HomeMy WebLinkAboutC2008-509 - 11/11/2008 - NACHANGE ORDER
(Page 1 of 2)
Department of Engineering Services
City of Corpus Christi, Texas
CHANGE ORDER No: 2 PROJECT No: 2281 CONTRACT TIME: 180
Operating Department: Storm Water Deaarhnent Date: November 6, 2008
Name of Project: Rolled Curb & Gutter Replacement FY 2007-2008
Contractor: A. Ortiz Construction & Paving Inc.
CONTRACT ITEM
A-5 (New)
A-6 (New)
CHANGE
ADD
200 Square Yards of Limestone @ $44.50/SY ..................................... $8,900
Manhole Adjustment -One each @ ................................................... $1,200
TOTAL THIS CHANGE ORDER ................................................ $10,100
Why was this change necessary? (If left offthe plans and specifications, explain why)
1. Base work due to raising of C & G and Portion of Road required additional limestone to provide adequate drainage to
nearest inlet. 2. The Contractor is being Riven additional days for added work. In accordance with General Provision B-7-8,
the contractor is also being given 30 calendar days due to weather delays over and above those anticipated by NOAA. See
contractors letter dated November 3.2008.
How can similar changes be avoided in the future?
A. CONTRACT PRICE ........... ......... . $ 431,300
B. TOTAL CHANGE ORDER (include current) ....... . $ 33,407
C. NEW CONTRACT PRICE . . ............... . $ 464,707
D. THIS CHANGE ORDER ............. .. ... . $ 10,100
E. PERCENT TOTAL CHANGE (B/A) ... ........ . . $ 7.7%
F. PREVIOUS ADDN'L TIME AUTHORIZED ....... . $ 30
G. ADDN'L CONTRACT TIME THIS CHANGE ORDER . . $ 30
H. TOTAL ADDITIONAL TIME ....... ........ . $ 60
CITY~G~ CORPUS RISTI, TEXAS
By: ~/'L/ I / r
City Engmeer
PROJECT
APPROVED:
/b
~r1,~/r`ts p. ~ .
~~~,/pq
Operat' De artment
Director of Management and Budget
Legal Department
/~ I 'n City Manager
/ V pT City Secretary
2008-509
11/11/08
A. Ortiz Constr. & Paving
NUV-b4-Lbb2S~lUt) by~bb
l/`'I~/CGNSi•9G
` o
<" •~Cy
x
'1YING ~
A.brtiz l;onstructionis+'aving lnc (rAX):itilt3t3341t3t3 F'.d(71/b191
A. Ortiz Construction & Paving Inc.
I o2 Airpon Rd
. Corpus Christi,'17C 7N4D5.
367-$$2-2122 Ofricc. 361-R7C3d 18R Fax.
November 3, 2008
City of Corpus Christi
L'•ngirtcering Services
PO 13ox 9277
Carpus Christi, TX
C/o Sylvia Arriaga
Via Facsimile: 361-880-3501
Subjcct:l2Glled Curb & Gutter Replacement FY 2007-2008 / Project No- 2281
Dear Ms. Arriaga,
We would like to request a 30 day (working day) extension on Project # 22$1. We aze
requesting this extension due to the fact that we were unable to work for approximately
22 days due to the rain.
if you have any questions, you may contact me at 361-882-2122
Thank you, for your time and attention to this matter.