HomeMy WebLinkAboutC2008-245 - 7/29/2008 - ApprovedCHANGE ORDER
Department of Engineering Services
City of Corpus Christi, Texas
CHANGE ORDER NO: 17 PROJECT NO: 2243 CONTRACT TIME: 625 C.D.
Operating Department: Engineering Services DATE: July 1, 2008
Name of Project: Lindale/Chenoweth Subdivision Area Drainage Improvements, Ph. 1, Pt. B
Contractor: SLC Construction, L.P.
CHANGE ADD DEDUCT
SEE ATTACHED
Why was this change necessary? (If left off the plans and specifications, explain why)
Multiple breaks on a very old 6-inch water line on Winnebago between Cazancahua and Upper Broadway makes
replacement of the line an urgent priority.
How can similar changes be avoided in the future?
Unavoidable
A. CONTRACT PRICE ............................................................... $ 11.300.441.39
B. TOTAL CHANGE ORDER (inc. current) ........................... $ 842.328.96
C. NEW CONTRACT PRICE .................................................... $ ]2.142,770.35
D. THIS CHANGE ORDER ....................................................... $ 91.270.00
E. PERCENT TOTAL. CHANGE (B/A) .................................... 7.45% Pro ct Engineer
F. PREVIOUS ADDN'L TIME AUTHORIZED ...................... 75 C.D.
G. ADDN'L CONTRTACT TIME THIS CHANGE ORDER. -0-
H. TOTAL ADDITIbNAL TIME .............................................. 75 C.D.
CITY OF CORPUS HRISTI, TEXAS
By: ~~~ ~~~~~ ~
City Engineer
n
ATTEST. --'~
ARMgrypO CHAPp
Ea.~cL3cc.5 cnysEC~FraR~
CONTRACTOR
By: ~,~,..:,.~.,~In. ~ . C~c-
Title: ~~' ~-~-
Operating Department /~,~ ~ ~(~
Capital Budget Officer f-"~•' ~..~~~/AUIIiUHI[L~
Legal Department 61 COUNCIL „,_f~~~~C~ 'Q
2008245 ---~-TTT•"""•"'..
07/29/08 SECR-TARv
M2008~195
SLC Construction
ADD DEDUCT
A. Add the following bid items to the contract:
R-1. 8" Waterline, C-900-
375 L.F.@$88.00/L.F. $ 33,000.00
R-2. 6" Tapping Sleeve and Valve -
1 ea @ $4,500.00/ea. 4,500.00
R-3. 8" Tapping Sleeve and Valve -
1 ea @ $6,000.00/ea. 6,000.00
R-4. 8" x 6' Tee -
1 ea @ $750.00/ea 750.00
R-5. 6" Waterline - C-900 -
20 L.F. @$82.00/L.F.. 1,640.00
R-6. 2" Service Connection -
2 ea @ $1,500.00/ea 3,000.00
R-7. 6" Service Connection -
1 Ea. @ $1,500.00/Ea. 1,500.00
R-8. Sawcut Pavement -
810 L.F. @ $8.00/L.F. 6,480.00
R-9. Remove and Replace Sidewalk -
50 L.F. @$28.00/L.F. 1,400.00
R-10. Remove and Replace Curb & Gutter -
100 L.F. @ $35.00/L.F. 3,500.00
R-11. Traffic Control -
1 L.S. @ $3,500.00/L.S. 3,500.00
R-12. SWPPP -
1 L.S. @ $1,000.00/L.S. 1,000.00
R-13. Mobilization-
1 L.S. @ $5,000.00/L.S. 5,000.00
R-14 Repair Asphalt Pavement -
250 S.Y@ $80.00/S.Y 20,000.00
TOTAL ADD $91,270.00
P:\2003 GEM03054-01 (C) City of C C-Lindale Subdivision-Design Phase\OS-CONTRACTS & CHANGE ORDERS\2008 07 01 Change
Older Nl7 Attach.doc
Department of Engineering Services
Change Order Summary Sheet
July 29, 2008
PROJECT: Lindale/Chenoweth Subdivision Drainage Area Improvements, Phase 1 -Part B
Project No: 2243
APPROVED: City Council on 10/31/06 Motion No. M2006-355
CONTRACTOR: SLC Construction, L. P.
P.O. Box 639
Conroe, TX 77305
TOTAL CONTRACT AMOUNT ...........................
25% Limit Amount .......................................
Change Order No. 1 (Council, 4/10/07) ..........,
Change Order No. 2 (4/11/07) .......................
Change Order No. 3 (5/21/07) .......................
Change Order No. 4 (6/12/07) .......................
Change Order No. 5 (6/22/07) .......................
Change Order No. 6 (7/5/07) .........................
Change Order No. 7 (9/18/07) .......................
Change Order No. 8 (10/16/07) .....................
Change Order No. 9 (Council, 12/11/07) .........
Change Order No. 10 (12/3/07) .....................
Change Order No. 11 (1/8/08) .......................
Change Order No. 12 (2/4/08) .......................
Change Order No. 13 (4/3/08) .......................
Change Order No. 14 (4/22/08) .....................
Change Order No. 15 (5/14/08) .....................
Change Order No. 16 (6/24/08) .....................
Change Order No. 17 (7/1/08) .......................
Total ...........................................................
$11, 300,441.39
2,825,110.34
261,300.02
11, 500.00
23,625.00
24,900.00
24,900.00
16,971.05
21,750.00
24,340.00
192,173.86
12,743.00
18, 351.16
21,396.00
24,736.37
24,699.60
24,912.90
22,760.00
91,270.00
842,328.96= 7.45% < 25%