HomeMy WebLinkAboutC2009-224 - 6/23/2009 - ApprovedCHANGE ORDER
Department of Engineering Services
City of Corpus Christi, Texas
CHANGE ORDER NO: l FUNDING SOURCE: CONTRACT TIME 120A/360B C.D.
Operating Department: Bond 2004 DATE: June 4, 2009
Name of Project: Laguna Shores Road Rehab. Graham Road to Hustlin Hornet Road P R #6278
Contractor:
CHANGE
G Contractors
Add the following items to the contract:
See attached breakdown:
Location: Triple Crown/Citation Ditch
ADD
$117,064.40
TOTAL NET: $117,064.40
DEDUCT
Why was this change necessary? (If left off the plans and specifications, explain why?
The work on the attached breakdown is required to prevent flooding in the area.
How can similar changes be avoided in the future?
Unavoidable.
A. CONTRACT PRICE $ 2,919,681.16
B. TOTAL CHANGE ORDERS (inc. current) $ 117,064.40
C. NEW CONTRACT PRICE $ 3,036,745.56
D. THIS CHANGE ORDER 117,064.40
E. PERCENT TOTAL CHANGE (B/A) 4.01%
F. PREVIOUS TIME AUTHORIZED 0 C.D.
G. ADDN'L CONTRACT TIME THIS CHANGE ORDER 0 C.D.
H. TOTAL ADDITIONAL TIME 0 C.D.
CITY OF CORPUS
By:
Director of
TEXAS
~~,,0..__perating Department
wn~Dir. of Management & Budget
~t'i.~al Department
CONTRACTOR
H &
By:
Title:
/ V~V
-~
Project Manager
G t7oattra
~~
Vice Presit~stt
BY COORCIL
Gl n
2009-224
M2009-177
06/23/09
H&G Contractors
Triple Crown Citation Drive Area Drainage Improvements
Per Plans with Poured Concrete
Bid Date: 5/]3/2009
H & G Contractors, Inc.
Item # Description Quantity Unit Unit Price Total
1 Mobt~zatton/Demobilization
2 Traffic controls
3 Patch Pavement
Inlet (3' to 5' depth)-south curb inlet with (2) 5'
4 extensions
Inlet (3' to 5' depth)-north curb inlet with (1) 5'
5 extension
6 18" RCP
7 Remove and replace sidewalks
8 Remove and replace curbs
9 Open 72" double barrel, north and south ends
Allowance for rehab of existing 72" headwall and
10 outfall
1 LS $ 1,500.00 $ 1,500.00
1 LS $ 1,250.00 $ 1,250.00
1 LS $ 1,161.70 $ 1,161.70
,`
1 EA $ 3,680.70 $ 3,680.70
1 EA $ 3,045.70 $ 3,045.70
25 LF $ 46.40 $ 1,160.00
100 SF $ 10.00 $ 1,000.00
75 LF $ 25.00 $ 1,875.00
2 EA $ 2,750.00 $ 5,500.00
11 Allowance fox leaning and rehab double 72" RCP
12 Conaete slope protection and Iltune at headwall
Concrete channel bottom and slope protection at
13 outfall
Partially fill 72" pipe with bullxock, sand (72 LF
14 each)
15 Install bar grates on 72" RCP
16 Excavate, grade ditch to drain
Sod 4' bottom of ditch and lowu 3' of ditch side
17 slopes
18 Hydroseed ditch slope and disturbed azeas
18 Trench Safety
19 Utility Allowance
20 Infall Stmctute
21 Outfall Structure
22 Cellulaz confinement system
23 Superintendence
24 Survey
25 SWPPP
121 SY $ 52.00 $ 6,292.00
327 SY $ 56.00 $ 18,312.00
89 CY $ 85.00 $ 7,565.00
2 EA $ 3,316.25 $ 6,632.50
2,327 BCY $ 8.50 $ 19,779.50
5.5 MSF $ 2,225.00 $ 12,237.50
31.35 MSF $ 200.00 $ 6,270.00
1 LS $ 300.00 $ 300.00
1 LS
1 EA $ 5,500.00 $ 5,500.00
1 EA $ 7,500.00 $ 7,500.00
240 SF $ 15.00 $ 3,600.00
1 LS $ 1,656.00 $ 1,656.00
1 LS $ 2,275.00 $ 2,275.00
1 LS $ 2,883.50 $ 2,883.50
Total -Drainage Improvements $ 117,064.40
Work will be done in accordance to undated Record Drawing No. STO-527, Sheets 1 & 3-6
and verbal instructions from Armando Gutierrez.
Page 1 of 1 Printed on 5/13/2009at 11:11 AM
DEPARTMENT OF ENGINEERING SERVICES
CHANGE ORDER SUMMARY SHEET
June 23, 2009
PROJECT: Laguna Shores Road Rehabilitation -Graham Road to Hustlin'
Hornet Drive
Project No. 6278 / CIP No. SW 18
BOND ISSUE 2004
APPROVED: City Council Motion No. 2008-275 on October 21, 2008
CONTRACTOR: H & G Contractors
P. O. Box 10706
Corpus Christi, TX 78460
TOTAL CONTRACT AMOUNT $2,919,681.16
25°/D Limit Amount $729,920.29
Chan e Order No. 1 June 23, 2009 $117,064.40
TOTAL All Chan e Orders $117,064.40 4% < 25%
LAGUNA SHORESICONSTRUCTION\CHANGE ORDER NO. 1\CHANGE ORDER SUMMARY