HomeMy WebLinkAboutC2011-083 - 3/22/2011 - ApprovedCHANGE ORDER (Page lof6) Department of Engineering Services City of Corpus Christi, Texas CHANGE ORDER No: 1 PROJECT No: 3400 CONTRACT TIME: 178 Operating Department: Parks & Rec Date: March 11 2011 Name of Project: Packery Channel Projects, Phase 2_ Parking & Overlooks Contractor: Safenet Services LLC Contract Drawings, sheets 32A and 32C have been revised, and are hereby made a part of this change order and are attached hereto. The Contract quantities, Part F, are hereby revised as follows: CONTRACTITEM CHANGE TOTAL F -1 Filler Stone Add 500 tons @$50.40 /ton $25,200.00 F-2 Rip Rap I Add 1,750 tons @61.20/ton $107,100.00 F- 3 Rip Rap 2 Add 636 tons @$61.20 /ton $3$,923.20 G -1 (New) Beach Sand Remove approximately Removal 15,000 cy of sand @$4.60 /ton $69,000.00 TOTAL THIS CHANGE ORDER .............................. $240,233.20 Also attached hereto and made a part of this change order is the Construction Manager's assessment and the Contractor's proposal. Why was this change necessary? (If left off the plans and specifications, explain why) burin the period between the time o the sure the AE used for the deli o the Etp ra and the actual start o construction. additional damages occurred to the shoreline protection creating a.need to change the scope of the re an irs. The Beach Sand Removal is a new cqgKzrement added to this contract for administrative convenience. How can similar changes be avoided in the future? The AE should check the field conditions lust prior to the bidding process. A. CONTRACT PRICE ................... . B. TOTAL CHANGE ORDER (include current) ...... . C. NEW CONTRACT PRICE ................ . D. THIS CHANGE ORDER .................. E. PERCENT TOTAL CHANGE (B /A)............ F. PREVIOUS ADDN'L TIME AUTHORIZED ....... G. ADDN'L CONTRACT TIME THIS CHANGE ORDER . H. TOTAL ADDITIONAL TIME ........ ...... . . $ . $2,371,927.61 $ $ 240.23320 $ $2.612.160.81 $ $ 240,233-20 10.1% 45 45 PROJECT ENGINEER By. Felix H_Ocanas Jr. P.E _ CITY OF CORD STI: By: Director of Engineering Services CONTRACTOR: By: c Title: fi t,. APPROVED: `r Operating Department Director of Management and Budget Legal Department 2011 -083 z y Man' O�Q,.�r� City Manager M2011 -070 03/22/11 Safenet Services i CHAPA SAW COI [ — 070 AUTHOMP INDEXED oONsO PW7s Var M0. CO2 L'4 PROkLr'A 25012/00 N � H . c�wic5cxr:+xev a- si -m�� EXIST SHORELINE ARMORING DAMAGED LOCATION #I a E %IST SHORELINE ARMORING EXIST SHORELINE ARMORING W E %IST SHORELINE ARMORING DAMAGED L0000N #3 DAMAGED LOCATION #5 C � pAMAGED LOCATION #2 EXIST SHORELINE ARMORING RASnaN¢ p , DAMAGED LOCATION #d EXIST SHORELINE ARMORING 19EE ROSE 17 DAMAGED LOCATION #6 Z o u VE %IST SH LIN OREE ARMORING FaCxEm cnwnn CDAMAGED LLO # _ �.�� r'r'r�/'� /�r� - (sE6 RGTE t7 ADDITIONAL SHORELINE ARMORING r _ DAMAGED LOCATION 1 �.1.9� ^§ - ADDITIONAL 5HORELIN ARMORING DAMAGED LOCATION ' #18 / 1 E ADDITIONAL SHORELINE ARMORING A001710HAL SHORELINE ARMORING ADDITIONAL SHORELINE ARMORING $ III DAMAGED LOCATION /� -1 o. DAMAGED LOCATION #12', ) DAMAGED LOCATION 18:- 'ANp't #:127 �I14 Cx W w ADDITIONAL SHORELINE ARMORING ��✓ U ti o ADDITIONAL SHORELINE ARMORING,,.,, ADDITIONAL SHORELINE ARMORING 1 #' s DAMAGED LOCATION T5 Mj DAMAGED LOCATION F - � [` s DAMAGED LOCATION ; #1.7'5 "' f`J Q v DAMAGED LOCAT I DAMAGED LOCATiGN #8 J ADDITIONAL SHORELINE ARMORING E %157 SHORELINE ARMORING EXIST S O , F- 4 l .. ✓// 5 9 ` ` ti X J D DAMAGED LOCAT DN . ,Z4,.