HomeMy WebLinkAboutC2008-465 - 12/16/2008 - ApprovedCHANGE ORDER
Department of Engineering Services
City of Corpus Christi, Texas
CHANGE ORDER NO: 6 FUNDING SOURCE: CONTRACT TIME: 640 C.D.
Operating Department: Bond 2004 DATE: December 1, 2008
Name of Project: Everhart Road, Phase 1 (Saratoga Blvd. to Cedar Pass Drive) P.R. 6263
Contractor: SLC Construction. L.P.
CHANGE ADD DEDUCT
Whataburger Way Drainage Improvements $139,909.04
Project No. 2294 - (See Attached Sheet)
TOTAL NET: $139,909.04
Why was this change necessary? (If left off the plans and specifications, explain why?
Poor storm water drainage found during a topographic survey and T.V.I. conducted by Freese and Nichols, Inc.
How can similar changes be avoided in the future?
Unavoidable.
A. CONTRACT PRICE $ 7,454,229.87
B. TOTAL CHANGE ORDERS (inc. current) $ 217,952.70
C. NEW CONTRACT PRICE $ 7,672,182.57 -7L
D. THIS CHANGE ORDER 139,909.04 Project Manager
E. PERCENT TOTAL CHANGE (B/A) 2.92%
F. PREVIOUS TIME AUTHORIZED 0 C.D.
G. ADDN'L CONTRACT TIME THIS CHANGE ORDER 0 C.D.
H. TOTAL ADDITIONAL TIME 0 C.D.
CITY OF C/O~,RnFU H STI, TEXAS CONTRACTOR
Director of En me i g 'ervices
/g~\1 lZ/(p Ug Title: ~~ ~~C
APPROVF,D• W O~er mg Department
i -~,../
2008-465 (p~~ I9Ir, of Management & Budget ~~ 71~0~-333 AUTHURttb
12/16/08 t -'t"' ~ ~ "~"'~„'..........
M2008-333 ~' Legal Department ~ ~tlFt;iL „„~°~,~ ~?.~~~
'.LC Construction ~~
'~MSE AETARV ~~•
. __=dam-"
MANDO CHAPA
SLC Construction, LP
P O Box 639
Conroe, Texas 77305
EXTRA WORK ORDER
P (936) 441-8088
F (936) 441-8098
Project Name:
Owner:
Whataburger Way
City of Corpus Christi
Description : Drainage Date: 20-Nov-08
Description Quantity Unit Unit
Cost Total
Cost
Remove Existin Concrete Sidewalk 545 SF $ 3.50 $ 1,907.50
Remove Existin Concrete Island 51 SF $ 3.50 $ 178.50
Remove Existin Concrete C&G 140 LF $ 5.18 $ 725.20
Remove Existin Curb Inlet 3 Each $ 560.00 $ 1,680.00
Remove Exiin RC Pie 85 LF $ 20.30 $ 1,725.50
18" Dia RCP Class III 72 LF $ 87.73 $ 6,316.80
24" Dia RCP Class III 10 LF $ 121.54 $ 1,215.43
30" Dia RCP Class III 376 LF $ 139.70 $ 52,525.57
18" Dia Concrete Plu 2 Each $ 2,345.00 $ 4,690.00
5' Standard Curb Inlet 3 Each $ 4,200.00 $ 12,600.00
6' Standard Curb Inlet 1 Each $ 4,900.00 $ 4,900.00
5' Inlet Extension 1 Each $ 1,750.00 $ 1,750.00
6' Dia Concrete Storm Water MH T e A 1 Each $ 5,600.00 $ 5,600.00
Concrete Storm Water MH T e B 1 Each $ 6,300.00 $ 6,300.00
Sediment Control Fence for SWPPP 160 LF $ 2.80 $ 448.00
5' C&G & Pavement Re air 140 LF $ 30.80 $ 4,312.00
4" Concrete Sidewalk 375 SF $ 8.40 $ 3,150.00
Concrete Curb Ram 165 SF $ 9.80 $ 1,617.00
Concrete Traffic Island 51 SF $ 12.60 $ 642.60
As halt Pavement Re air T e 1 301 SY $ 33.88 $ 10,197.88
As halt Pavement Re air T e 2 27 SY $ 50.68 $ 1,368.36
Block Soddin in Disturbed Areas 71 SY $ 7.70 $ 546.70
Television Ins ection of Enclosed SW Conduit 458 LF $ 9.80 $ 4,488.40
Trench Safe for RCP 458 LF $ 4.20 $ 1,923.60
Excavation Safe for Storm Water MH 2 Each $ 1,050.00 $ 2,100.00
Traffic Control 1 LS $ 7,000.00 $ 7,000.00
TOTAL $ 739,909.04
- --E-xcludess-Bor~Goncrete in-trench, - - - - --
Striping, New Casing
Schmitt-City of Corpus Christi