HomeMy WebLinkAboutM1986-0452 - 10/28/1986• Motions - 10/28/86 • 9. Approving the following actions on the Everhart - Wooldridge Intersection and Crestmont Entrance Improvement project: a. The project be accepted and final payment of $8,413.17 be authorized to the contractor, A. Ortiz Construction and Paving, Inc. b. The contractor be granted a 23 -day time extension to supplement the 40 working days allotted for the project due to utility relocation delays beyond the contractor's control and additional work added to the contract by change order. The total construction cost of this project is $842131.65. M86 -0452