�,f ✓ 5 x SHORELINE REPAIR LOCATION PLAN LEGEND ww ® aPPR01RN.A1E L OF O Fnr+NOSO sNOEU RVE ueTwwxe gy p, AFRR0IRDA'IE LO Wr OF 1 Da 4 ¢ z o wAD SHORL t N CRNG @k a Z q 0 A ESnUATEO QWRTY SUNELARY - TOWS NOTES z _ O PACKERY CkONEL PRWECTS Q 1. REFERENCE C04S CPCN FUNS PRMMM BY FREESE MG NICHOLS G PIRCE 2 - PARKING AN6 GWRL00KS rte` row Cm MR ECI OS.. 10R MSWK 'A' AND 'c' DATA Nib F- 9 ACOWE ALTERNATE NP. 2 SHORELWE REPAIR A111110NAL ` PRWCCT CONTROL KW OATA x Lu ITEU DESCRIPTION DNIT GUANTITY OLANnTY q AWITIVF ALTERNATE NO. 2- SHORE04C REPAIR A C) 0 FI nttER STONE TON 536 500 4j I in F2 RIPRAP I TON 1150 r, 75D U N F3 RIPRAP 2 TON 705 6J6 F4 CE.V5w STARILI2Eb FAL CY 40 tl Q F5 24 CUP tF t00 0 5 q a SHEU,52A OT 32.. ADDITIVE ALTERNATE No. 2 rt RECORD INmAC HO. CP 170 g e o urrPRa(cr /J!iQ0_ 40' 3 �1 EXISTING DAMAGED MATS AREA TO 5E FILLED WITH "FILLER STONE" ? RE4SZO CHANNEL SLOPE SOUTH SHORLINE ARMORING REPAIR PLAN STA 540 TO VA 7{50 (LOCATION N7) NOTTOSGALE EXIST CONC 4' (APPROX) IfL'IjT, CELLULAR MAT ORIGINAL SHORELINE PROFILE � MPRAP 1 t�l RIPRAP 1 (1.5 FT THK) ASTM D 4751 (SEE NOTE 7) EL -5,25 -- -- 3 ------- - ----------- -- -- - EL -2.0' Lf (SEE NOTE 8) 1 S M {4 1 T EL- 11.0_ { - ` PUN R T G H EL -14.0 REO'D DEPTH Ibe 2' ALLOWABLE OVERDEPTH r fit CHANNEL WIDTH SOUTH SHORLINE ARMORING REPAIR PLAN STA 540 TO VA 7{50 (LOCATION N7) NOTTOSGALE TYPICAL SOUTH SHORLINE ARMORING REPAIR PLAI - / STA 15 +00 LOCATION 1891 STA 13 +20 LOCATION STA 17 +00 LOCATION STA 16 +00 LOCATION S4 STA I5 +00 LOCATION S STA SSe00 LOCATION S5 9 STA STA ST A IZ +00 IL-CATION I #12 TA 23 +50 LOCAT NOT TO SCALE ADDITIVE ALTERNATE No. 2 SHORELINE ARMQR REPAIR NOTES: 1. CONTRACTOR SHALL FIELD VERIFY LIMITS OF DAMAGED AREAS. 2. ALL STATIONS OF OAMAGED AREAS ARE APPROXIMATE AND REFERENCED TO BASELINE 'A' FOR NORTH SHORELINE AND BASELINE 'C' FOR SOUTH SHORELINE. REFERENCE CONSTRUCTION PLANS PREPARED BY FREESE AND NICHOLS FOR CITY PROJECT #340C FOR BASELINE 'A' AND 'C' LAYOUT. 3. REMOVE TWO (2) SECTIONS OF E%ES7 CELLULAR CONIC MAT EACH SIDE OF EXIST 24" CMP AND TOP TO EXPOSE PIPE. REMOVE AND REPLACE PIPE TO MATCH INVERT ELEV AT MANHOLE AND SET OUTFALL INVERT ELEV 0.00', PLACE CEMENT STABILIZED SAND PRIOR TO PLACING PIPE AS BEDDING AND COVER PIPE WITH CEMENT STABILIZED SAND AS SHOWN. 4.EXIST CONIC CELLULAR MAT TO REMAIN IN PLACE. PLACE NEW RIPRAP OVER DEPRESSED AREA AND BENCH RIPRAP AS SHOWN, NEW RIPRAP SHALL ENTEND 3' MIN FROM DETERMINED DEPRESSED BOUNDARY. 5. GEOTE %TILE SHALL BE WOVEN WITH THE FOLLOWING PHYSICAL REQUIREMENTS: PRGRFNtY EXIST CONC 4' (APPROX) IfL'IjT, CELLULAR MAT APPARENT FELLER STONE MPRAP 1 RlPRIP 2 VARIES (5' MIN) ASTM D 4751 U.S. SIEVE EL -5,25 NEW RIPRAP 2 GY Lf (SEE NOTE 8) P ITt S M {4 1 T EXIST FILL PUN R T G H A 1 R 3 Ibe EXIST GRADE TRAPESOIDAL TEAR ASTM D 4583 Ihv TYPICAL SOUTH SHORLINE ARMORING REPAIR PLAI - / STA 15 +00 LOCATION 1891 STA 13 +20 LOCATION STA 17 +00 LOCATION STA 16 +00 LOCATION S4 STA I5 +00 LOCATION S STA SSe00 LOCATION S5 9 STA STA ST A IZ +00 IL-CATION I #12 TA 23 +50 LOCAT NOT TO SCALE ADDITIVE ALTERNATE No. 2 SHORELINE ARMQR REPAIR NOTES: 1. CONTRACTOR SHALL FIELD VERIFY LIMITS OF DAMAGED AREAS. 