HomeMy WebLinkAboutM1986-0421 - 10/07/1986• Motions - 10/7/86 • 2. Approving the following actions on the Oso Trunk Sewer Main Sliplining, Phase I project: a. The contractor be granted a 45 -day time extension. b. $25,000 be withheld from remaining funds due the contractor pending resolution of a damage claim by Southwestern Bell Telephone Company along the route of the work. C. Payment of remaining funds in the amount of $153,106.12 be authorized to Channel Construction Co., Inc. d. An interim, but not final, acceptance of the project be made. The total cost of the work performed by Channel Construction Company is $1,733,973.70. M86 -0421