HomeMy WebLinkAboutM1986-0371 - 08/19/1986Motions - 8/19/86 0 8. Approving the following actions on the Saratoga /Weber Public Safety Building: a. The contractor be granted a 27 day time extension to supplement 120 working days allotted for the project due to material delivery delays beyond the contractor's control. b. The project be accepted and final payment of $26,355.70 be authorized to the contractor, Hunt Construction Company, Inc. The total construction cost of this 1982 Bond project is $263,557. M86 -0371