HomeMy WebLinkAboutC2011-113 - 3/8/2011 - Approvedengin*W-rs architects contractors
TSPE FIRM NO. P -366
801 Navigation, Suite 3-00
Corpus Christ., Texas
Phones 361- 883 -1984
Fax:.:`361 -883 -1986
FOR
City of
Corpus
Chfisti
DEPARTMENT OF ENC31NEERING SERVICES
CITY OF CORPUS CHRISTI, TEXAS
Phone: 361/826 -3500
Fax: 361/826 -3501
PROJECT NO: 64.69
DRAWING NO: STR 841
.
r
t n�
f �
h o / 2 d�C
y
lE
(Revised 6/27/99)
STAPLES STREET, PHASE 2..
BARRACUDA PLACE TO GOLLI ROAD
(BOND 2008)
PROJECT No 6469
Table of Contents
NOTICE TO BIDDERS (Revised 10/21/98)
NOTICE TO CONTRACTORS - A (Revised March 2009)
Insurance Requirements
NOTICE TO CONTRACTORS - B
Worker's Compensation Coverage for Building or Construction Projects for
Government Entities
- PART A - SPECIAL PROVISIONS
A -1 Time and Place of Receiving Proposals /Pre -Bid Meeting
A -2 Definitions and Abbreviations
A -3 Description of Project
A -4 Method of Award /Explanation of Bid Items
A -5 Items to be Submitted with Proposal
- A -6 Time of Completion /Liquidated Damages
A -7 Workers Compensation Insurance Coverage
A -8 Faxed Proposals
A -9 Acknowledgment of Addenda.
A -10 Wage Rates
A -11 Cooperation with Public Agencies
A -12 Maintenance of Services
A -13 Area Access and Traffic Control
A -14 Construction Equipment Spillage and Tracking
A -15. Excavation and Removals
A -16 Disposal /Salvage of Materials
A -17 Field Office
A -18 Schedule and Sequence of Construction
A -19 Construction Project Layout and Control
A -20 Testing and Certification
A -21 Project Signs
A -22 Minority /Minority Business Enterprise Participation Policy (Revised 10/98)
A -23 Inspection Required
A -24 Surety Bonds
A25 Sales Tam Exeffiptien (NO LONGER APPLICABLE) .(6/11/98)
A 726 Supplemental Insurance Requirements
R Respensibllif=y €ems - Damage mits (NOT USED)
A--28 Considerations for Contract Award and Execution
A--29 Contractor's Field Administration Staff
A- 30 Amended "Consideration of Contract" Requirements
A -31 Amended Policy on Extra Work and Change Orders
A -32 Amended "Execution of Contract" Requirements
A -33 Conditions of Work
A -34 Precedence of Contract Documents
Table of Contents
Page '1 of 7
(NOT USED)
A -36 Other Submittals
A Amended rr City (NOT USED)
A -38 Worker's Compensation Coverage for Building or Construction Projects for
Government Entities
A Gertifieate of GeeiipaRey and Final Reeeptanee (NOT USED)
A -40 Amendment to Section B -8 -6: Partial Estimates
A -41 Ozone Advisory
A -42 OSHA Rules & Regulations
A -43 Amended Indemnification & Hold Harmless (9/98)
A -44 Change Orders (4/26/99)
A -45 As -Built Dimensions and Drawings
A -46 Disposal of Highly Chlorinated Water (7/5/00)
A -47 Pre - Construction Exploratory Excavations (7/5/00)
A -48 Overhead Electrical Wires
A -49 Amended "Maintenance Guaranty" (8/24/00)
A -50 Amended Prosecution and Progress
A -51 Electronic Submittal of Bids
A -52 Dust Control
A -53 Regional Transportation Authority (RTA) Contract Documents
ATTACHMENTS
1 -- Project Sign
2 - Electronic Bid
PART B - GENERAL PROVISIONS
PART C - FEDERAL WAGE RATES AND REQUIREMENTS
PART D - RTA CONTRACT DOCUMENTS
PART S - STANDARD SPECIFICATIONS
Section 022020 Excavation and Backfill for Utilities and Sewers
Section 022022 Trench Safety for Excavations
Section 022100 Select Material
Section
026202
Hydrostatic Testing of System (S -89)
Section
026206
Ductile Iron Pipe and Fittings (S -81)
Section
026210
Polyvinyl. Chloride Pipe (S -83.)
Section
026402
Water Pipe (S -88.)
Section
026404
Water Service Lines (S -87) �.
Section
026409
Tapping Sleeve & Valve
Section
'026411
Gate Valves for.'Water Lines
Section
026416
Fire Hydrants
Section
027203
Vacuum Testing of Manhole
Section
027602
Gravity Sanitary Sewers (S -61)
Section
030020
Portland Cement Concrete
Section
032020
Reinforcing Steel (S -42)
Section
038000
Concrete Structures (S -41)
Section
055420
Frames Gates Rings and Covers
PART T - TECHNICAL SPECIFICATIONS
100 Preparing Right of Way
105 Removing Stabilized Base and Asphalt Pavement
110 Excavation
Table of Contents
Page 2 of 7
132. Embankment
150 Blading
204 Sprinkling
210 Rolling
216 Proof Rolling
247 Flexible Base
260 Lime Treatment (Road Mixed)
300 Asphalts, Oils, and Emulsions
301 Asphalt Antistripping Agents
302 Aggregates for Surface Treatments
310 Prime. Coat
314 Emulsified Asphalt Treatment
316 Surface Treatments
320 Equipment for Asphalt Concrete Pavement
341 Dense - Graded Hot Mix Asphalt (QC /QA)
360 Concrete Pavement
400 Excavation and Backfill for Structures
420 Concrete Structures
421 Hydraulic Cement Concrete
424 Precast Concrete Structures (Fabrication)
427 Surface Finishes for Concrete
432 Ripxap
440 Reinforcing Steel
440 -001 Reinforcing Steel (Revision)
462 Concrete Box Culverts and Storm Drains
464 Reinforced Concrete Pipe
465 Manholes and Inlets
496 Removing Structures
500 Mobilization
502 Barricades, .Signs, and Traffic Handling
506 Temporary Erosion, Sedimentation, and Environmental Controls
528 Colored Textured Concrete and Landscape Pavers
529 Concrete Curb, Gutter, and Combined Curb and Gutter.
531 Sidewalks
585 Ride Quality for Pavement Surfaces
636 Aluminum Signs
644 Small Roadside Sign Supports and Assemblies
662 Work Zone Pavement Markings
666 Reflectorized Pavement Markings
672 Raised Pavement Markings
677 Eliminating Existing Pavement Markings
678 Pavement Surface Preparation for Markings
5121 Geogrid Base Reinforcement
6007 Removing Traffic Signals
6011 Testing, Training, Documentation, Final Acceptance and Warranty
6013 Electronic Components
6038 Portable Changeable Message Sign
T- 020800 Well Pointing, Dewatering and Disposal
T- 026700 Air Release Valves
T- 027205 Glass -Fiber Reinforced Polyester (FRP) Manholes
T- 027604 Disposal of Waste from Wastewater Line Cleaning Operations
T- 027611 Cleaning and Televised Inspection. of Wastewater Lines
TS -100 General Notes
TS -416 Drilled Shaft Foundations
TS -600 Traffic Signal Standards & Specifications
TS -601 Traffic Signal Controller Unit
Table of Contents
Page 3 of 7
TS -615 Traffic Signal. Cabinet and Assemblies
TS -618 Conduit
TS -620 Electrical Conductors
TS -621 Tray Cable
TS -624 Ground Boxes
TS -628 Electrical Services
TS -633 Uninterruptable Power Supply
TS -655 Controller Foundation
TS --680 Installation of Highway Traffic Signals
TS -682 Vehicle and Pedestrian. Signal Head
TS -683 LED Pedestrian Signal Countdown Module
TS -684 Traffic Signal Cables ti
TS --686 Traffic Signal Pole Assemblies (Steel)
TS -698 Pan /Tilt /Zoom Camera
TS -699 Radar Presence Detection Device
TS -6041 Internally Lighted Street Name Sign with Light- Emitting Diode Lamps
PART W - DRAWINGS
1 Cover Sheet
2 Sheet Index 1
3 Legend
4 Location Map
5 General Motes & Testing Schedule
6 General Notes
7 Estimated Quantities
8 Base Bid Typical. Street Sections 1 OF 3
9 Base Bid Typical Street Sections 2 OF 3
10 Base Bid Typical Street Sections 3 OF.3
11 Alternate Typical Street Sections 1 OF 3
12 Alternate Typical Street Sections 2 OF 3
13 Alternate Typical Street Sections 3 OF 3
14 Control Layout & Alignment Data
15 Removal Summary
16 Base Bid Construction and Traffic Control Notes
17 Alternate Construction and Traffic Control Notes
18 Base Bid Construction Sequence Typical Sections
19 Alternate Construction Sequence Typical Sections
20 Advance Warning Signs At Project Limits
21 Base Bid Construction Sequence Layout
22 Alternate Construction Sequence Layout
23 Traffic Control Plan Step 2 1 of 2
24 Traffic Control Plan Step 2 2 of 2
25 Traffic Control Plan Step 3 1 of 2
26 Traffic Control Plan Step 3 2 of 2
27 Traffic Control Plan Step 4
28 Traffic Control Plan Step 5
29 Traffic Control Plan Step 6
30 Traffic Control Plan. Step 7
31 Supplemental Traffic Control Plan For Base Bid Construction Sequence Step 2
32 Supplemental Traffic Control Plan For Base Bid Construction Sequence Step 3
33 Supplemental Traffic Control Plan For Base Bid Construction Sequence Steps 4
& 5
34 Everhart Road Intersection Reconstruction Traffic Control Plan Step 1
35 Everhart Road Intersection Reconstruction Traffic Control Plan Step 2
36 Everhart Road Intersection Reconstruction Traffic Control flan Step 3
Table of Contents
Page 4 of 7
37
Everhart Road Intersection Reconstruction Traffic Control Plan Step 4
38
Gollihar Road Intersection Reconstruction Traffic Control Plan
Step 1
39
Gollihar Road Intersection Reconstruction Traffic Control Plan
Step 2
40
Existing Wastewater Basemap
41
Existing Water Basemap
42
Existing Storm Water Basemap
43
Existing Gas Basemap
44
Base Bid Utility Plan and Profile STA 45 +00 to STA 47 +75
44A
Additive Alternate Water Line Plan and Profile STA 45 +00 to
STA 47 +75
45
Base Bid Utility Plan and Profile STA 47 +75 to STA 53 +00
45A
Additive Alternate Water Line Plan and Profile STA 47 +75 to
STA 53-00
46
Base Bid Utility Plan and Profile STA 53 +00 to STA 58 +25
46A
Additive Alternate Water Line Plan and Profile STA 53 +00 to
STA 58 +25
47
Base'Bid Utility Plan and Profile STA 58 +25 to STA 63 +50
47A
Additive Alternate Water Line Plan and Profile STA 58 +25 to
S`.['A 63 +50
48
Base Bird Utility Plan and Profile STA 63 +50 to STA 68 +75
48A
Additive Alternate Water Line Plan and Profile STA 63 +50 to
STA 68 +75
49
Base Bid Utility Plan and Profile STA 68 +75 to STA 74 +00
49A
Additive Alternate Water Line Plan and Profile STA 68 +75 to
STA 74 +00
50
Base Bid Utility Plan and Profile STA 74 +00 to STA 79 +25
50A
Additive Alternate Water Line Plan and Profile STA 74 +00 to
STA 79 +25
51
Base Bid Utility Plan and Profile STA 79 +25 to STA 84 +50
51A
Additive Alternate Water Line Plan and Profile STA 79 +25 to
STA 84 +50
52
Base Bid Utility Plan and Profile STA 84 +50 to STA 89 +00
52A
Additive Alternate Water Plan and Profile STA 84 +50 to STA
89 +00
53
Waterline Tie --in Details 1 of 3
53A
Additive Alternate Waterline Tie -in Details 1 of 2
54
Waterline Tie -in Details 2 of 3
54A
Additive Alternate Waterline Tie -in Details 2 of 2
55
Waterline Tie -in Details 3 of 3
56
Drainage Area Map STA 45 +00 to 54 +00
57
Drainage Area Map STA 54 +00 to 81 +00
58
Drainage Area Map STA 81 +00 to 89 +00
59
Hydraulic Data Sheet
60
Storm Water Plan and Profile STA 45-00 to STA 47 +75
61
Storm Water Plan and Profile STA 47 +75 to STA 53 +00
62
Storm Water Plan and Profile STA 53 +00 to STA 58 +25
63
Storm Water Plan and Profile STA 58 +25 to STA 63 +50
64
Storm Water Plan and Profile STA 63 +50 to STA 68 +75
65
Storm Water Plan and Profile STA 68 +15 to STA 74 +00
66
Storm Water Plan and Profile STA 74 +00 to STA 79 +25
67
Storm Water Plan and Profile STA 79 +25 to STA B4 +50
68
Storm Water Plan and Profile STA 84+50 to STA 89 +00
69
Storm Water Laterals 1 of 3
70
Storm Water Laterals 2 of 3
71
Storm Water Laterals 3 of 3
72
Street Plan and Profile STA 45 +00 to STA 47 +75
73
Street Plan and Profile STA 47 +75 to STA 53 +00
74
Street Plan and Profile STA 53 +00 to STA 58 +25
.75
Street Plan and Profile STA 58 +25 to STA 63 +50
76
Street Plan and Profile STA 63 +50 to STA 68 +75
77
Street Plan and Profile STA 68 +75 to STA 74 +00
78
Street Plan and Profile STA 74 +00 to STA 79 +25
79
Street Plan and Profile STA 79 +25 to STA 84 +50
80
Street Plan and Profile STA B4 +50 to STA 89 +00
81
Intersection & Curb Ramp Details Carmel Parkway
Table of contents
Page 5 of 7
"i
82 Intersection & Curb Ramp Details Gollihar Road
83 Intersection & Curb Ramp Details Everhart Road
84 Intersection & Curb Ramp Details Gollihar Road & Autotown Drive
85 Intersection & Curb Ramp Details Barracuda, Coral, Miramar & Barry
86 Standard Water Details 1 of 5
87 Standard Water Details 2 of 5
88 Standard Water Details 3 of 5
89 Standard Water Details 4 of 5
90 Standard Water Details 5 of 5 b
91 FLDCD With Vault and Meter Vault Details
92 Sanitary Sewer Standard Details 1 of 5
93 Sanitary Sewer Standard Details 2 of 5 ,
94 Sanitary Sewer Standard Details 3 of 5
95 Sanitary Sewer Standard Details 4 of 5
96 Sanitary Sewer Standard Details 5 of 5
97 Miscellaneous Details I of 5
98 Miscellaneous Details 2 of 5
99 Miscellaneous Details 3 of 5
100 Miscellaneous Details 4 of 5
101 Miscellaneous Details 5 of 5
102 Storm Water Standard Details 1 of 2
103 Storm Water Standard Details 2 of 2
104 Single Box Culverts Precast And Cast in Place SCC -5 &6, SCP -6, SCC -MD, SCP -MD
105 Single Box Culvert SCP -5
106 Commercial Driveway Details 1 of 2
107 Commercial Driveway Details 2 of 2
108 Pedestrian Facilities PED -05 Sheets 1 - 4
109 Sign Layout STA 45 +00 to STA 66 +00 r
110 Sign Layout STA 66 +00 to STA 89 +00
111 Traffic Sign Requirements TSR(4) -08
112 Sign Mounting Details SMD -08, SMD(SLIP- 2) -08, SMD(TWT) -08
113 Pavement Markings Layout STA 45 +00 to STA 52.50
114 Pavement Markings Layout STA 52 +50 to STA 63 +00
115 Pavement Markings Layout STA 63 +00 to STA 73 +50
116 Pavement Markings Layout STA 73 +50 to STA 84 +00
117 Pavement Markings Layout STA 84 +00 to STA 89 +00
118 Pavement Marking Details PM(1) -03 - PM(4) -03
119 Pavement Marking PM(5)- 01(Words) PM(6)- 01(Arrows)
120 Storm Water Pollution Prevention Plan STA 45 +00 to STA 52 +50
121 Storm Water Pollution Prevention Plan ,STA 52+50 to STA 63+00
122 Storm Water Pollution Prevention Plan STA 63 +00 to STA 73 +50
123 Storm Water Pollution Prevention Plan STA 73 +50 to STA 84 +00
124 Storm Water Pollution Prevention Plan STA 84 +00 to STA 89 +00
125 Pollution_ Control Measures Erosion Control Log
126 Pollution Control Measures EC (3) -93
127 Environmental Permits Issues and Commitments (EPIC) Sheet 1 of 2
128 Environmental Permits Issues and Commitments (EPIC) Sheet 2 of 2
129 Barricade and Construction Details BC(1) -07 - BC(4) -07
130 Barricade and Construction Details BC(5) -07 - BC(8) -07
131 Barricade and Construction. Details BC(9) -07 - BC(12) -07
132 Traffic Control Plan Typical Details TCP (2-- 1)--98 TCP(2 -2) -03 TCP(2 -4) -03
TCP(2 -5) -03
133 Traffic Control Plan Mobile Operations TCP(3 -1) -98 TCP(3 -3) -98
134 Work Zone, Traffic Control, Signing for Uneven Lanes WZ(STMP) -03, WZ(TD) -03,
WZ(UL) -03
135 Concrete Paving Details Joint Seals JS -94
Table of Contents
Page 6 of 7
136 Continuously Reinforced Concrete Pavement CRCP(1) -09
Traffic Signal Improvements Staples St. and Gollihar Rd - Autotown Dr.
