9. Approving the following actions on the Everhart - Wooldridge
Intersection and Crestmont Entrance Improvement project:
a. The project be accepted and final payment of $8,413.17 be
authorized to the contractor, A. Ortiz Construction and Paving,
Inc.
b. The contractor be granted a 23 -day time extension to supplement
the 40 working days allotted for the project due to utility
relocation delays beyond the contractor's control and additional
work added to the contract by change order.
The total construction cost of this project is $842131.65.