2. ALL STATIONS OF OAMAGED AREAS ARE APPROXIMATE AND REFERENCED TO BASELINE 'A' FOR NORTH SHORELINE AND BASELINE 'C' FOR SOUTH SHORELINE. REFERENCE CONSTRUCTION PLANS PREPARED BY FREESE AND NICHOLS FOR CITY PROJECT #340C FOR BASELINE 'A' AND 'C' LAYOUT. 3. REMOVE TWO (2) SECTIONS OF E%ES7 CELLULAR CONIC MAT EACH SIDE OF EXIST 24" CMP AND TOP TO EXPOSE PIPE. REMOVE AND REPLACE PIPE TO MATCH INVERT ELEV AT MANHOLE AND SET OUTFALL INVERT ELEV 0.00', PLACE CEMENT STABILIZED SAND PRIOR TO PLACING PIPE AS BEDDING AND COVER PIPE WITH CEMENT STABILIZED SAND AS SHOWN. 4.EXIST CONIC CELLULAR MAT TO REMAIN IN PLACE. PLACE NEW RIPRAP OVER DEPRESSED AREA AND BENCH RIPRAP AS SHOWN, NEW RIPRAP SHALL ENTEND 3' MIN FROM DETERMINED DEPRESSED BOUNDARY. 5. GEOTE %TILE SHALL BE WOVEN WITH THE FOLLOWING PHYSICAL REQUIREMENTS: PRGRFNtY TFSI Nf IfL'IjT, MINIMUM TE51 VALUE I APPARENT FELLER STONE MPRAP 1 RlPRIP 2 OPENING ASTM D 4751 U.S. SIEVE (TON) SIZE (U.S. SIEVE) GY Lf I P ITt S M {4 1 - ad PUN R T G H A 1 R 3 Ibe *70;; TRAPESOIDAL TEAR ASTM D 4583 Ihv - NNTRNAGLES J 15450 - DEGRADATION EO {PERCENT STRENNGTH AS7M 0 4355 R RETAINED AT 00 5 HOURS - - as __SEAM_URE AS M 0 4854 Ib rS 2E +5a 6. FILLER STONE SHALL BE QUARRIED RCCX, IRREGULAR IN SHAPE WITH GRADATION AS FOLLOWS: 9 PASSING 4 IN - 90 TO 100 % PASSING 3 IN - 25 TO 5C X PASSING 2 IN - 0 TO 15 R PASSING I IN - 0 TO 5 7, RIPRAP l SHALL BE QUARRIED ROCK, WEIGHT 1.0-2.0 TONS, IRREGULAR IN SHAPE WITH TOLERANCE OF 75% BY WEIGHT 1.0 -2,5 TONS WELL GRADED, NO MORE THAN 15% UNDER 400 LBS, B. RIPRAP 2 SHALL BE QUARRIED ROCK, WEIGHT 50 -200 LBS, IRREGULAR IN SHAPE WITH TOLERANCE OF 75% BY WEIGHT 80 -200 LOS WELL GRADED, NO MORE THAN 15% UNDER 15 LEE. ESTIMATED aWnTY FOR SHORELINE ARMORING REPAIR LGCARaN E TAR(1N (�PROx} FELLER STONE MPRAP 1 RlPRIP 2 CfMEM S!A &UZfa RlL 24' CMP EON (TON) pN GY Lf I 7 +ID - - ad - - 2 11 +80 - as - - J 15450 - EO 4 19 +BO a0 5 29+50 - - as - - 6 2E +5a 30 - Ta5 B0 Tao 7 a +70 Ta 7 +B 500 1 -. - B 15 +00 - - 60 - - 50 TOTAL 5J0 1,750 705 �.Ii.d.er�.rr�I.�■ 90 i00 R S MA;Mr' Val WO 04 PRq(CT 14. Z iZ R0 II eeemlar glib 1 n � H x U c N Uti o w o w U v 4 +n 4 a LL ? O 4 zz z �0. E I U LV LL " D 4. SNEET32Ca RECO.Q-0 Oft;m M?. - - -cP 1 10 •'1 W a O C7 X u 4 to U. 0 M 4 rrr���rralww��l)I�■e�r■ �.Ii.d.er�.rr�I.�■ R S MA;Mr' Val WO 04 PRq(CT 14. Z iZ R0 II eeemlar glib 1 n � H x U c N Uti o w o w U v 4 +n 4 a LL ? O 4 zz z �0. E I U LV LL " D 4. SNEET32Ca RECO.Q-0 Oft;m M?. - - -cP 1 10 •'1 W a O C7 X u 4 to U. 0 M 4 Packery Channel Projects -Phase 2, Parking & Overlooks Project Number 3400 Change Order No. 1 Scope of Work for Sand Removal Background: During the dredging of the Boat Ramp at the Packery Channel Parking Lot, sand was deposited in front of the El Constante and in front of the adjacent Hotel to the south. Under a separate contract with Garrett Construction Company, about 4 feet in depth of sand was removed and transported just south of this area and leveled. The location of the required work is at Padre island, Corpus Christi, Texas, at the north end of the seawall, in front of the El Constante Condominiums. The scope of this change order is to continue to transport sand from the same location towards lower areas to the south, but maintaining a leveled area in the north -south direction and with a gentle slope of approximately 1 on 12 towards the beach. The work can be done by maintainer (road grader), bull dozer, front -end loader or a combination thereof. The City surveyor will