphalt Pavement Repair ~ 1 L.S @ $12,000/L.S. G 1 n. SWPPP 1 LS. @ S 1 ,SOO.OO/L.S. 12,000.00 $ ] 0,000.00 15,000.00 16,000.00 8,050.00 8,786.00 7,000.00 5,200.00 276.00 1,500.00 B. Total Part G Add the following bid item to the contract: C 16. Bore Obstruction Removal ~ ] L.S @ $3~,3] 4.38!L.S 38,314.38 $83.812.00 TOT AL ADD $122.126.38 I .PROJECT DA'j A CORPUS12005 PROJ ECTS A05C28-00 (Cl City of Corpus Chnsti - Antelope Street and Salt Flats WGIL\05-CONTRACTS \.. G!o\"GE ORDERS\2006 in =4 Chang. Order !l,tta:hd{'l