HomeMy WebLinkAboutC2008-466 - 12/16/2008 - ApprovedCHANGE ORDER
Department of Engineering Services
City of Corpus Christi, Texas
CHANGE ORDER NO: 5 FUNDING SOURCE: CONTRACT TIME: 364 C.D.
Operating Department: Bond 2004 DATE: November 4, 2008
Name of Project: Greenwood Drive Phase 1 from Gollihar to SPID -Project No. 6277
.Contractor: Salinas Construction Technologies Ltd.
CHANGE AS FOLLOWS: ADD DEDUCT
1. Additional Sidewalks, Driveways, and Curb & Gutter for $186,166.42
Phases 1, 2, 3, 5, & 6.
Why was this change necessary? (If left off the plans and specifications, explain why)
Proiect was originally reviewed by TDLR and accepted before construction commenced. The City has
implemented new ADA initiatives which exceed minimum ADA requirements and these changes provide
improvements for all of the sidewalks and drivewavs which do not comply with current standards.
How can similar changes be avoided in the future? N/A
A. CONTRACT PRICE .............................................. $3,787,013.79 ~
B. TOTAL CHANGE ORDER (inc. current) .................... $281,138.11 ~
C. NEW CONTRACT PRICE ...................................... $4,068,151.90 /
D. THIS CHANGE ORDER ........................................ $186,166.42 / ~.. ,E
E. PERCENT TOTAL CHANGE (B/A) .......................... 7.42% / Project E near
F. PREVIOUS ADDN'L TIME AUTHORIZED .................. 61
G. ADDN'L CONTRACT TIME THIS CHANGE ORDER .... 80 ~ ~~~' T EYG
H. TOTAL ADDITIONAL TIME ..................................... 141 ~
CITY O~ PU CHRISTI, TEXAS
By: ~os~a~"
City Engi ear ,
APPROVED:
CONTRACTOR
By: ,~
Title: /~/
Operating Department
Director of Management & Budget
/~egal Department
KiTE31?
ANiIAANDOCHAPA ~{'°
_. il:~r.hf;i
2008-466
12/16/08
M2008-332
Salinas Constr. Technologies
dl~g ~:AUTHORIGt~
RT CatlRCIL....I..~~l~•'b~
SEC fTARY ~1~
11/4/08 CHANGE ORDER Ifs COST BREAK DOWN
(City Project No. 5277)
GREENWOOD DRNE IMPROVEMENTS -PHASES 1, 2, 3, 5, 8 6
ADDITIONAL DRNEWAY, AND CURB AND GUTTER QUANTITIES
Phase 1 (West side from NPID to Trojan) Addkional
Bid Item Description Quantity Unit Price Subtotal
H15 Unanticipated Concrete Driveway 4,020 SF $7.66 $30,793.20
C11 Unanticipated Concrete Driveway removal 4,020 SF $4.62 $18,572.40
H12 Unanticipated Concrete Sidewalk
C8 Unanticipated Concrete Sidewalk removal
2,602 SF $4.94 $12,853.88
2,602 SF $2.09 $5,438.18
H13 Unanticipated Concrete Curb and Gutter 283 LF $16.08 $4,550.64
C9 Unanticipated Concrete Curb and Gutter removal 283 LF $6.94 $1,964.02
Total Cost for Phase 2 $74,172.32
Phase 2 (East side from NPID to Trojan) Addkional
Bid Item Description Quantity Unk Price Subtotal
H15 Unanticipated Concrete Driveway 0 SF $7.66 $0.00
C11 Unanticipated Concrete Driveway removal 0 SF $4.62 $0.00
H12 Unanticipated Concrete Sidewalk 2,178 SF $4.94 $10,759.32
C8 Unanticipated Concrete Sidewalk removal 2,178 SF $2.09 $4,552.02
H13 Unanticipated Concrete Curb and Gutter 0 LF $16.08 $0.00
C9 Unanticipated Concrete Curb and Gutter removal 0 LF $6.94 $0.00
