HomeMy WebLinkAboutC2009-203 - 5/26/2009 - ApprovedCHANGE ORDER
Depnrtment of Engineering Services
City of Corpus Christi, Texes
Change Order No. 14 FUNDING SOURCE: CONTRACT TIME: 730 C.D.
Operating Department: 2004 Bond Project DATE: May 7, 2009
Name of Project: Cimarron Boulevard, Phase 1 -Saratoga to Yorktown • P.R. 6261
Contractor: Bay, LTD.
CHANGE
Add the followine itears to the contract:
See the attached breakdown:
Total Net:
$599,985.00
5599,985.00
Why was this change necessary? (If left off the plans and specifications, explain why?)
To provided uniform traffic surface from Saratoga to Airline prior to contractor completing Cimarron Phase I.
How can similar changes be avoided in the future?
Unavoidable.
A. CONTRACT PRICE $ 10,540,640.75
B. TOTAL CHANGE ORDERS (inc. current) $ 673,242.03
C. NEW CONTRACT PRICE S 11,413,882.78 ~"7'L
D. THIS CHANGE ORDER 599,985.00 Project Manager
E. PERCENT TOTAL CHANGE (B/A) 8.28%
F. PREVIOUS TIME AUTHORIZED 0 C.D.
G. ADDN'L CONTRACT TIME THIS CHANGE ORDER 0 C.D.
H. TOTAL ADDITIONAL TIME 0 C.D.
CITY OF CORPUS RI TI, TEXAS c CONTRACTOR
By' r~0 I ~~~/ By.
hector f gi Bering Services
Title: ~~~`,.,..d~-:~~ h/1ar,
APPROVED:Operating Department
~~~~ s "Dir. of Management & Budget
v~_ p;, $-i8•~5 ~ ~ -~~~ AUTHURIZtl1
~,,(/yr 'n~ct^~''~' Legal Department nnqq
2009-203 _ 8Y COUNCIL..~~.`2~.~111..
M2009-142 -Assistant City Mngr. G
,. r. ~,....... _ _...........
05/26/09 2~ SECRETARY
Bay, Ltd.
11-May-09
Cimarron Overlay -Saratoga to Airline
Aporo~. 26,800 SY
1.) Mobilization - 1 LS $15,000.00
2.) SWPPP - 1 LS $2,000.00
3.) Traffic Control - 1 LS $20,000.00
4.) Milling
10,000 S.Y. @$2.00/S.Y. $53,600.00
5.) Seal coat
26,800 S.Y. @$2.25/S.Y. $60,300.00
6.) HMAC Overlay (2")
26,800 S.Y. @$12.00/S.Y. $321,600.00
7.) Adjust Existing Sanitary Sewer Mnahole
11 Ea. @$3,000/Ea. $33,000.00
8.) Adjust Existing Storm Sewer Manhole
8 Ea. @$3,000/Ea. $24,000.00
9.) Refl. Pvmt. Mrk. TYI (4"Bxk White)
1,020 LF. @$.50/LF. $510.00
10.) Refl. Pvmt. Mxk. TYI (8" White Solid)
1,500 L.F. @$1.40/L.F. $2,100.00
11.) Refl. Pvmt. Mxk. TYI (4" Yellow Solid) $1,865.00
3,730 L.F. @$.50/L.F.
12.) Refl. Pvmt. Mxk. TYI (4" Bxk Yellow)
1,020 LF @$.50/LF $510.00
13.) Full Depth Pavement Repair
1,310 SY @$ 50.00/SY 65,500.00
Total: $599,985.00