CONTRACT FOR ARCHITECTURAUENGINEERING SERVICES
The City of Corpus Christi, a Texas Home Rule Municipal Corporation, P.O. Box 9277, Corpus Christi, Texas
78469-9277 (City) acting through its duly authorized Ciry Manager or Designee (Director of Engineering
Services) and Chiang, Patel, and Yerby, Inc., a Texas corporation, 1820 Regal Row, Suite 200, Dallas, Texas
75235, (ArchitecUEngineer-Consuhant), hereby agree to the amendment of the contract administratively
approved December 21, 2007 and amended by Motion 2008-005, January 8, 2008 and amended
administratively by amendment January 3, 2008 and administratively approved February 10, 2008 and
administratively approved March 24, 2008 October 14, 2008 and administratively amended November 20,
2008 is hereby agree to the amendment as follows
Section II. C.1 Basic Services, Construction Phase Services is amended to add the following:
• 4A Ongoing Construction Support Site Visits -Amendment No. 5 authorized services through October
31, 2008. Construction was to be complete on October 13, 2008. Completion of construction services
were required after this date and continue at this time. CP&Y requests additional fees to continue
providing until project estimated completion date of 12131/08. It is estimated site visits during this
period will be one site visit every other week at 12 hours per week.
• 4A Ongoing Construction Office Support -Office support services will be provided under this Task
and are assumed to continue with construction extending beyond 10/13/08. Office support services
will assumed to be completed by 12/31/08 and be provided 8 hours per week.
Section III Fees Authorized is amended to read:
II. FEES AUTHORIZED
The City will pay the Consultant a total not to exceed fee of $332,676.00. The fee consists of:
• An original contract fee not to exceed fee of $50,000.00;
• a fee for Amendment No. 1 services not to exceed fee of $147,000.00;
• a fee for Amendment No. 2 services not to exceed $20,500.00;
• a fee for Amendment No. 3 services not to exceed $49,730.00;
• a fee for Amendment No. 4 services not to exceed $31,046.00;
• a fee for Amendment No. 5 services not to exceed $20,000.00; and
• a fee for Amendment No. 6 services not to exceed $14,400.00.
Completion of design phase, bid phase and construction phase services are authorized by Amendment No. 1
as set forth in the original contract as amended. Consultant will be compensated for airfare, ground
transportation, lodging, and per diem meal expenses incurred due to out-of-town travel on a not to exceed
basis as set forth in the Summary of Fees. Travel will be will be documented by photocopies of receipts and
invoices. Per Diem will be at the GSA rate.
The table "Summary of Fees' shall be used when calculating the fee due for the proportion of services
completed. The City shall make prompt payments in response to Consultant's statements for Professional
Services.
Billing for services provided in Section II A, B, D, and E will be based on the Consultant's estimate of the
percent of services complete at the time of billing. The fee for additional services (Section II.E) is included as
part of the fee listed for Design, Bid and Construction phase services listed in the table "Summary of Fees'.
However, in no case will the billing exceed 90°/u of the fee for each phase until the delivery of documents
associated with each phase has been reviewed and accepted by the Ciry. Billing for services provided in
Section II.C.1 will be based on the amount of construction completed. Billing for services provided in Section
II.C.2 shall be payable upon delivery of the record drawings to the Ciry Engineer. Billing for services provided
in Section II.C will be payable upon pertormance of inspections and delivery of all materials to the City.
Survey work will be invoiced at the billing rate of the sub-consultant performing the survey without markup.
2009-029
01/23/09 V statements for work authorized by the City Engineer and performed by the
vlll be based upon Consultant's estimate and concurrence by the City of the
~biang, Patel &Yerby alenzuelaCe1154A48WEAmd6Contract.doc
proportion of the total services actually completed at the time of billing. The City will make prompt monthly
payments in response to Consultant's monthly invoices.
All invoices shall be accompanied by a cover letter summarizing the fee in accordance with the Summary
Schedule of Fees. Invoices will be sequentially numbered for each project and state the project name. The
letter shall state the number of the current invoice, the contract fee for each task, the amount previously
invoiced for each task, and the current amount due. Invoices will be organized to accommodate funding
sources. During the construction phase, the ArchitecUEngineer will also submit a brief letter/memo
summarizing observations during the site visit, the work of the contractor, construction progress forthe billing
period, and any pending items.