T1 Traffic Signal Layout
T2 Traffic Signal Summary
T3 Termination and Phasing Summary
T4 Signal Head Detail Sheet
T3 . ILSN Sign Details (LED)
T6 Traffic Signal Signage Sheet
TRAFFIC SIGNAL STANDARD SHEETS
SMA- 100(1) -99
SMA- 100(2) --96
TS -FD -99
ED (1) -03
ED (2) -03
ED (3) --03
ED(4) -03
ED(5) -03
ED (6) --03
ED(7) -03
LUM -A- 9 9
MA -C -09
MA -D -07
TS -CF -04
APPENDIX
A - GEOTECHNICAL INVESTIGATION
NOTICE
AGREEMENT
PROPOSAL /DISCLOSURE STATEMENT
PERFORMANCE BOND
PAYMENT BOND
Table of Contents
Page 7 of 7
NOTICE TO BIDDERS
NOTICE TO BIDDERS
Sealed proposals, addressed to the City of Corpus Christi, Texas for:
STAPLES STREET PHASE 2 - BARRACUDA PLACE TO GOLLIHAR ROAD (BOND 2008) ; PROJECT NO. 6469;
The Base Bid for this project consists of (approximately) 37,479 square yards of roadway
excavation, 37,479 square yards of flexible base, 34,381 square yards of HMAC, 37,479
square yards of geo -grid, 8,816 linear feet of curb and gutter, 49,090 square feet of
concrete sidewalk, 4,534 linear feet of 18 " -54" RCP, 1,029 linear feet of concrete box
culvert, curb inlets, proposed 5' diameter manholes, 470 linear feet of 8 " -15" PVC
wastewater line, 2,703 linear feet of 6 " -12" PVC water line, 6 -20" gate valves, fire
hydrant assemblies, 8 " -24" tapping sleeves, ABA improvements, concrete bus pad and traffic
signal improvements; in accordance with the plans, specifications, and contract documents.
Alternate No. 1 - ALTERNATE TRAFFIC CONTROL PLAN & CONSTRUCTION SEQUENCING% Consists of
constructing the proposed improvements in three (3) separate parts or phases.
a_ Part 1: Carmel Parkway to Everhart.
b. Part 2: Barracuda to Carmel Parkway.
c. Part 3. Everhart to Gollihar / Autotown.
Alternate No. 2 - CONTINUOUSLY REINFORCED CONCRETE PAVEMENT IN LIEU OF HMAC
(SEQUENCING /TRAFFIC CONTROL SAME AS 'SHOWN FOR THE BASE BID): Consists of installing 9" of
Continuously reinforced concrete pavement (Type P) in lieu of HMAC from Barracuda to
Gollihar / Autotown.
Alternate No. 3 CONTINUOUSLY REINFORCED CONCRETE PAVEMENT IN LIEU OF HMAC
(SEQUENCING /TRAFFIC CONTROL SAME AS SHOWN FOR ALTERNATE NO. 1) : Consists of installing 9"
of continuously reinforced concrete pavement (Type P) in lieu of HKAC. Sequencing and
phasing limits are the same as shown in Alternate No. 1.
Alternate No. 4 - EXPEDITED SCHEDULE FOR CARMEL PARKWAY TO EVERHART (HMAC OPTION) provides
for additional compensation to the Contractor for an accelerated construction schedule to
complete the project by October 1, 2011 (from Notice to Proceed). This only applies for the
section of work from Carmel Parkway to Everhart.
Alternate No. 5 - EXPEDITED SCHEDULE FOR CARMEL PARKWAY TO EVERHART (CONCRETE OPTION);
provides for additional Compensation to the Contractor for an accelerated construction
schedule to complete the project by October 1, 2011 (from Notice to Proceed). This only
applies for the section of work from Carmel Parkway to Everhart.
Alternate No. 6 — WATER IMPROVEMENTS: Consists of approximately 3,492 linear feet of 6 " -8"
PVC waterline and associated fittings, 6 " -8" gate valves, 8 " -20" tapping sleeves & valves
and fire hydrant assemblies.
Bids will be received at the office of the City Secretary until 2:00 p.m. on
Wednesday, February 9, 2011 and then publicly opened and read. Any bid received after
Closing time will be returned unopened.
A pre -bid meeting is scheduled for Wednesday, February 2, 2011 beginning at 10:00 a.m. The
pre -bid meeting will convene at the Engineering Services Conference Room, 3rd Floor,
City Hall, 1203 Leopard Street. The pre -bid meeting will be conducted by the City and will
not include a site visit. No additional or separate visitations will be conducted by the
City.
A bid bond in the amount of 5% of the highest amount bid must accompany each proposal.
Failure to provide the bid bond will constitute a non - responsive proposal which will not be
considered. Failure to provide required performance and payment bonds for contracts over
$25,000.00 will result in forfeiture of the 5% bid bond to the City as liquidated damages.
Bidder's plan deposit is subject to mandatory forfeiture to the City if bidding documents
are not returned to the City within two weeks of receipt of bids.
Plans, proposal forms, specifications and contract documents may be procured from the City
Engineer upon a deposit of One Hundred and no /100 Dollars ( $100.00 ) as a guarantee of their
return in good condition within two weeks of M date. Documents can be obtained by mail
upon receipt . of an additional ( $10.00 ) which is a non - refundable postage /handling charge.
The bidder is hereby notified that the owner has ascertained the wage rates which prevail
in the locality in which this work is to be done and that such wage scale is set out in the
contract documents obtainable at the office of the City Engineer and the Contractor shall
pay not less than the wage rates so shown for each craft or type of "laborer,." "workman,"
or "mechanic" employed on this project.
The City reserves the right to reject any or all bids, to waive irregularities and to
accept the bid which, in the City's opinion, seems most advantageous to the City and in the
best interest of the public.
CITY OF.CGRPUS CHRISTI, TEXAS
/s/ Pete Anaya, P.E.
Director of Engineering Services
/s/ Armando Chapa
City Secretary
NOTICE TO CONTRACTORS A
NOTICE TO CONTRACTORS -- A
INSURANCE REQUIREMENTS
Revised March, 2009
A Certificate of Insurance indicating proof of coverage in the
following amounts is required:
r---
TYPE OF INSURANCE
MINIM M INSURANCE COVERAGE
30 -Day Notice of Cancellation required on
Bodily Injury and Property Damage
all certificates
PER OCCURRENCE / AGGREGATE
Commercial General Liability including;
$2,000,000 COMBINED SINGLE LIMIT
1. Commercial Form
2. Premises - Operations
3. Explosion and Collapse Hazard
4. Underground Hazard
5. Products/ Completed Operations
Hazard
G. Contractual Liability
7. Broad Form Property Damage
8. Independent Contractors
9. Personal Injury
AUTOMOBILE LIABILITY - -OWNED NON -OWNED
$1,000,000 COMBINED SINGLE LIMIT
OR RENTED
WHICH COMPLIES WITH.THE TEXAS WORKERS'
WORKERS' COMPENSATION
COMPENSATION ACT AND PARAGRAPH II OF
THIS EXHIBIT
EMPLOYERS' LIABILITY
$500,000
EXCESS LIABILITY
$1,000,000 COMBINED SINGLE LIMIT
PROFESSIONAL POLLUTION LIABILITY/
$2,000,000 COMBINED SINGLE LIMIT
ENVIRONMENTAL IMPAIRMENT COVERAGE
Not limited to sudden & accidental
❑ REQUIRED
discharge; to include long -term
environmental impact for the disposal of
NOT REQUIRED
contaminants
BUILDERS' RISK
See Section B -6 -11 and Supplemental
Insurance Requirements `
❑ REQUIRED
X NOT REQUIRED
INSTALLATION FLOATER
See Section B -6 -11 and Supplemental
Insurance Requirements
❑ REQUIRED
X NOT REQUIRED
Page 1 of 2
The City of Corpus Christi must be named as an additional insured on all
coverages except workers compensation liability coverage.
The name of the project must be listed under "description of operations" on
each certificate of insurance.
For each insurance coverage, the Contractor shall obtain an endorsement to
the applicable insurance policy, signed by the insurer, providing the City
with thirty (30) days prior written notice of cancellation of or material
change on any coverage. The Contractor shall provide to the City, the other
endorsements to insurance policies or coverages which are specified in
section B -6 -11 or Special Provisions section of the contract.
A completed "Disclosure of Xnterest" must be submitted with your proposal.
Should you have any questions regarding insurance requirements, please
contact the Contract Administrator at 826 -3500.
Page 2 of 2
NOTICE TO CONTRACTORS - B
NOTICE TO CONTRACTORS - B
WORKER'S COMPENSATION INSURANCE
REQUIREMENTS
Page 1 of 11
Texas Administrative Code
TITLE 28 INSURANCE
PART 2 TEXAS DEPARTMENT OF INSURANCE, DIVISION OF
WORKERS' COMPENSATION
CHAPTER 110 REQUIRED NOTICES OF COVERAGE
SUBCHAPTERS EMPLOYER NOTICES
RULE §110.110 Reporting Requirements for Building or Construction
Projects for Governmental Entities
(a) The following words and terms, when used in this rule, shall have the following meanings,
unless the context clearly indicates otherwise. Terms not defined in this rule shall have the
meaning defined in the Texas Labor Code, if so defined.
(1) Certificate of coverage (certificate) - -A copy of a certificate of insurance, a certificate of
authority to self- insure issued by the commission, or a workers' compensation coverage
agreement (TWCC -81, TWCC -82, TWCC -83, or TWCC -84), showing statutory workers'
compensation insurance coverage for the person's or entity's employees (including those subject
to a coverage agreement) providing services on a project, for the duration of the project.
(2) Building or construction - -Has the meaning defined in the Texas Labor Code,
§406.096(e)(1).
(3) Contractor - -A person bidding for or awarded a building or construction project by a
governmental entity.
(4) Coverage -- Workers' compensation insurance meeting the statutory requirements of the
Texas Labor Code, §401.011(44).
