2. Approving the following actions on the Horne Road and Water Street
Sanitary Sewer Sludge Removal project:
a. Payment of $46,824.52, which represents previously earned
retainage and settlement of claims on this project, be authorized
to John G. Holland Construction and Shur -Flo, Inc., dba
Slipliners.
b. The contract between this firm and the City be terminated by
mutual consent prior to completion.
The total cost of the work performed. by the contractor, including
claim settlement, is $108,223.60 .
M86 -0430