establish the high water line, marked with stakes and flagging. Before and after surveys will be performed for quality control and payment purposes. The limits of the work are from the seawall to the high -water line.An existing Corps of Engineers permit, dated December 5, 2008 exists which permits this activity. Prepared by ECMS LLC Feli H. Ucdhas, March 14, 2011 PAGE 4 OF 6 PN 3400 CHANGE ORDER NO, I March 11, 2011 Project No. 11C101 REF: Packery Channel Projects Phase 2- Parking & Overlooks Felix Ocanas ECMS City of Corpus Christi Dear Mr_ Ocanas, SafeNet Services, LLC is pleased to provide our proposal for additional construction services at the above referenced project. A brief Scope of Work is as follows: Shore Repairs -South Side • Repair six additional locations on the South Shore of Packery Channel per the two pages of new drawings by URS and received by SafeNet on March 5 2011. • Increase the size of the repair for location #7 per the aforementioned drawings. Additional Materials required will be provided at the following unit prices: • Filler Stone- 500 tons $50.40 /ton $ 25,200.00 • Rip Rap #1- 1750 tons $61.20/ton $107,100.00 • Rip Rap #2 636 tons $61.20/ton $ 38,923.20 The total cost for the above listed materials will be $171,223.20. Relocate Sand Behind El Constante • Relocate approximately 13,500 Cubic Yards of Sand behind El Constante- Scope of Work is based on a site visit on March 11, 2011. Quantities are APPROXIMATE. • Unit Pricing will be $4.60 per Cubic Yard of Sand relocated. SafeNet will require an additional 45 days be added to our contract due to the extra work involved. Please contact us with any questions or concerns at 361- 937 -9300. Sincerely, A�_ Ken R. Williams SafeNet Services, LLC CC.' file 1 1C1 01 1321 Glenoak Dr Corpus Christi, TX 78418 tel (361) 937 -9300 fax (361) 937 -8853 PAGE 5 OF 6 PN 3400 CHANGE ORDER NO.1 MEMORANDUM FOR RECORD March 14, 2011 REFERENCE Packery Channel Projects -Phase 2, Parking & Overlooks SUBJECT Change Order Number 1, Review and analysis of Contractor's Proposal E N O P N E E R I N G & CON5TR UC.T10N M A N A G E M E N T S E R v I C E S 5001 OAKMONT DRIVE CORPUS CHRISTI TX 78413 361 9861 1202 OFFICE 361 54914576 MO61hE 361 90612477 FAX ECMS @STX.RR.COM Further reference copy of proposed change order number 1 document. The change order includes additional stone, contract items F -1, F -2 and F -3. The contractor has proposed to perform the additional work at contract prices, as per contract requirements and requests an additional 45 days to complete the work. In view of the fact that this particular part of the contract was suspended until this change order is processed, it is equitable to grant the contractor the additional time requested. Regarding the sand removal; Item G -1, the contractor has proposed a price of $4.60 per cubic yard, The work has been discussed in the field with the Contractor and there is an understanding as to the scope of work. Based on the previous work performed by Garrett Construction Company, at $3.41 per cubic yard, and based on the fact that fuel prices have gone up considerably since then, it is my opinion that the price of $4.60 per cubic is a reasonable price. It is recommended that the contractor's proposal be accepted and the change order be issued. Feli H. Ocanas, Jr., P. . President, ECMS LLC PAGE 6 OF 6 PN 3400 CHANGE ORDER NO.1