(5) Coverage agreement - -A written agreement on form TWCC -81, form TWCC -82, form
TWCC -83, or form TWCC -84, filed with the Texas Workers' Compensation Commission which
establishes a relationship between the parties for purposes of the Texas Workers' Compensation
Act, pursuant to the Texas Labor Code, Chapter 406, Subchapters F and G, as one of
employer /employee and establishes who will be responsible for providing workers'
compensation coverage for persons providing services on the project.
(6) Duration of the project -- Includes the time from the beginning of work on the project until
the work on the project has been completed and accepted by the governmental entity.
(7) Persons providing services on the project ( "subcontractor" in §406.096 of the Act) - -With the
exception of persons excluded under subsections (h) and (i) of this section, includes all persons
or entities performing all or part of the services the contractor has undertaken to perform on the
project, regardless of whether that person contracted directly with the contractor and regardless
of whether that person has employees. This includes but is not limited to independent
contractors, subcontractors, leasing companies, motor carriers, owner- operators, employees of
any such entity, or employees of any entity furnishing persons to perform services on the project.
Page 2 of 1 I
"Services" includes but is not limited to providing, hauling, or delivering equipment or materials,
or providing labor, transportation, or other service related to a project. "Services" does not
include activities unrelated to the project, such as food/beverage vendors, office supply
deliveries, and delivery of portable toilets.
(8) Project -- Includes the provision of all services related to a building or construction contract
for a governmental entity.
(b) Providing or causing to be provided a certificate of coverage pursuant to this rule is a
,._ representation by the insured that all employees of the insured who are providing services on the
project are covered by workers' compensation coverage, that the coverage is based on proper
reporting of classification codes and payroll amounts, and that all coverage agreements have
been filed with the appropriate insurance carrier or, in the case of a self-insured, with the
commission's Division of Self- Insurance Regulation. Providing false or misleading certificates of
coverage, or failing to provide or maintain required coverage, or failing to report any change that
materially affects the provision of coverage may subject the contractor or other person providing
services on the project to administrative penalties, criminal penalties, civil penalties, or other
civil actions.
(c) A governmental entity that enters into a building or construction contract on a project shall:
(1) include in the bid specifications, all the provisions of paragraph (7) of this subsection, using
the language required by paragraph (7) of this subsection;
(2). as part of the contract, using the language required by paragraph (7) of this subsection,
require the contractor to perform as required in subsection (d) of this section;
(3) obtain from the contractor a certificate of coverage for each person providing services on
the project, prior to that person beginning work on the project;
(4) obtain from the contractor a new certificate of coverage showing extension of coverage:
(A) before the end of the current coverage period, if the contractor's current certificate of
coverage shows that the coverage period ends during the duration of the project; and
(B) no later than seven days after the expiration of the coverage for each other person
providing services on the project whose current certificate shows that the coverage period ends
during the duration of the project;
(S) retain certificates of coverage on file for the duration of the project and for three years
thereafter;
(6) provide a copy of the certificates of coverage to the commission upon request and to any
person entitled to them by law; and
(7) use the language contained in the following Figure 1 for bid specifications and contracts,
without any additional words or changes, except those required to accommodate the specific
document in which they are contained or to impose stricter standards of documentation: Attached
Graphic
Page 3 of 11
(d) A contractor shall:
(1) provide coverage for its employees providing services on a project, for the duration of the
project based on proper reporting of classification codes and payroll amounts and filing of any
coverage agreements;
(2) provide a certificate of coverage showing workers' compensation coverage to the
governmental entity prior to beginning work on the project;
(3) provide the governmental entity, prior to the end of the coverage period, a new certificate of
coverage showing extension of coverage, if the coverage period shown on the contractor's L
current certificate of coverage ends during the duration of the project;
(4) obtain from each person providing services on a project, and provide to the governmental
entity:
(A) a certificate of coverage, prior to that person beginning work on the project, so the
governmental entity will have on file certificates of coverage showing coverage for all persons
providing services on the project; and
(B) no later than seven days after receipt by the contractor, a new certificate of coverage
showing extension of coverage, if the coverage period shown on the current certificate of
coverage ends during the duration of the project;
(5) retain all required certificates of coverage on file for the duration of the project and for one
year thereafter;
(6) notify the governmental entity in writing by certified mail or personal delivery, within ten
days after the contractor knew or should have known, of any change that materially affects the
provision of coverage of any person providing services on the project;
(7) post a notice on each project site informing all persons providing services on the project that
they are required to be covered, and stating how a person may verify current coverage and report
failure to provide coverage. This notice does not satisfy other posting requirements imposed by
the Act or other commission rules. This notice must be printed with a title in at least 30 point
bold type and text in at least 19 point normal type, and shall be in both English and Spanish and
any other language common to the worker population. The text for the notices shall be the
following text provided by the commission on the sample notice, without any additional words
or changes: Attached gKohic
(8) contractually require each person with whom it contracts to provide services on a project to:
(A) provide coverage based on proper reporting of classification codes and payroll amounts
and filing of any coverage agreements for all of its employees providing services on the project,
for the duration of the project;
(B) provide a certificate of coverage to the contractor prior to that person beginning work on
the project;
(C) include in all contracts to provide services on the project the language in subsection (e)(3)
of this section;
Page 4 of 11
(D) provide the contractor, prior to the end of the coverage period, a new certificate of
coverage showing extension of coverage, if the coverage period shown on the current certificate
of coverage ends during the duration of the project;
(E) obtain from each other person with whom it contracts, and provide to the contractor:
(i) a certificate of coverage, prior to the other person beginning work on the project; and
(ii) prior to the end of the coverage period, a new certificate of coverage showing extension
of the coverage period, if the coverage period shown on the current certificate of coverage ends
during the duration of the project;
(F) retain all required certificates of coverage on. file for the duration of the project and for one
year thereafter;
(G) notify the governmental entity in writing by certified mail or personal delivery, within ten
days after the person knew or should have known, of any change that materially affects the
provision of coverage of any person providing services on the project; and
(H) contractually require each other person with whom it contracts, to perform as required by
subparagraphs (A) -(H) of this paragraph, with the certificate of coverage to be provided to the
.person for whom they are providing services.
(c) A person providing services on a project, other than a contractor, shall:
(1) provide coverage for its employees providing services on a project, for the duration of the
project based on proper reporting of classification codes and payroll amounts and filing of any
coverage agreements;
(2) provide a certificate of coverage as required by its contract to provide services on the
-- project, prior to beginning work on the project;
(3) have the following language in its contract to provide services on the project: "By signing
this contract or providing or causing to be provided a certificate of coverage, the person signing
this contract is representing to the governmental entity that all employees of the person signing
this contract who will provide services on the project will be covered by workers' compensation
coverage for the duration of the project, that the coverage will be based on proper reporting of
classification codes and payroll amounts, and that all coverage agreements will be filed with the
appropriate insurance carrier or, in the case of a self - insured, with the commission's Division of
Self- Insurance Regulation. Providing false or misleading information may subject the contractor
to administrative penalties, criminal penalties, civil penalties, or other civil actions."
(4) provide the person for whom it is providing services on the project, prior to the end of the
coverage period shown on its current certificate of coverage, a new certificate showing extension
of coverage, if the coverage period shown on the certificate of coverage ends during the duration
of the project;
(5) obtain from each person providing services on a project under contract to it, and provide as
required by its contract:
(A) a certificate of coverage, prior to the other person beginning work on the project; and
(B) prior to the end of the coverage period, a new certificate of coverage showing'extension of
the coverage period, if the coverage period shown on the current certificate of coverage ends
during the duration of the project;
Page 5 of 11
(6) retain all required certificates of coverage on file for the duration of the project and for one
year thereafter;
(7) notify the governmental entity in writing by certified mail or personal delivery, of any
change that materially affects the provision of coverage of any person providing services on the
project and send the notice within ten days after the person knew or should have known of the
change; and
(8) contractually require each other person with whom it contracts to:
(A) provide coverage based on proper reporting of classification codes and payroll amounts
and filing of any coverage agreements for all of its employees providing services on the project,
for the duration of the project;
(B) provide a certificate of coverage to it prior to that other person begin_ ning work on the
project;.
(C) include in all contracts to provide services on the project the language in paragraph (3) of
this subsection;
(D) provide, prior to the end of the coverage period, a new certificate of coverage showing
extension of the coverage period, if the coverage period shown on the current certificate of `
coverage ends during the duration of the project;
(E) obtain from each other person under contract to it to provide services on the project, and
provide as required by. its contract:
(i) a certificate of coverage, prior to the other person beginning work on the project; and
(ii) prior to the end of the coverage period, a new certificate of coverage showing extension
of the coverage period, if the coverage period shown on the current certificate of coverage ends
during the duration of the contract;
(F) retain all required certificates of coverage on file for the duration of the project and for one
year thereafter;
(G) notify the governmental entity in writing by certified mail or personal delivery, within ten
days after the person knew or should have known, of any change that materially affects the
provision of coverage of any person providing services on the project; and _w
(H) contractually require each person with whom it contracts, to perform as required by this
subparagraph and subparagraphs (A) -(G) of this paragraph, with the certificate of coverage to be W
provided to the person for whom they are providing services.
(f) If any provision of this rule or its application to any person or circumstance is held invalid,
the invalidity does not affect other provisions or applications of this rule that can be given effect
without the invalid provision or application, and to this end the provisions of this rule are
declared to be severable.
(g) This rule is applicable for building or construction contracts advertised for bid by a
governmental entity on or after September 1, 1994. This rule is also applicable for those building
or construction contracts entered into on or after September 1, 1994, which are not required by
law to be advertised for bid.
Page 6 of 11
(h) The coverage requirement in this rule does not apply to motor carriers who are required
pursuant to Texas Civil Statutes, Article 6675c, to register with the Texas Department of
Transportation and who provide accidental insurance coverage pursuant to Texas Civil Statutes,
Article 6675c, §40).
(i) The coverage requirement in this rule does not apply to sole proprietors, partners, and
corporate officers who meet the requirements of the Act, §406.097(c), and who are explicitly
excluded from coverage in accordance with the Act, §406.097(a) (as added by House Bill 1089,
74th Legislature, 1995, § 1.20). This subsection applies only to sole proprietors, partners, and
corporate executive officers who are excluded from coverage in an insurance policy or certificate
of authority to self - insure that is delivered, issued for delivery, or renewed on or after January 1,
1996.
Source Note: The provisions of this §110.110 adopted to be effective September 1, 1994,19
TexReg 5715; amended to be effective November 6, 1995, 20 TexReg 8609
Page 7 of 11
T28S 110.110 (d) (7)
"REQUIRED WORKERS' COMPENSATION COVERAGE"
"The law requires that each person working on this site or providing services related to this
construction project must be covered by workers' compensation insurance. This includes persons
providing, hauling, 'or delivering equipment or materials, or providing labor or transportation or
other service related to the project, regardless of the identity of their employeY or status as an
employee.
"Call the Texas Workers' Compensation Commission at 51.2- 440 -3789 to receive information on
the legal requirement for coverage, to verify whether your employer has provided the required
coverage, or to report an employer's failure to provide coverage. if
Page 8 of 11
T28S 110.110(c)(7)
Article _ Workers' Compensation .Insurance Coverage.
A. Definitions:
Certificate of coverage ( "certificate')- A copy of a certificate of insurance, a certificate of
authority to self - insure issued by the commission, or a coverage agreement (TWCC -8I, TWCC-
82, TWCC-83, or TWCC -84), showing statutory workers' compensation insurance coverage for
the person's or entity's employees providing services on a project, for the duration of the project.
Duration of the project - includes the time from the beginning of the work on the project until the
contractor's /person's work on the project has been completed and accepted by the governmental
entity.
Persons providing services on the project ("subcontractor" in §406.096) - includes all persons
or entities performing all or part of the services the contractor has undertaken to perform on the
project, regardless of whether that person contracted directly with the contractor and regardless
of whether that person has employees. This includes, without limitation, independent
-- contractors, subcontractors, leasing companies, motor carriers, owner - operators, employees of
any such entity, or employees of any entity which furnishes persons to provide services on the
project. "Services" include, without limitation, providing, hauling, or delivering equipment or
materials, or providing labor, transportation, or other service related to a project. "Services'
does not include activities unrelated to the project, such as food/beverage vendors, .office supply
deliveries, and delivery ofportable toilets.
B. The contractor shall provide coverage, based on proper reporting of classification codes and
payroll amounts and filing of any coverage agreements, which meets the statutory requirements
of Texas Labor Code, Section 401.011(44) for all employees of the contractor providing services
on the project, for the duration of the project.
C The Contractor must provide a certificate of coverage to the governmental entity prior to
being awarded the contract.
D. If the. coverage period shown on the contractor's current certificate of coverage ends during
the duration of the project, the contractor must, prior to the end of the coverage period, file a
new certificate of coverage with the governmental entity showing that coverage has been
extended.
E. The contractor shall obtain from each person providing services on a project, and provide to
the governmental entity:
(1) a certificate of coverage, prior to that person beginning work on the project, so the
governmental entity will have on file certificates of coverage showing coverage for all persons .
providing services on the project, and
(2) no later than seven days after receipt by the contractor, a new certificate of coverage
showing extension of coverage, if the coverage period shown on the current certificate of
coverage ends during the duration of the project.
Page 9 of 11
F. The contractor shall retain all required certificates of coverage for the duration of the project
and for one year thereafter.
G. The contractor shall notify the governmental entity in writing by certified mail or personal
delivery, within 10 days after the contractor knew or should have known, of any change that
materially affects the provision of coverage of any person providing services on the project.
H. The contractor shall post on each project site a notice, in the text, form and manner
prescribed by the Texas . Workers' Compensation Commission, informing all persons providing
services on the project that they are required to be covered, and stating how a person may verify
coverage and report lack of coverage.