Summary of Fees:
Tasks Description Fee
Original Contract
Pre-design and Review Services
II.A Preliminary Design and Review 12,180.00
II.B Survey Update (Allowance) 10,000.00
II.C Travel 1,000.00
Pre-design Subtotal 23,180.00
Basic Services & Additional Services
11.6.1 Initial Design -Construction Document Phase 60% 26,820.00
Original Total Fee 50,000.00
Amendment No. 1 Authorized Services
11.6.2 Design -Construction Document Phase 100% 40,000.00
11.6.3 Bid Phase 5,000.00
Design/Bid Subtotal 45,000.00
Construction Services
II.C.1 Construction Phase 88,000.00
II.C.2 Record Drawings 5,000.00
Construction Service Subtotal 93,000.00
Post Construction Services
II.D Post Construction Phase 5,000.00
Post Construction Services Subtotal 5,000.00
Expense Allowance 4,000.00
Amendment No. 1 Fee 147,000.00
Amendment No. 2 Authorized Services
I.A.1.f. Surveying -Storm Water Pond for Disposal Cells 4A and 46 20,500
Amendment No. 2 Fee 20,500
Amendment No. 3 Authorized Services
I.A.1.f. Cell Construction Schedule and Storm Water Pond 1 18,858
I.A.2.k. Mass Excavation Cell 4A 18,968
I.A.2.1. Prepare Separate Bid Construction Documents for Cells 4A and 4B 11,904
Amendment No. 3 Fee 49,730
Amendment No. 4 Authorized Services
11.6.3 Bid Phase Services Cell 4B 3,712
II.C.1.m Construction Phase -Cell 4A and Cell 46 10,150
I IC.1.n Construction Phase -Surveying -Topographic 8 Documentation 4A & 4B 17,184
Page 2 of 3
H:\HOME\KEV INS\GEN\LANDFILL\ValenzuelaCells4A48W EAmd6Coniract.doc
Amendment No. 4 Fee 31,046
Amendment No. 5 Authorized Services
II.A Preliminary Design and Review 20,000
Amendment No. 5 Fee 20,000
Amendment No. 6 Authorized Services
II.C.1 4A Ongoing Construction Support Site Visits 7,680
4A Ongoing Construction Office Support 6,720
Amendment No. 6 Fee 14,400
TOTAL 332,676.00
XI. DISCLOSURE OF INTEREST
In compliance with City of Corpus Christi Ordinance No. 17112, Consultant agrees to complete the City of
Corpus Christi Disclosure of Interests form which is incorporated in the contract as Exhibit "C".
All other terms and conditions of the originally authorized, as amended, between the City and Consultant
shall remain in effect.
CITY OF CORPUS CHRISTI
By: ~~ 1.23°s
Oscar Martinez Date
Assistant City Manager
CHIANG ATEL AND YER Y, INC.
Authorized Representative D e
RECOM ENDED:
iv 9
PeteAnaya, P.E. Date
Director -Engineering Services
APPROVED AS TO FORM:
Assist nt City ttorney Date e
ATTEST:
~C
Armando Chapa Date
City Secretary
~~ 1 Jl3/~~
L-~SS~,4~N
Page 3 of 3
H:\HOM EVtE V I NS\GE N\LANDFILL\V a lenzue IaCeIIS4A48V~EAmd6Contract.doc
ctrY of coRPUS cltRlsn
~ DISCLOSURE OF INTERESTS
City of Corpus Chri~i Ordinance 17112, as amended, requires all persons or fines seeking to do business with the City to
provide the following information. Every question must be answered. If the question is not applipble, answer with'NA'.
FlRM NAME: _(~
STREET: ~~~
FlRM is: 1. Corporation 2. Partrrership ^
CITY:.l/a ~~a ZIP: /X
5. Other o
3. Sole Owner ^ 4. Assoaation o
DISCLOSURE RUESTIONS
If additional space is necessary, please use the reverse side of this page or attach separate sheet
1. Static the names of each "employee" of the City of Corpus Christi having an "ownership interest" constituting 3°k
or more of the ownership in the above named "firm".
NaAme~ Job TNe and Cily Deparhnent (rf Imown)
/!/~,
2. State the names of each "official" of the City of Corpus Christi having an "ownership interest" constituting 3% or
more of the ownership in fhe above named "firm".
Name Title
~(~//~_
3. Static fhe names of each "board member" of fhe City of Corpus Christi having an "ownership interest" constituting
3% or more of the ownership in the above named "firm".
N,,ame// Board, Commission or Commdtee
/v~~
4. State the names of each employee or officer of a "consultant" for the City of Corpus.Christi who worked on any
matter related to the subject of this contract and has an "ownership interest' constituting 3% or more of the
ownership in the above named "firm".
Name e / Consultant
~ U~rtR-
CERTIFICATE
I certify that all information provided is true and correct as of the date of this statement, that I have not knowingly
wtihhekf dsdosure of any mfomiation requested; and that supplemental statemerris vn11 be promptly submitted to the Cily
of Corpus Christi, Texas as changes occur. {/ D ,~ Q ~
Certifying Person: , ~!/ Tile: v~C~7 iE~`°"'~ _
{Type or Prirrt) ~
Signature of Certifjrirtg_ Perso ~ Date: ~~ 3~'/D9