Sidewalk Drain at (STA 15+75 approximately) $5,100.00
Shopping Center Driveway Storm Box Lid Rebuild $2,100.00
Total Cost for Phase 2 $22,511.34
Phase 3 (West side from Trojan to West Point) Additional
Bid Item Description Quantity Unk Price Subtotal
H15 Unanticipated Concrete Driveway 1,375 SF $7.66 $10,532.50
C11 Unanticipated Concrete Driveway removal 1,375 SF $4.62 $6,352.50
H12 Unanticipated Concrete Sidewalk 1,120 SF $4.94 $5,532.80
C8 Unanticipated Concrete Sidewalk removal 1,120 SF $2.09 $2,340.80
H13 Unanticipated Concrete Curb and Gutter 25 LF $16.08 $402.00
C9 Unanticipated Concrete Curb and Gutter removal 25 LF $6.94 $173.50
- - $25,334.10
Phase 5 (East side from Trojan to West Point) Addkional
Bid Item Description Quantky Unit Price Subtotal
H15 Unanticipated Concrete Driveway 0 SF $7.66 $0.00
C11 Unanticipated Concrete Driveway removal 0 SF $4.62 $0.00
H12 Unanticipated Concrete Sidewalk 2,092 SF $4.94 $10,334.48
C8 Unanticipated Concrete Sidewalk removal 2,092 SF $2.09 $4,372.28
H13 Unanticipated Concrete Curb and Gutter 300 LF $16.08 $4,824.00
C9 Unanticipated Concrete Curb and Gutter removal 300 LF $6.94 $2,082.00
$21,612.76
Phase 6 (East side from West Point to Gollihar) Addkional
Bid Item Description Quantity Unk Price Subtotal
H15 Unanticipated Concrete Driveway 0 SF $7.66 $0.00
C11 Unanticipated Concrete Driveway removal 0 SF $4.62 $0.00
H12 Unanticipated Concrete Sidewalk 1,512 SF $4.94 $7,469.28
C8 Unanticipated Concrete Sidewalk removal 1,512 SF $2.09 $3,160.08
H13 Unanticipated Concrete Curb and Gutter 300 LF $16.08 $4,824.00
C9 Unanticipated Concrete Curb and Gutter removal 300 LF $6.94 $2,082.00
$17,535.38
Allowance for Subgrade Treatment under Commercial Driveways $25,000.00
Total Cost of work for phases 1, 2, 3, 5, 8 8.
5186.165.88
Notes:
1. These additional improvements will complete accessible routes meeting ADA requirements along both
sides of Greenwood Drive from NPID to Gollihar.
2. Fitty four cents was added to this Change Order to account for a math error in Change Order #4.
DEPARTMENT OF ENGINEERING SERVICES
CHANGE ORDER SUMMARY SHEET
December 9, 2008
PROJECT: Greenwood Drive, Phase 1 - Gollihar to SPID
Project No. 6277
APPROVED: City Council Motion No. M2008-054 on February 26, 2008
CONTRACTOR: Salinas Construction Technologies
3734 FM3006
Pleasanton, TX 78064
TOTAL CONTRACT AMOUNT .................... ........ $3,787,013.79
25°/G Limit Amount . .. .................................. ......... 946,753.45
Chan a Order No. 1 June 18, 2008 ............ ......... 21,757.11
Chan a Order No. 2 Au ust 12, 2008) ......... ......... 24,713.41
Chan a Order No. 3 Au ust 18, 2008 ......... ......... 24,500.00
Chan a Order No. 4 Se tember 22, 2008 ... ......... 24,001.17
Chan a Order No. 5 December 9, 2008 ...... ......... 186,166.42
TOTAL All Chan a Orders .......................... .......... $281,138.11 7.42% < 25°/D
H:\USERS2\HOME\VELMAP\GEN\STREET\62]] GREENWOOD DRIVE\CONSTRUCTION\CHANGEQRDER NO. SCHANGE ORDER SUMMARY