L The contractor shall contractually require each person with whom it contracts to provide
services on a project, to:
(1) provide coverage, based on proper reporting of classification codes and payroll amounts and
filing of any coverage agreements, which meets the statutory requirements of Texas Labor Code,
Section 401.011(44) for all of its employees providing services on the project, for the duration of
the project;
(2) provide to the contractor, prior to that person beginning work on the project, a certificate of
coverage showing that coverage is being provided for all employees of the person providing
services on thoproject, for the duration of the project,
(3) provide the contractor, prior to the end of the coverage period, a new certificate of coverage
showing extension of coverage, if the coverage period shown on the current certificate of
coverage ends during the duration of the project;
(4) obtain from each other person with whom it contracts, and provide to the contractor:
(a) a certificate of coverage, prior to the other person beginning work on the project; and
(b) a new certificate of coverage showing extension of coverage, prior to the end of the coverage
period, if the coverage period shown on the current certificate of coverage ends during the
duration of the project;
(S) retain all required certificates of coverage on file for the duration of the project and for one
year thereafter;
(6) notify the governmental entity in writing by certified mail or personal delivery, within 10
days after the person knew or should have known, of any change that materially affects the
provision of coverage of any person providing services on the project; and
(7) contractually require each person with whom it contracts, to perform as required by
paragraphs (1) - (7), with the certificates of coverage to be provided to the person for whom they
are providing services.
J. By signing this contract or providing or causing to be provided a certificate of coverage, the
contractor is representing to the governmental entity that all employees of the contractor who
will provide services on the project will be covered by workers' compensation coverage for the
duration of the project, that the coverage will be based on proper reporting of classification
codes and payroll amounts, and that all coverage agreements will be filed with the appropriate
insurance carrier or, in the case of a se f insured, with the commission's Division of Self-
Page 10 of 11
Insurance Regulation. Providing false or misleading information may subject the contractor to
administrative penalties, criminal penalties, civil penalties, or other civil actions.
K The contractor's failure to comply with any of these provisions is a breach of contract by the
contractor which entitles the governmental entity to declare the contract void if the contractor
does not remedy the breach within ten days after receipt of notice of breach from the
governmental entity.
Page 11 of 11
PART A - SPECIAL PROVISIONS
STAPLES STREET, PEASE 2
BARRACUDA PLACE TO GOLLIHAR ROAD (BOND 2008)
PROJECT NO. 6469
SECTION A - SPECIAL PROVISIONS
A -1 Time and Place of Receiving Proposals/Pre-Bid Meetin
Sealed proposals will be received in conformity with the official advertisement
inviting bids for the project. Proposals will be received in the office of the
City Secretary, located on the first floor of City Hall, 1201 Leopard Street,
until 2:00 .m., Wednesday-, Februaa 9, 2011. Proposals mailed .should be
addressed in the following manner:
City Secretary's Office
City of Corpus Christi
1201 Leopard Street
Corpus Christi, Texas 78401
ATTN: BID PROPOSAL - STAPLES STREET, PEASE 2
BARRACUDA PLACE TO GOLLIHAR ROAD (BOND 2008)
PROJECT NO. 6469
Any prop osals not physically in possession of the City Secretary's Office at the
time and date of bid opening will be deemed late and non -res onsive. Late
p roposals will be returned unopened to the proposer. The proposer is solel
responsible for delivery to the City Secretary's Office. Delivery of an
proposal, by the proposer, their agent /representative, U.S. Mail, or other
delivery service, to any Cit Z address or office other than the City Secretary's
Office will be deemed non - responsive if not ia3, possession of the City
Secret 's Office prior to the date and time of bid opening.
A pre -bid meeting will be held on Wednesday, February 2, 2011 beginning at 10:00
a.m. The meeting will convene at the Engineering Services Main Conference Room,
Third Floor, City Hall, 1201 Leopard Street, Corpus Christi, TX. and will
include a discussion of the project elements. The pre -bid meeting will be
conducted by the City and will not include a site visit.
No additional or separate visitations will be conducted by the City
A -2 Definitions and Abbreviations
Section B -1 of the General Provisions will govern.
A -3 Description of Project
STAPLES S TREET PHASE 2 - BARRACUDA PLACE TO GOI=MR ROAD (BOND 2008) ; PROJECT NO. 6469;
The Base Bid for this project consists of (approximately) 37,479 square yards of
roadway excavation, 37,479 square yards of flexible base, 34,381 square yards of
HMAC, 37,479 square yards of geo -grid, 8,816 linear feet of curb and gutter,
49,090 square feet of concrete sidewalk, 4,534 linear feet of 1$" -54" RCP, 1,029
linear feet of concrete box culvert, curb inlets, proposed 5' diameter manholes,
470 linear feet of 8 -15" PVC wastewater line, 2,703 linear feet of 6 -12" PVC
water line, 6"-20" gate valves, fire hydrant assemblies, 8" -24" tapping sleeves,
ADA improvements, concrete bus pad and traffic . signal improvements; in
accordance with the plans, specifications, and contract documents.
Alternate No. 1 - ALTERNATE TRAFFIC CONTROL PLAN & CONSTRUCTION SEQUENCING:
Consists of constructing the proposed improvements in three (3) separate parts
or phases.
a. Part 1: Carmel Parkway to Everhart.
b. Pant 2: Barracuda to Carmel Parkway.
- c. Part 3: Everhart to Gollihar / Autotown.
Section A - SP
(Revised 12/15/64)
Page 1 of 26
Alternate No. 2 - CONTINUOUSLY REINFORCED CONCRETE PAVEMENT IN LIEU OF HMAC
(SEQUENCING /TRAFFIC CONTROL SAME AS SHOWN FOR THE SASE SID): Consists of
installing 9" of continuously reinforced concrete pavement (Type P) in lieu of
HMAC from Barracuda to Gollihar / Autotown.
Alternate No. 3 - CONTINUOUSLY REINFORCED CONCRETE PAVEMENT IN LIEU OF HMAC
(SEQUENCING /TRAFFIC CONTROL SAME As SHOWN FOR ALTERNATE NO. 1) : Consists of
installing 9 , 1 of continuously reinforced concrete pavement (Type P) in lieu of
HMAC. Sequencing and phasing limits are the same as shown in Alternate No. 1.
Alternate No. 4 - EXPEDITED SCHEDULE FOR CARMEL PARKWAY TO T (HMAC
OPTION ): provides for additional compensation to the Contractor for an
accelerated construction schedule to complete the project by October 1, 2011
(from Notice to Proceed) . This only applies for the section of work from arms
Parkway to Everhart. This, work would need to be completed in its entirety prior
to October 1, 2011. This includes completing the utility work, concrete work, .
and MMC over ay . This also includes striping and open to traffic without any
barricades or ° traffic control remaining. The anticipated start of Construction
for this project is estimated to be around April 11, 2011 (approximate)
Alternate No. 5 - EXPEDITED SCHEDULE FOR CARMEL PARKWAY TO - SV$RHART (CONCRETE
OPTION): provides for additional compensation to the Contractor for an
accelerated construction schedule to complete the project by October 1, 2011
(from Notice to Proceed). This only applies for the section of work rom arms
Parkway to Everhart. This work would need to be completed in its entirety prior
to October 1, 2011. This includes completing the utility work, concrete work,
and concrete pavement This also includes striping and open to traffic without
any '5 or traffic control remaining. The anticipated start of
Construction for this project is estimated to be around Aril 11, 2011
(approximate)
Alternate No. 6 - WATER LINE IMPROVEMENTS: Consists of approximately 3,492
linear feet of 6 " -12" PVC waterline and associated fittings, 6 11 -12n gate valves,
8"-20 tapping sleeves & valves and fire hydrant assemblies.
A -4 Method of Award
The bids will be evaluated based on the following, subject to availability of
funds
1. Total Base Sid -or-
2. Total Base Bid plus Any Combination of Alternates
The City reserves the right to reject any or all bids, to waive irregularities
and to accept the bid which, in the City's opinion, is most advantageous to the
City and in the best interest of the public.
A -5 Items to be Submitted with Proposal
The following items are required to be submitted with the proposal:
1. 5% Bid Bond (Must reference STAPLES STREET, PHASE 2 - BARRACUDA PLACE TO
GOLLIHAR ROAD (BOND 2008); PROJECT NO. 6469, as identified in the
Proposal)
(A Cashier's Check, certified check, money order or bank draft from any
State or National Bank will also be acceptable.)
2. Disclosure of Interests Statement
Section A - SP
(Revised 22/15/04)
Page 2 of 26
A -6 Time of Completion/Liquidated ]lama es
The working time for completion of the Project will be broken down as follows:
Description
Project Limits
Calendar
Liquidated
Days /
Damages /Day
Alloted
Base Bid
Barracuda to Gollihar /Autotown
350
$1,100
Alternate No. 1
Part 1
Carmel Parkway to Everhart
195
$1,100
Part 2
Barracuda to Carmel Parkway
go
$1,100
Part 3
Everhart to Gollihar / Autotown
65
$1,100
Alternate No. 2
Barracuda to Gollihar /AUtotown
Same as Base Bid shown
(Concrete Pavement) - Sequencing /TCP as
above.
Shown in Base Bid
Alternate No. 3
Barracuda to Gollihar /Autotown
Same as Alternate No. 1
(Concrete Pavement) - Sequencing /TCP as
shown above.
Shown in Alternate No. I
Alternate No. 4
Carmel Parkway to Everhart - Expedited
165
$2,000
Schedule (EMAC Option)
Alternate No. 5
Carmel.Parkway to Everhart - Expedited
165
$2,600
Schedule (Concrete Pavement Option)
Alternate No. 6
Barracuda to Gollihar /Autotown - Water
Included in Base Bid
Line Improvements
The Contractor shall commence work within ten (10) calendar days after receipt
of written notice from the Director of Engineering Services or designee ("City
Engineer ") to proceed.
Any section of work not completed within the allotted contract time as shown in
the breakdown above will be assessed liquidated damages as stated below.
For each calendar day that any work. remains incomplete after the time specified
in the Contract for completion of the work or after such time period as extended
pursuant to other provisions of this Contract, ONE THOUSAND AND ONE HUNDRED
DOX,LARS ($1,100.00) per calendar day, or TWO THOUSAND DOLLARS ($2,000.00) (For
Alternate No. 4 &5) will be assessed against the Contractor as liquidated
damages.. Said liquidated damages are not imposed as a penalty but' as an
estimate of the damages that the City will sustain from delay in completion of
the work, which damages by their nature are not capable of precise proof. The
Director of Engineering Services (City Engineer) may withhold and deduct from
monies otherwise due the Contractor the amount of liquidated damages due the
City.
A -7 Workers Compensation Insurance Coveraae
If the Contractors workers'. compensation insurance coverage for its employees
working on the Project is terminated or canceled for any reason, and replacement
workers' compensation insurance coverage meeting the requirements of this
Contract is not in effect on the effective date of cancellation of the workers'
compensation insurance coverage to-be replaced, then any Contractor employee not
covered by the required workers compensation insurance coverage must not
perform any work on the Project.
Furthermore, for each calendar day including and after the effective date of
termination or cancellation of the Contractor's workers' Compensation insurance
coverage for its employees working on the Project until the date replacement
workers' compensation insurance coverage, meeting the requirements of this
Contract, is in effect for those Contractor employees, liquidated damages will
be assessed against and paid by the Contractor at the highest daily rate
elsewhere specified in this Contract. Such liquidated damages will accumulate
Section A - SP
r (Revised 12 /15/04)
Page 3 of 26
without notice from the City Engineer to the Contractor and will be assessed and
paid even if the permitted time to complete the Project has not expired.
In accordance with other requirements of this Contract, the Contractor shall not
permit subcontractors or others to work on the Project unless all such
individuals working on the Project are covered by workers compensation
insurance and unless the required documentation of such coverage has been
provided to the Contractor and the City Engineer.
A -8 Faxed Proposals.
Proposals faxed directly to the City will be considered non - responsive.
Proposals must contain original signatures and guaranty and be submitted in
accordance with Section B -2 of the General Provisions.
A--9 Acknowledgment of Addenda
,r
The Contractor shall acknowledge receipt of all addenda received in the
appropriate space provided in the proposal. Failure to do so will be interpreted
as non - receipt. Since addenda can have significant impact on the proposal,
failure to acknowledge receipt, and a subsequent interpretation .of non- receipt,
could have an adverse effect when determining the lowest responsible bidder.
A - 10 wage Rates (Revised 7/5/00)
Labor preference and wage rates for Heavy & Highway construction in e ase 9-9
eenfliet eentraeter shall -tise higher wage rate.
Minimum Prevailing Wage Scales
The Corpus Christi City Council has determined the general prevailing minimum
hourly wage rates for Nueces County, Texas as set out in Part C. The Contractor —
and any subcontractor must not pay less than the specified wage rates to all
laborers, workmen, and mechanics employed by them in the execution of the
Contract. The Contractor or subcontractor shall forfeit sixty dollars ($60.00)
per calendar day, or portion thereof, for each laborer, workman, or mechanic 4
employed, if such person is paid less than the specified rates for the
classification of work performed. The Contractor and each subcontractor must
keep an accurate record showing the names and classifications of all laborers, -
workmen, and mechanics employed by them in connection with the Project and
showing the actual wages paid to each worker.
The Contractor will make bi- weekly certified payroll submittals to the City
Engineer. The Contractor will also obtain copies of such certified payrolls from
all subcontractors and others working on the Project. These documents will also
be submitted to the City Engineer bi- weekly. (See section for Minority /Minority �-
Business Enterprise Participation Policy for additional requirements concerning
the proper form and content of the payroll submittals.)
One and one -half (1%) times the specified hourly wage must be paid for all hours
worked in excess of hours in any one week and for all hours worked on Sundays
or holidays. (See Section. B -1 -1, Definition of Terms, and Section B -7 -6,
Working Hours.)
A -11 Coo eration with Public Agencies (Revised 7/5/00)
The Contractor shall cooperate with all public and private agencies with
facilities operating within the limits of the .Project. The Contractor shall
provide a forty -eight (48) hour notice to any applicable agency when work is
anticipated to proceed in the vicinity of any facility by using the Dig Tess at
Section A - SP
(Revised 12/15/04)
Page 4 of 25
1- 800- 344 -8377, the Lone Star Notification Company at 1 -800- 669 -8344, and the
Verizon Dig Alert at 1- 800 - 483 -6279. For the Contractor's convenience, the
following telephone numbers are listed.
City Engineer
Project Engineer
LNV ENGINEERING
Dan S. Leyendecker, P.E.
Ruben T. Perez, Jr., P.E.
Antonio Saenz, III., P.E.
Traffic Engineering
Police Department
Water Department
Wastewater Department
Gas Department
Storm Water Department
Parks & Recreation Department
Streets & Solid Waste Services
A E P
S B C /AT &T
City Street Div. for Traffic
Signal /Fiber Optic Locate
Cablevision
ACSI (Fiber Optic)
KMC (Fiber Optic)
ChoiceCom (Fiber Optic)
CAPROCK (Fiber Optic)
Brooks Fiber Optic (MAN)
826 -3500
883 -1984
883 -1986
(fax)
883 -1984
883 -1986
(fax)
883 -1984
883 -1986
(fax)
826 -3540
886-2600
826 - 1881
. (826 -1888
after
hours)
826 -1800
(826 -1888
after
hours)
885 -6900.
(885 -6900
after
hours)
826 -1875
(826 -1888
after
hours)
826 -3461
826 -1940
1- 877 - 373
-4858
881 -2511
(1- 800 -824 -4424,
after hours)
826 -1946 826 -3547
857 -5000 (857 -5060 after hours)
887 -9200 (Pager 800- 724 - 3624)
813 -1124 (Pager 888 - 204 - 1679)
881 -5767 (Pager 850 -2981)
512/935 -0958 (Mobile)
972 - 753 -4355
A -12 Maintenance of Services
The Contractor shall take all precautions in protecting existing utilities, both
above and below ground. The Drawings show as much information as can be
reasonably obtained from existing as -built drawings, base maps, utility records,
etc. and from as much field work as normally deemed necessary for the
construction of this type of project with regard to the location and nature of
underground utilities, etc. However, the accuracy and completeness of such
information is not guaranteed It is the Contractor's sole and complete
responsibility to locate such underground features sufficiently in advance of
his operations to preclude damaging the existing facilities. If the Contractor
encounters utility services along the line of this work, it is his
responsibility to maintain the services in continuous operation at his own
expense..
In the event of damage to underground utilities, whether shown in the drawings,
the Contractor shall make the necessary repairs to place the utilities back in
service to construct the work as intended at no increase in the Contract price.
All such repairs must conform to the requirements of the company or agency that
owns the utilities.
Where existing sewers are encountered and are interfered with (i.e. broken, cut,
etc.), flow must be maintained. Sewage or other liquid must be handled by the
Contractor either by connection into other sewers or by temporary pumping to a
satisfactory outlet, all with.the approval of the City Engineer. Sewage or
other liquid must not be pumped, bailed or flumed over the streets or ground
surface and Contractor must pay for all fines and remediation that may result if
sewage or other liquid contacts the streets or ground surface. It is also the
Contractor's responsibility to make all necessary repairs, relocations and
adjustments to the satisfaction of the City Engineer at no 'increase in the
Section A - SP
(Revised 12 /15/04)
Page 5 of 26
Contract price. Materials for repairs, adjustments or relocations of sewer
service lines must be provided by the Contractor.
A -13 Area Access and Traffic Control J
Sufficient traffic control measures must be used to assure a safe condition and
to provide a minimum of inconvenience to motorists and the public.
The Contractor will be required to schedule his operations so as to cause
minimum adverse impact on the accessibility of the public. This may include, but
is not limited to, working driveways in half widths, construction of temporary
ramps, etc.
The Contractor shall comply with the City of Cox Christi's Uniform
Barricading Standards and Practices as adopted by the City. Copies of this
document are available through the City's Traffic Engineering Department. The
Contractor shall secure the necessary permit from the CityFs Traffic Engineering
Department.
All costs for traffic control shall be as shown in the proposal. Please see
Traffic Control sheets included in the Construction draw.in s for Base Bid a Lion
and also Alternate options.
A -14 Construction Equipment Spillage and Tracking
The Contractor shall keep the adjoining streets free of tracked and /or spilled
materials going to or from the construction area. Band labor and /or mechanical
equipment must be used where necessary to keep these roadways clear of job -
related materials. Such work must be completed without any increase in the _J
Contract price.
Streets and curb line must be cleaned at the end of the work day or more
frequently, if necessary, to prevent material from washing into the storm sewer
system. No visible material that could be washed into storm sewer is allowed to
remain on the Project site or adjoining streets.
A -15 Excavation and Removals
The excavated areas behind curbs and adjacent to sidewalks and driveways must be
filled with "clean" dirt. "Clean" dirt is defined as dirt that is capable of -
providing a good growth of grass when applied with seed /sod and fertilizer. The
dirt must be free of debris, caliche, asphalt, concrete an d any other material
that detracts from its appearance or hampers the growth of grass.
All existing concrete and asphalt within the limits of the Project must be
removed unless otherwise noted.
All necessary removals including but not limited to pipe, driveways, sidewalks,
.etc., are shown in the removal summary and paid for as shown in the proposal.
A -16 Disposal/ Salvage of Materials -
Excess excavated material, broken asphalt, concrete, broken culverts and other
unwanted material becomes the property of the Contractor and must be removed
from the site by the Contractor. The cost of all hauling is considered
subsidiary; therefore, no direct payment will be made to Contractor.
Section A - SP
(Revised 12/15/04)
Page 6 of 26
A -17 Field Office
The Contractor must furnish the City Engineer or his representative with a field
office at the construction site. The field office must contain at least 120
square feet of useable space. The field office must be air- conditioned and
heated and must be furnished with an inclined table that measures at least 30 x
60 and two (2) chairs. The Contractor shall move the field office on the site
as required by the City Engineer or his representative. The field office must be
furnished with a telephone (with 24 -hour per day answering service) and PAX
machine paid for by the Contractor. There is no separate pay item for the field
office. This item shall be considered subsidiary to the appropriate bid items.
A -18 Schedule and Sequence of Construction
The Contractor shall submit to the City Engineer a work plan based only on
cALmwAR days. This plan must detail the schedule of work and must be submitted
to the City Engineer at least three (3) working days prior to the pre-
construction meeting.
The plan must - indicate the schedule of the following work items:
1. Initial Schedule Submit to the City Engineer.three (3) days prior to the
Pre- Construction Meeting an initial Construction Progress Schedule for
review.
_ 2. Items to Include Show complete sequence of construction by activity,
identifying Work of separate stages and other logically grouped activities.
Identify the first work day of each week.
3. Submittal Dates Indicate submittal dates required for all submittals.
4. Re- Submission Revise and resubmit as required by the City Engineer.
5. Periodic Update Submit Updated Construction Progress Schedule to show
actual progress of each stage by percentage against initial Schedule. The
detailed updated construction progress schedule shall be submitted with the
monthly pay request.
The working time for completion of the.Project will be broken down as follows:
Description
Project Limits
Calendar
Liquidated
Days /
Damages /Day
Alloted
Base Bid
Barracuda to Gollihar /Autotown
350
$1,100
Alternate No. 1
Part 1
Carmel Parkway to Everhart
195
$1,100
Part 2
Barracuda to Carmel Parkway
9t1:2,
,100
Part 3
Everhart to Gollihar / Autotown
6
100
Alternate No. 2
Barracuda to Gollihar /Autotown
Same as Base Bid shown
(Concrete Pavement)- Sequencing /TCP as
above.
Shown in Base Bid
Alternate No. 3
Barracuda to Gollihar/Autotown
Same as Alternate No. 1
(concrete Pavement) - Sequencing /TCP as
shown above.
Shown in Alternate No. 1
Alternate No. 4
Carmel Parkway to Everhart - Expedited
165
$2,000
Schedule (HMAC Option)
Alternate No. 5
Carmel Parkway to Everhart - Expedited
165
$2,000
Schedule (Concrete Pavement Option)
Alternate No. 6
Barracuda to Gollihar/Autotown - Water
Included in Base Bid
Tine Improvements
Section A - SP
(Revised 12 /15/04)
Page 7 of 26
The Contractor shall commence work within ten (10) calendar days after receipt
Of written notice from the Director of Engineering Services or designee ( "City
Engineers) to proceed.
Any section of work not com feted within the allotted contract time as shown in
the breakdown above will be assessed li idated damages as stated below.
For each calendar day that any work remains incomplete after the time specified
in the Contract for completion of the work or after such time period as extended
pursuant to other provisions of this Contract, ONE THOUSAND AND OM HUNDRED
DOLLARS ($1,100.00) per calendar day, or TWO THOUSAND DOLLARS ($2,000.00) (For
Alternate No. 4 & 5) will be assessed against the Contractor as liquidated
damages. Said liquidated damages are not imposed as a penalty but as an
estimate of the damages that the City will sustain from delay in completion of
the work, which damages by their nature are not capable of precise proof. The
Director of Engineering Services (City Engineer) may withhold and deduct from
monies otherwise due the Contractor the amount of liquidated damages due the
City.
Days Allocation for Rain
The contractor shall anticipate the following number of work days lost due to
rain in determining the contract schedule for each part of the contract. A rain
day is defined as any day in which the amount of rain measured by the National
Weather Service at the nearest location is 0.50 inch or greater. No extension
of time will be considered until the expected number of rain days has been
exceeded and the Engineer has agreed that the status of construction was such
that there was an impact detrimental to the construction schedule.
January 3 Days May 4 Days September 7 Days
February 3 Days June 4 Days October 4 Days
March 2 Days. July 3 Days November 3 Days
April 3 Days August 4 Days December 3 Days
Completion shall be based on satisfactory work, completed, tested, in accordance
with the plan, specifications, and contract documents and connected to the
existing system, and accepted by the City for the entire project.
Certificate of Completion
The requirements to issue the. Contractor a Certificate of Completion are the
following (Project Acceptance Procedures Check List):
(1) Final inspection, (Contractor shall have red lined set ready to
submit to City with all corrections /notes - Engineering Services to
coordinate As -Built plan preparation with A/E Consultant).
(2) Inspector prepares final quantities, contractor evaluation form, and
project summary.
(3) Inspector /Engineer verifies that all submittals, payrolls,
Inspection Reports, As- Builts, manuals (in electronic format as
required), SCADA documentation, and other Field Information are
complete.
(4) Contractor reviews and agrees to final quantities or differences
agreed upon by Contractor and Inspector.
(5) Final estimate reviewed by City Construction Engineer.
(6) City Construction Engineer submits to Engineering Administrative
Asst.,.the final estimate and Contractor evaluation form and Project
Acceptance Procedures Check List.
(7) Final payment checklist:
(a) Affidavit that all bills have been paid, "waiver of
Lien"
(b) Submittal of all remaining payrolls _
section A - SP
(Revised 12/15104)
Page 8 of 26
(c) Submittal of MBE letter on what Contractor has actually
subcontracted through end of project
(d) ,
t.'r....i c-t
(8) Final.Acceptance Memorandum prepared by Administrative Assistant.
(9) Administrative Asst. reviews for completeness, funding availability,
prepares financial paperwork.
(10) Administrative Asst. submits to director of Engineering
Services /Operating Department Head for approval and forwarding to
Asst. City Manager.
(11) Final Acceptance memo returned from Asst. City Manager.
(12) Authorization.for payment (AFP) prepared and submitted to Accounting
Department.
(13) Contractor receives final payment after City Council (if required or
Asst. City Manager accepts project.
(14) Administrative Asst. sends letter to Contractor informing him or her
when one -year warranty date begins (Acceptance Memorandum).
_ City acceptance of the project will be described in an Acceptance Memorandum to
the Contractor.
The warranty will begin on'the. date that the Acceptance Memorandum is issued to
the Contractor.
A -19 Construction Project Layout and Control,
The drawings may depict but not necessary include: lines, slopes, grades,
sections, measurements, bench marks, baselines, etc. that are normally required
to construct a project of this nature.
Major controls and two (2) bench marks required for project layout, will be
provided by the City or Consultant Project Engineer.
The Contractor shall furnish all lines, slopes and measurements necessary for
control of the work.
if, during construction, it is necessary to disturb or destroy a control point
or bench mark, the Contractor shall provide the City or Consultant Project
Engineer 48 hours notice so that alternate control points can be established by
the City or Consultant Project Engineer as necessary, at no cost to the
Contractor. Control points or bench marks damaged as a result of the
Contractor's negligence will be restored by the City or Consultant Project
Engineer at the expense of the Contractor.
If, for whatever reason, it is necessary to deviate from proposed line and grade
to properly execute the work, the Contractor shall obtain approval of the City
or Consultant Project Engineer prior to deviation. if, in the opinion of the
City or Consultant Project Engineer, the required deviation would necessitate a
revision to the drawings, the Contractor shall provide supporting measurements
as required for the City or Consultant Project Engineer to revise the drawings.
The Contractor shall tie in or reference all valves and manholes, both existing
and proposed, for the purpose of adjusting valves and manholes at the completion
of the paving process. Also, the City or Consultant Project Engineer may require
that the Contractor furnish a maximum of two (2) personnel for the purpose of
assisting the measuring of the completed work.
Section A - SP
(Revised 12/15/04)
Page 9 of 26
The Contractor shall provide the following certification for documentation and
verification of compliance with the Contract Documents, plans and
specifications. Said compliance certification shall be provided and prepared by
a Third Party or in house independent Registered Professional Land Surveyor or
in house (R.P.L.S.) licensed in the state of Texas retained and paid by the
Contractor. The Third Party R.P.L.S. shall be approved by the City prior to any
work. Any discrepancies shall be noted by the Third Party or in. house Surveyor
and certify compliance to any regulatory permits.
Following is the minimum schedule of documentation required:
Streets:
• All curb returns at point of tangency /point of circumference
• Curb and gutter flow line - both sides of street on a 200 interval;
• Street crowns on a 200' interval and at all intersections.
Wastewater:
• All rim /invert elevations at manholes;
• All intersecting lines in manholes;
• Gasing elevations tap ef pipe and flew line) (TY-POT and RR permits).
Water:
• All top of valves box;
• Valves vaults rim;
C 4- n.vn• — a --
• All rim /invert elevations at manholes;
• All intersecting lines in manholes;
• Gasing elevatiens (t9P ef pipe and flow line) (T-XDGT- and RR per-mite).
A -20 Testing and Certification
All tests required under this item must be done by a recognized testing
laboratory selected by the City Engineer. The cost of the laboratory testing
will be borne by the City. In the event that any test fails, that test must be
done over after corrective measures have been taken, and the cost of retesting
will be borne by the Contractor and deducted from the.payment to the Contractor.
The.Contractor must provide all applicable certifications to the City Engineer.
A -21 Project Signs
The Contractor must furnish and install 2 Project signs.as furnished by the City
and as indicated on the following drawings (Attachment 1, B01M 2008 Project
sign). The signs must be installed before construction begins and. will be
maintained throughout the Project period by the Contractor. The location of the
signs will be determined in the field by the City Engineer.
A -22 Minority /Minority Business Enterprise Participation Policy (Revised 10/98)
1. Policy
It is the policy of the City of Corpus Christi that maximum opportunity is
afforded minorities, women and Minority Business Enterprises to participate
in the performance of contracts awarded by the City of .Corpus Christi in
support of Equal Employment Opportunity goals and objectives of the
Section A - 3P
(Revised 12/15/04)
Page 10 of 26
Affirmative Action Policy Statement of the City dated October, 1989, and
any amendments thereto. In accordance with such policy, the City has
established goals, as stated herein, both for minority and female
participation by trade and for Minority Business Enterprise.
2. Definitions
a. Prime Contractor Any person, firm, partnership, corporation,
association or joint venture as herein provided which has been awarded
a City contract.
b. Subcontractor Any named person, firm, partnership, corporation,
association, or joint venture as herein identified as providing work,
labor, services, supplies, equipment, materials or any combination of
the foregoing under contract with a prime contractor on a City
contract.
C. Minorit Business Enterprise: A business enterprise that is owned and
controlled by one or more minority person(s). Minority persons
include Blacks, Mexican - Americans and other persons of Hispanic
origin, American Indians, Alaskan Natives, and Asians or Pacific
Islanders. For the purposes of this section, women are also
considered as minorities. Minority person(s) must collectively own,
operate and /or actively manage, and share in payments from such an
enterprise in the manner hereinafter set forth:
1. Owned
(a) For a sole proprietorship to be deemed a minority
business enterprise, it must be owned by a minority
person.
(b) For an enterprise doing business as a partnership, at
least 51.0% of the assets or interest in the partnership
property must be owned by one or more minority person(s).
(c) For an enterprise doing business as a corporation, at
least 51.01; of the assets or interest in the corporate
shares must be owned by one or more minority person(s).
2. Controlled
The primary power, direct or indirect, to manage a business
enterprise rests with a minority person(s).
3. Share in Payments
Minority partners, proprietor or stockholders, of the
enterprise, as the case may be, must be entitled to receive
51.0% or more of the total profits, bonuses, dividends,
interest payments, commissions, consulting fees, rents,
procurement, and subcontract payments, and any other monetary
distribution paid by the business enterprise.
d. Minority See definition under Minority Business Enterprise.
e. Female Owned Business Enterprise A sole proprietorship that is owned
and controlled by a woman, a partnership at least 51.0% of whose
assets or partnership interests are owned by one or more women, or a
corporation' at least 51.0% of whose assets or interests in the
corporate shares are owned by one or more women.
Section A - SP
(Revised 12/15/04)
Page 11 of 26
f. Joint venture A joint venture means an association of two or more
persons, partnerships, corporations, or any combination thereof,
founded to carry on a single business activity which is limited in
scope and direction. The degree to which a joint venture may satisfy
the stated MBE goal cannot exceed the proportionate interest of the
MBE as a member of the joint venture in the work to be performed by
the joint venture. For example, a joint venture which is to perform
50.0a of the contract work itself and in which a minority joint
venture partner has a 50.0% interest, shall be deemed equivalent to
having minority participation in 25.0% of the work. Minority members W
of the joint venture must have either financial, managerial, or
technical skills in the work to be performed by the joint venture.
3. Goals
a. The goals for participation by minorities and Minority Business
Enterprises expressed in percentage terms for the Contractor's
aggregate work force on all construction work for the Contract award
are as follows:
Minority Participation Minority Business Enterprise
(Percent) Participation (Percent)
45 % 15 %
b. These goals are applicable to all the construction work (regardless of
federal participation) performed in the Contract, including approved change
orders. The hours of minority employment must be substantially uniform
throughout the length of the Contract and in each trade. The transfer of
minority employees from Contractor to Contractor or from project to project
for the sole purpose of meeting the Contractor's percentage is prohibited.
4. Compliance
a. Upon completion of the Project, a final breakdown of MBE
participation, substantiated by copies of paid invoices, shall be
submitted by the Contractor to the City Engineer.
b. The Contractor shall make bi- weekly payroll submittals to the City
Engineer. The Contractor is to indicate the percent of minority and
female participation, by trade, which has been utilized on the
Project. Along with the request for final payment on the Project, the
Contractor will indicate, in writing, the overall participation in
these areas which have been achieved: The City Engineer may withhold
monthly or final payments to the Contractor for failure to submit bi-
weekly payrolls in a .timely fashion or to submit overall participation
information as required.
A -23 Inspection Required (Revised 7/5/00)
The Contractor shall assure the appropriate Ong inspections by the Building
Inspection Division at the various intervals of work for which a permit is
required and to assure a final inspection
applieable. Section B -6-2 of the General Provisions is hereby amended in that
the Contractor must pay all fees and charges levied by the City's Building
Inspection Department, and all other City fees, including water /wastewater meter
fees and tap fees as required by City.
Section A - SP w
(Revised 12/15/04)
Page 12 of 26
A -24 Surety Bonds
Paragraph two (2) of Section B -3 -4 of the General Provisions is changed to read
as follows:
"No surety will be accepted by the City from any Surety Company who is
now in default or delinquent on any bonds or who has an interest in
any litigation against the City. All bonds must be issued by an
approved Surety Company authorized to do business in the State of
Texas., If performance and payment bonds are in an.amount in excess of
ten percent (10%) of the Surety Company's capital and surplus, the
Surety Company shall provide certification satisfactory to the City
Attorney that the Surety Company has reinsured the portion of the bond
amount that exceeds ten percent (.10°6) of the Surety Company's capital
_ and surplus with reinsurer(s) authorized to do business in the State
of Texas. The amount of the bond reinsured by any reinsurer may not
exceed ten percent (10 of the reinsurer(s capital and surplus. For
purposes of this section, the amount of allowed capital and surplus
will be verified through the State Board of. Insurance as of the date
of the last annual statutory financial statement of the Surety Company
or reinsurer authorized and admitted to do business in the State of
Texas. The Surety shall designate an agent who is a resident of
Nueces County, Texas. Each bond must be executed by the Contractor and
the Surety. For contracts in excess of $100,000 the bond must be
executed by a Surety company that is certified by the United States
Secretary of the Treasury or must obtain reinsurance for any liability
in excess of $100,000 from a reinsurer that is certified by the United
States Secretary of the Treasury and that meets all the above
requirements.. The insurer or reinsurer must be listed in the Federal
Register as holding certificates of authority on the date the bond was
issued."
A -25 Sales Tax Exemption (NO LONGER APPLICABLE)
Seetien —B 6 22, Tex— Exemptien Previeien, is deleted in its entirety and the
feliewing substituted in lieu thereef.
Centraets— fer— imprevemeRts to real — preperty awarded
b-y —the City ef— Gears
Publie
Fla&aee the Texas
• ,
the Cemp-treller of Publie— Aeee�mts of Texas.
of
. . . . . . . . . . . . . .
Section A - SP
(Revised 12/15/04)
Page 13 of 26
A -26 Supplemental Insurance Requirements
For each insurance coverage provided in accordance with Section 13-6 -11 of the
Contract, the Contractor shall obtain an endorsement to the applicable insurance
Policy, signed by the insurer, stating:
In the event of cancellation or material change that reduces or restricts
the insurance afforded by this coverage part, each insurer covenants to
mail prior written notice of cancellation or material chap a to:
1. Name: City of Corpus Christi
Engineering Services Department
Attn: Contract Administrator
2. Address: P.O. Box 9277
Corpus Christi, Texas 78469 -9277
3. Number of days advance notice: 30
The Contractor shall provide to the City Engineer the signed endorsements, or
copies thereof certified by the insurer, within thirty (30) calendar days after
the date the City Engineer requests that the Contractor sign the Contract
documents.
Within thirty (30) calendar days after the date the City. Engineer requests that
the Contractor sign the Contract documents, the Contractor shall provide the
City Engineer with a certificate of insurance certifying that the Contractor
provides worker's compensation insurance coverage for all employees of the
Contractor employed on the Project described in the Contract.
For each insurance coverage provided in accordance with Section B -6 -11 of the
Contract, the Contractor shall obtain an endorsement to the applicable insurance
policy, signed by the insurer, stating that the City is an additional insured
under the insurance policy. The City need not be named as additional insured on
Worker's Compensation coverage.
For contractual liability insurance coverage obtained in accordance with Section
B -6 -11 (a) of the Contract, the Contractor shall obtain an endorsement to this
coverage stating:
Contractor agrees to indemnify, save harmless and defend the City, its
agents, servants, and employees, and each of them against and hold it
and them harmless from any and all lawsuits, claims, demands,
liabilities,. losses and expenses, including court costs and attorneys'
fees, for or on account of any injury to any person, or any death at
any time resulting from such injury, or any damage to any property, J
which may arise or which may be alleged to have arisen out of or in
connection with the work covered by this Contract. The foregoing
indemnity shall apply except if such injury, death or damage is caused
directly by the negligence or other fault of the City, its agents,
servants, or employees or any person indemnified hereunder.
A -27 RegPonsibility for Damage Claims (NOT USED)
Section A - SP
(Revised 12/15/04)
Page 14 of 26
eeverage,
A -28 Considerations for Contract Award and Execution
To allow the City Engineer to determine that the bidder is able to perform its
obligations under the proposed contract, then prior to award, the City Engineer
may require a bidder to provide documentation concerning:
1. Whether any liens have been filed against bidder for either failure to pay
for services or materials supplied against any of its projects begun within
the preceding two (2) years. The bidder shall specify the name and address
of the party holding the lien, the amount of the lien, the basis for the
lien claim, and the date of the release of the lien. If any such lien has
not been released, the bidder shall state why the claim has not been paid;
and
2. Whether there are any outstanding unpaid claims against bidder for services
or materials supplied which relate to any of its projects begun within the
preceding two (2) years. The bidder shall specify the name and address of
the claimant, the amount of the claim, the basis for the claim, and an
explanation why the claim has not been paid.
A bidder may also be required to supply construction references and a financial
statement, prepared no later than ninety (90) days prior to the City Engineer's
request, signed and dated by the bidder's owner, president or other authorized
party, specifying all current assets and liabilities.
A -29 Contractor's Field Administration Staff
The Contractor shall employ for this Project, as its field administration staff,
superintendents and foremen who are careful and competent and acceptable to the
City Engineer.
The criteria .upon which the City Engineer makes this determination may include
the following:
1. The Superintendent must have at least five (5) years recent experience in
field management and oversight of projects of a similar size and complexity
to this Project. This experience must include, but not necessarily limited
to, scheduling of manpower. and materials, safety, coordination of
subcontractors, and familiarity with the submittal process, federal and
state wage.rate requirements, and City contract close -out procedures.
The superintendent shall be present, on the job site, at all tunes that work
is being performed.
2. Foremen, if utilized, shall have at least five (5) years recent experience
in similar work and be subordinate to the superintendent.
Foremen cannot act as superintendent without prior written approval from
the City.
Section A - SP
(Revised 12/15/04)
Page 15 of 26
Documentation concerning these requirements will be reviewed by the City
Engineer. The Contractor's field administration staff, and any subsequent
substitutions or replacements thereto, must be approved by the City Engineer in
writing prior to such supefintendent assuming responsibilities on the Project.
Such written approval of field administration staff is a prerequisite to the
City Engineer's obligation to execute a contract for this Project.. If such -
approval is not obtained, the award may be rescinded: Further, such written
approval is also necessary prior to a change in field administration staff
during the term of this Contract. If .the Contractor fails to obtain prior
written approval of the City Engineer concerning any substitutions or
replacements in its field administration staff for this Project during the term
of the Contract, such a failure constitutes a basis to annul the Contract
pursuant to section B -7 -13.
A -30 Amended "Consideration of Contract" Requirements
Under "General Provisions and Requirements for Municipal Construction Contracts" �
Section B -3 -1 Consideration of Contract add the following text:
Within five '(5) working days following the public opening and reading of the
proposals, the three (3) .apparent lowest bidders (based on the Base Bid only)
must submit to the City Engineer the following information:
1. A list of the major components of the work;
2. A list of the products to be incorporated into the Project;
3. A. schedule of values which specifies estimates of the cost for each major
component of the work;
4. A schedule of anticipated monthly payments for the Project duration.
5. The names and addresses of MBE firms that will participate in the Contract,
along with a description of the work and dollar amount for each firm; and
substantiation, either through appropriate certifications by federal
agencies or signed affidavits from the MBE firms, that such MBE firms meet
the guidelines contained herein. Similar substantiation will be required
if the Contractor is an MBE. If the responses do not clearly show that MBE
participation will meet the requirements above, the bidder must clearly
demonstrate, to the satisfaction of the City Engineer, that a good faith
effort has, in fact, been made to meet said requirements but that meeting
such requirements is not reasonably possible.
6. A list of subcontractors that will be working on the Project. This list
may contain more than one subcontractor for major components of the work if
the Contractor has not completed his evaluation of which subcontractor will
perform the work.
The City Engineer retains the right to approve all subcontractors that will
Perform work on the Project. The Contractor shall obtain written approval
by the City Engineer of all of its subcontractors prior to beginning work
on the Project. If the City Engineer does not approve all proposed
subcontractors, it may rescind the Contract award.
In the event that a subcontractor previously listed and approved is sought
to be substituted for or replaced during the term of the Contract, then the
City Engineer retains the right to approve any .substitute or replacement
subcontractor prior to its participation in the Project. Such approval
will not be given if the replacement of the subcontractor will result in an
Section A - SP
(Revised 12/15/04)
Page 16 of 26
increase in the Contract price. Failure of the Contractor to comply with
this provision, constitutes a basis upon which to annul the Contract
pursuant to Section B -7 -13;
7. A preliminary progress schedule indicating relationships between the major
components of the .work. The final progress schedule must be submitted to
the City Engineer at the pre - construction conference;
8. Documentation required pursuant to the Special Provisions A -28 and A -29
concerning Considerations for Contract Award and Execution and the
Contractor's Field Administration Staff.
9. Documentation as required by Special Provision A -35 -x, if applicable.
10. Within five (5) days following bid opening, submit in letter form,
information identifying type of entity and state, i.e., Texas (or other
state) Corporation or Partnership, and name(s) and Title(s) of
individual(s) authorized to execute contracts on behalf of said entity.
A -31 Amended Policy on Extra work and Change orders
Under "General. Provisions and Requirements for Municipal Construction Contracts"
B -8 -5 Policy on Extra Work and Change Orders the present text is deleted and
replaced with the following:
Contractor acknowledges that the City has no obligation to pay for any
extra work for which a change order has not been signed by the Director of
Engineering Services or his designee. The Contractor also acknowledges
that the City Engineer may authorize change orders which do not exceed
$25,000.00. The Contractor acknowledges that any change orders in an
amount in excess of $25,000.00 must also be approved by the City Council.
A -32 Amended "Execution of Contract° Requirements
Under "General Provisions and Requirements for Municipal Construction Contracts"
B -3 -5 Execution of Contract add the following:
The award of the Contract may be rescinded at any time prior to the date
the City Engineer delivers a contract to the Contractor which bears the
signatures of the City Manager, City Secretary, and City Attorney, or their
authorized designees. Contractor has no cause of action of any kind,
including for breach of contract, against the City, nor is the City
obligated to perform under the Contract, until the date the City Engineer
delivers the signed Contracts to the Contractor.
A -33 Conditions of work
Each bidder must familiarize himself fully with.the conditions relating to the
completion of the Project. Failure to do so will not excuse a bidder of his
obligation to carry out the provisions of this Contract. Contractor is reminded
to attend the Pre -Bid Meetina referred to in Special Provision A -1.
A -34 Precedence of Contract Documents
In case of conflict in the Contract documents, first precedence will be given to
addenda issued during the bidding phase of the Project, second precedence will
be.given to the Special Provisions, third precedence will be given to the
construction plans, fourth . precedence will be given to the Standard
Specifications and.the General Provisions will be given last precedence. In the
event of a conflict between any of the Standard Specifications with any other
Section A - SP
(Revised 12/15/04)
Page 17 of 26
referenced specifications, such as the Texas Department of Public Transportation
Standard Specifications for Highways, Streets and Bridges, ASTM specifications,
etc. , the precedence will be given to addenda, Special Provisions and
Supplemental Special Provisions (if applicable), construction plans, referenced
specifications, Standard Specifications, and General Provisions, in that order.
A -35 City► Water Facilities: Special Requirements (NOT USED)
All -- materials any-- equipment
used in the repair-, reassembly,
items, Whieh eeeld eeffie inte eentaet
with petable water, must eefiferm
MOWN
61 dese3F4:bed in
S r, .t
as the Standard
All -- materials any-- equipment
used in the repair-, reassembly,
items, Whieh eeeld eeffie inte eentaet
with petable water, must eefiferm
FOundatlen (ANSI��F) Standard
61 dese3F4:bed in
S r, .t
as the Standard
All trash generated by the— Sent - aeter er his employees age er
subeeR must be eentained at all times at the water faellity
site Siewing- trash will net — be— allewed. a Gentraeter —s 1j;a3,! —)eel
werA areas— el-ean at all times and remeve all trash Elally.
Section A - SP
revised 12/15/04)
Page 18 of 26
.-- M-. M
W- -� - -- -- fT ....ay =► --
RNw ell
per €erred -enly
detemmined fteet-ding
g l } €ie� ee ieel
the efaa;lifiea
ae
iens g
s��ex x ee
thi-{t 8 belew.
a sc
This
e1 —es
wer-1
a.ael--ee, but is
net limited to,
i iea;iens,
additiens.
ehanges,
seleetiens, furnishing,
ee-a-u-eeting,
f a t
He is reTalarl-y engaged in the eempi*ber- based flenitering ;a3 �
eentrel system business, preferably as applied te-- the
He has per-fermed war-Ira en systems ef eeemipaEable size, type,
eempleXity -as L-equireel is this Gentraet en at least -� -de
3. He has been aetively engaged in the type ef wer-k speeifled
herein €eE at least 5 years.
4.
lie — emgleys --a-- Registered. Pie €essienal Engineer, aGen-tEe'l
Syst Engiaeea', e:e an Bleetrieal Engineer $e supervie!
per-€ewm she wewk - e , b t ; „ _ ; U, e t ; ons .
eempletedamanu€aeturer' s training- eeuFse in senfigur-Ing; nd implementing the feel €ie eat €eEs, RWS' s, and se €twa e
prepesed feE the EentEaet.
f-aei•lity within 400 miles e€ the Picejeet site te maintain,
repair, ealibr- and pregrram the systems speeiffied :7. He shall furnish equipment whieh is Wie preduet ef
.
Section a - Sp
(Revised 12115/04)
Page 29 of 26
A -36 Other Submittals
1. Shop Drawing Submittal The Contractor shall follow the procedure outlined
below when processing Shop Drawing submittals:
a. Quantity: Contractor shall submit seven (7) copies required by the
City to the City Engineer or his designated representative.
b. Reproducibles: In addition to the required copies, the Contractor
shall also submit one (1) reproducible transparency for all shop
drawings.
C. Submittal Transmittal Forms: Contractor shall use the Submittal
Transmittal Form attached at the end of this Section; and sequentially
number each transmittal form. Resubmittals must have the original
submittal number with an alphabetic suffix. Contractor must identify
the Contractor, the Subcontractor or supplier; pertinent Drawing sheet
and detail number(s), and specification Section number, as -
appropriate, on each submittal form.
d. Contractors Stamp: Contractor must apply Contractor's stamp,
appropriately signed or initialed, which certifies that review, -
verification of Products required, field dimensions, adjacent
construction work, and coordination of information, is all in
accordance with the requirements of the Project and Contract
documents.
e. Scheduling: Contractor must schedule the submittals to expedite the
Project, and deliver to the City Engineer for approval, and coordinate
the submission of related items.
f. Marking: Contractor must mark each copy to identify applicable
products, models, options, and other data. Supplement manufacturers
standard data to provide information unique to this Project.
g. Variations: Contractor must identify any proposed variations from the
Contract documents and any Product or system limitations which may be
detrimental to successful performance of the completed work.
h. Space Requirements: Contractor must provide adequate space for
Contractor and Engineer review stamps on all submittal forms.
Section A - SP
(Revised 12/15/04)
Page 20 of 26
I Resubmittals: Contractor must revise and resubmit submittals as
required by City Engineer and clearly identify all changes made since
previous submittal.
j. Distribution: Contractor must .distribute copies of reviewed submittals
to subcontractors and suppliers and instruct subcontractors and
suppliers to promptly report, thru Contractor, any inability to comply
with provisions.
2. Sam The Contractor must submit samples of finishes from the full
range of manufacturers' standard colors, textures, and patterns for City
Engineer's selection.
3. Test and Repair Report
When specified in the Technical Specifications Section, Contractor must
submit three (3) copies of all shop test data, and repair report, and all
on -site test data within the specified time to the City Engineer for
approval. Otherwise, the related equipment will not be approved for use on
the project.
A -37 Amended "Arrangement and Charge for Water Furnished b X the cit " ( NOT USED)
the fellewlngt add-
'IT-he r=entr-aeteE must eemply with the City ef Ger-pus Ghristile Water
Genser-vation and Dr-ought Gentingeney Plan as a-mended (the "Plan") This
eepy of the Plan en the Prejeet site thr-eugheut eenstL-aetien.
_ p n
A -38 Government Entities
on Coverage for Building or Construction Projects for
„
The requirements of "Notice to Contractors 'B ''I are incorporated by reference in
this Special Provision.
A -39 Certificate of Occupancy and Final Acceptance NOT USED
A -40 Amendment to Section B -8 -6: Partial Estimates
General Provisions and Requirements for Municipal Construction Contracts Section
B -8 -6: Partial Estimates is amended to provide that approximate estimates from
which partial payments will be calculated will not include the net invoice value
of acceptable, non - perishable materials delivered to the Project worksite unless
the Contractor provides the City Engineer with documents, satisfactory to the
City Engineer, that show that the material supplier has been paid for the
materials delivered to the Project worksite.
A -41 Ozone Adviso
Priming and hot -mix paving operations must not be conducted on days for which an
ozone advisory has been issued, except for repairs. The City Engineer will
notify Contractor about ozone alert. If 'a delay such as this is experienced, the
day will not be counted as a work day and the Contractor will be compensated at
7 the unit price indicated in the proposal.
Section A - SP
(Revised 12/15/04)
Page 21 of 26
A -42 OSHA Rules a Recrulations
It is the responsibility of the Contractor(s) to adhere to all applicable OSHA
rules and regulations while performing any and all City - related projects and or
jobs.
A -43 Amended Indemnification & Hold Harmless
Under "General Provisions and Requirements for Municipal Construction Contracts"
B -6 -21 Indemnification & Hold Harmless text is deleted in its entirety and the
following is substituted in lieu. thereof:
The Contractor shall hold the City, its officials, employees, - attorneys,
and agents harmless and shall indemnify the City, its officials, employees,
attorneys, and agents from any and all damages, injury or liability
whatsoever from an act or omission of the contractor, or any subcontractor,
supplier, materialman, or their officials, employees, agents, or
consultants, or any work done under the contract or in connection therewith
by the contractor, or any subcontractor, supplier, materialman, or their
officials, employees, agents, or consultants.
The contractor shall hold the City, its officials, employees, attorneys,
and agents harmless and shall indemnify the City, its officials, employees,
attorneys, and agents from any and all damages, injury, or liability
whatsoever from a negligent act or omission of the city, its officials,
employees, attorneys, and agents that directly or indirectly causes injury
to an employee of the contractor, or any subcontractor, supplier or
materialman.
A -44 Change Orders
Should a change order(s) be required by the engineer, Contractor shall furnish
the engineer a complete breakdown as to all prices charged for work of the
change order (unit prices, hourly rates, sub- contractor's costs and breakdowns,
cost of materials and equipment, wage rates, etc.) This breakdown information
shall be submitted by contractor as a basis for the price of the change order.
A -45 _As -Built Dimensions and Drawings (7/5/00)
(a) Contractor shall make appropriate daily measurements of facilities
constructed and keep accurate records of location (horizontal and
vertical) of all facilities.
(b) Upon completion of each facility, the Contractor shall furnish Owner
with one set of direct prints, marked with red pencil, to show as-
built dimensions and locations of all work constructed. As a minimum,
the final drawings shall include the following:
(1) Horizontal and vertical .dimensions due to substitutions/ field
changes.
(2) Changes in equipment and dimensions due to substitutions.
(3) "Nameplate" data on all installed equipment.
(4) Deletions, additions, and changes to scope of work.
(5) Any other changes made.
Section A - SP
(Revised 12/15/04)
Page 22 of 26
A -46 Disposal of Hi Chlorinated water (7/5/00)
The Contractor shall be. responsible for the disposal of water used for testing,
disinfection and line flushing in an approved manner. Contaminants in the water,
particularly high levels of chlorine, will be used for disinfection, and may
exceed the permissible limits for discharge into wetlands or environmentally
sensitive areas. These are regulated by numerous agencies such as T.C.E.Q., EPA,
etc. It will be the Contractors responsibility to comply with the requirements
of all regulatory agencies in the disposal of all water used in the project. The
methods of disposal shall be submitted to the City for approval. There shall be
no separate pay for - disposal of highly chlorinated water. Contractor shall not
use the City's sanitary sewer system for disposal of contaminated water.
A -47 Pre- Construction Exploratory Excavations (7/5/00)
Prior to any construction whatsoever on the project, Contractor shall excavate
and expose all existing pipelines of the project at tie -in locations, possible
conflict areas, and crossings which pass within twenty (20)feet of proposed
pipelines of the project. The Contractor shall survey the exact vertical and
horizontal location of each existing pipeline tie -in /conflict and determine the
pipeline diameter.
For existing pipelines which parallel and are within ten (10) feet of proposed
pipelines of the project, Contractor shall excavate and expose said existing
pipelines at a maximum of 300 -feet O.C., and Contractor shall survey the
accurate horizontal and vertical locations of said parallel pipelines at a
maximum of 300 -feet O.C.
Contractor shall then prepare a report and submit it to the City for approval
indicating the owner of pipelines excavated and surveyed, as well as, the
approximate station thereof, distance to the pavement centerline, elevations of
the top of existing pipelines, and their diameters.
Contractor shall perform no construction work on the project until 1) all
exploratory excavations have been made in their entirety, 2) the results thereof
reported to the Engineer, and 3) un til Contractor receives Engin eer's approval
of the report. .
Exploratory excavations shall be paid for as indicated in the proposal.
Ewpleratery exea�eatians -aid Any pavement repair associated with exploratory
excavations shall be considered subsidiary to the appropriate bid item. paid
€eraeeerdinq to the established priee far pa-vemeat patehing. C ontractor shall
provide all his own survey work effort (no separate pay) for exploratory
excavations.
A -48 Overhead Electrical Wires (7/5/00).
Contractor shall comply with all OSHA safety requirements with regard to
proximity of construction equipment beneath 'overhead electrical wires. There are
many overhead wires crossing the construction route and along the construction
route. Contractor shall use all due diligence, precautions, etc., to ensure that
adequate safety is provided for all of his employees and operators of equipment
and with regard to ensuring that no damage to existing overhead electrical wires
or facilities occurs.
Contractor shall coordinate his work with AFP /CP&L and inform AEP /CP &L of his
construction schedule with regard to said overhead lines.
Section A - SP
(Revised 12/15/04)
Page 23 of 26
Some overhead lines are shown in the construction plans, while others are not.
It shall be the Contractor's sole responsibility to provide for adequate safety
with regard to overhead lines whether shown in the plans or not.
A -43 Amended "Maintenance Guaranty" (8/24/00)
Under "General Provisions and Requirements for Municipal Construction
Contracts ", B -8 -11 Maintenance Guaranty add the following:
"The Contractors guarantee is a separate, additional remedy available to
benefit the City of corpus Christi. Neither the guarantee nor expiration of
the guarantee period will operate to reduce, release, or relinquish any
rights or remedies available to the City of Corpus Christi for any claims
or causes of action against the Contractor or any other individual or
entity."
A -50 Amended Prosecution and Progress
Under "General Provisions and Requirements for Municipal Construction
Contracts ", B -7 Prosecution and Progress, add the following
"Funds are appropriated by the City, on a yearly basis. If funds, for any
reason, are not appropriated in any given year, the City may direct
suspension or termination of the contract. If the Contractor is terminated
or suspended and the City requests remobilization at a later date, the
Contractor may request payment for demobilization /remobilization costs.
Such costs shall be addressed through a change order to the contract."
A -51 Electronic Submittal of Bids
The following paragraph modifies Paragraph 'B -2 -7 - Preparation of Proposal, of
the General Provisions:
The bidder has the option of submitting a computer- generated print -out, in lieu
of, the Proposal (SHEETS: 1 THRU 24 OF 24), INCLUSIVE. The print -out will list
all bid items (including any additive or deductive alternates) contained on
Proposal Sheets (3 THRU 21 OF 24). If the Contractor chooses to submit a print-
out, the print -out shall be accompanied by properly completed proposal pages 1,
2, 22, 23, and 24. A "sample" print out is shown in Attachment 2.
In addition, the print out will contain the following statement and signature,
after the last bid item:
(Contractor) herewith
certifies that the unit prices shown on this print -out for bid items (including -.
any additive or deductive alternates) contained in this proposal are the unit --
prices and no other Information from this print -out.
(Contractor) acknowledges and agrees that the Total Bid Amount shown will be
read as Its Total Bid and further agrees that the official Total Bid amount will
be determined by multiplying the unit bid price (Column IV) shown in this print-
out by the respective estimated quantities shown in the Proposal ( Column II) and
then totaling the extended amounts.
(Signature)
(Title)
(Date)"
Section A - SP
(Revised 12/15/04)
Page 24 of 26
A -52 Dust Control
Contractor shall take reasonable measures to prevent unnecessary dust. Earth
surfaces subject to dusting shall be kept moist with water or applications of a
chemical dust suppressant. when practicable, dusty materials in piles or in
transit shall be covered to prevent blowing dust.
A -53 Regional Trans ortation Authority (RTA) Contract Documents
All RTA Contract Documents (as listed in PART D) shall be executed and submitted
to the City, prior to award of Contract. The RTA Contract Documents shall apply
only to the RTA - identified improvements on this project. The City of Corpus
Christi Standards shall take precedence, for the remainder of the project
elements included on this'Contract.
Section A. - SP
(Revised 12/15/04)
Page 25 of 26
SUBMITTAL TRANSMITTAL FORM
PROJECT: STAPLES STREET, PHASE 2 - BARRACUDA PLACE TO GOLLIHAR ROAD (BOND 2008)
PROJECT No. 6469
DRAWING No. STR 841
OWNER: CITY OF CORPUS CHRISTI
ENGINEER: Antonio Saenz, III PE, LHV, Inc.
CONTRACTOR:
SUBMITTAL DATE: SUBMITTAL NUMBER:
.APPLICABLE SPECIFICATION
OR DRAWING SUBMITTAL
Section A - SP
(Revised 12/15/04)
Page 26 of 26
A G R E E M E N T
THE STATE OF TEXAS §
COUNTY OF NUECES §
THIS AGREEMENT is entered into this 8TH day of MARCH 2011, by
and between the CITY OF CORPUS CHRISTI of the County of Nue ces, State
of Texas, acting through its duly authorized City Manager, termed in
the Contract Documents as "City," and Texas Sterling Construction
Co. termed in the Contract Documents as "Contractor," upon these
terms, performable in Nueces County, Texas:
In consideration of the payment of $6,313,253.50 by City and
other obligations of City. as set out herein, Contractor will
construct and complete certain improvements described as follows:
STAPLES STREET, PHASE 2 BARRACUDA PLACE
TO GOLLIHAR ROAD(BOND 2008)
PROJECT NO. 6469
(TOTAL BASE BID: $6,313,253.50)
according to the attached Plans and Specifications in a good and
workmanlike manner for the prices and conditions set out in their
attached bid proposal supplying at their expense such materials,
services, labor and insurance as required by the attached Contract
Documents, including overseeing the entire job. The Contract
Documents include this Agreement, the bid proposal and instructions,
The General and Special Provisions and Requirements for Municipal
Construction Contracts of the City of Corpus Christi, plans and
specifications, including all maps, plats, blueprints, and other
drawings, the Performance and Payment bonds, addenda, and related
documents all of which constitute the contract for this project and
are made a part hereof.
Page 1 of 3
Rev. Jun -2010
P R 0 P 0 S A L F 0 R M
F 0 R
STAPLES STRLET PRASE 2
B"mACUDAw. PLACE TO GOILTHAR ROAD
(BOND 2008)
PRoJECT No. 6469
DUAFt'NHENT OF WGIAM" RING SERVICES
CITY OF CORPUS CHRISTI, TFJW9
nwas n- rnoNcem sOPM
TAGS 1 or 34
r~
IM a4
PROPOSAL
place, City of Corpus Christi, Texas
Date: February 16, 2010
Texas Sterling Construction Co. ,
Proposal of
-
a Corporation organized and existing under the laws Of the
state of Delaware
OR
a partnership or Individual doing business as
To: The City Of COacpus Ch =iSti, 2eXaLS
Gentlemen:
The undersigned hereby praposes to furnish all labor and
materials, tools, and necessary equipments and to perform the work
required for:
STAPLES STRUT pWSL 2 'AMA PLACJR TO GOLLIEAR ROAD (BOND 200)
PROJECT NO. 6469
at the looations set out by the plans and specifications and in
strict _accordance with the contract: documents for the following
prices, to-Wit
Addendum No. 2
Mtv SM- Ppiwom TOM Attactment no. 4
FAM 2 op 24 Page 2 of 24
STAFI,ES STREET P1 E 2 BARRACUDA PIACE TO GOT+I,IRM ROAD (BOND 2009)
PROJECT N 6469
PART A - STREET IMQROMSNTS
r
SJD
x
�z
TA2
A3
A4
A5
A6
A7
AS
A9
A10
All
Al2
A13
A14
A15
r
A18
MVISM- MPOSAL P024
FAGS 3 ov 24
MUndum No. 2
Attachment No _ 4
Page 3 of 24
III
Iv v
II
MIT PRICE BIB YT3M
QTY &
DESCRIBTION nN YI(;M$S 19 E'iIENS10N
LiNTx
Preparing Right of Way, complete 'n place per
$ -
44.00 STA
100 -FT station.
Concrete Curb and Gutter, oornp2ate in place
3Z Zd0"�
8,816 LF
per linear foot.
Concrete Header Curb, complete in place per
--�-`
1, 23.1 LF
linear foot.
in per
Concrete Driveway, complete place
$
2,291 SY
squa yar d.
Concrete Island (Staples @ Everhart),
1,569 SF
complete in place per a uar_ge foot.
Excavation (Roadway), complete in place per
$��
.37,479 SY
square yard
Hot -Mix Asphalt Concrete Pavement
34.381 SY
Type D
(4 "), complete in place per s are ard.
34,382 SY
Seal Coat, complete in place per igmrE Yard
Emulsified ,Asphalt Treatment (Base Or
$�-
37,479 SY
Subgrade) (MC-30) , complete in place per
—
s uare ard.
Base (Complete In Place) (Type A
37,479 SY
Flexible
Grade 1)(12 "), complete in place per s_guare
$ ��--
yS rd
Base Reinforcement (Type 11 complete $_5 $ 11�� --
37,479 SY
Geogrid
in place per s are ard. 00
in place $ �"3�
Full Depth Pavement Repair, complete
$
2,000 SY
per s note ard.
02 100
-} S
Barricades, Signs and Traffic Handling,
$ 1.� L-
12 MO
complete in place per month
��
Temporary Driveways complete in place per
$ W � ~
2,241 SY
s axe ard.
Temporary Speed Humps, complete in place per $ $
10 EA
each
2 ),
,e�y
S oa
Construction Exits Installed ('Type
$ W _
550 5Y
complete in place Per square yard
in
r
lace -r
Construction Exits Removed, complete p $ $
550 SY
per square yard.
$ $
3 EA
ozone Day, complete in place pex each
��
MVISM- MPOSAL P024
FAGS 3 ov 24
MUndum No. 2
Attachment No _ 4
Page 3 of 24
Iv v
UNIT PRICE BzD ITEM
CIA QTY S
DESCRIPTION
7W FIGURES 1 MT$EfiT0N
3 TEM UNIT
Sign Assemblies with Aluminum Signs (Type H),
$ - $ `
X19 33 EA
complete in place per each
Portable, Changeable Message Sign, complete
!Lo $ (�
X20 720 DAY
place per day.
Erosion Control Log (12" Diameter)(Install &
$_ ? $ �• ��-�
,2Z 2,357 IF
Remove), complete in place per linear foot
Erosion Control Log (12" Diameter)(Remove &
$
2,357 IF
Replace), complete in place per linear foot
Cellulose Fiber Mulch Seeding, complete in
$ 04� $ �t�I �
-
51,916 SF
1 �
place per square foot
Mobilization ! Demobilization, complete in
r� o�
1 LS
r2
r lump sum
--
e Pavement Marking Short Tenn (TAB)
A2 590
low - 2, compl ete in place per each .
Short Term (TAB)
mark Zone Pavement Marking
1,320 EA
Type White, complete in place per each
Reflectorized Pavement Marking Type I (White) 09 �
A27 2,020 LF
4" (Broken) (90mil), complete in place per
$
linear foot.
�
Reflectorized Pavement Marking Type I (White) � $
A28 1,400 LF
8" (Solid) (90mil), complete in place per
$
Linear foot
_
Reflectorized Pavement Marking Type I (White)
A29 600 IF
24 ( Solid) (90mil), complete in place per
line ax toot.
Reflectorized Pavement Marking Type I
$
A30 8,940 LF
(Yellow) 4" (Solid) (90mil), complete in
$ �
'
place per linear foot.
-
Reflectorized Pavement Marking Type
A31 980 IF
(Yellow) 4" (Broken) (90mil), complete in
$ �-
place per linear foot
Reflectorized pavement Marking Type I
A32 350 IF
(Yellow) 24" (Solid) (90mil), complete in
_
place vex linear foot
Type C (White) q
Prefabricated Pavement Marking
$ F0� $
A 94 EA
(Arrow), complete in place per each
Prefabricated Pavement Marking Type C (White)
A34 26
(Word), complete in place per each
Prefabricated Pavement Marking Type C (White) $
--
A35 1 14 EA
(Dauble Arrow), complete in place per each - --�"
Prefabricated Pavement Marking Type C (White) $ S A O
A36 7 EA,
(1.8 ") (Yield Triangle), complete in place
per $
each
Addam&= No. 2
VZn8 D - pp.M8AL F=4
Attadment No 4
7= 4 OF 24
Page 4 of 24
zzs
IV
v
UNIT PRICE
3a7]?
QTY &
DESCRIPTION
IN PIGURES
EXTIMMBxON
3 r-%Sm
UNIT
Pavement Marker Type II - A A
r
g ��`"
_
a 4 ✓
Reflectorized
A37
350 EA
complete in place per each
Reflectorized Pavement Marker Type I -C,
A38
220 EA
complete in place per each
$ 3 2 32 B Lj .?D
PART A -
SUB -TOTAL STRMET nWgOVXMWTS (ITZ,49 Al TIMU
A38)
Addendum NO. 2
asyssm- r�toPOSU ro a
At tachment: No. 4
�AGB 5 QS 24
Page 5 0£ 24
STAPLES STRMT PEASE 2 BARRACUDA PLACE TO GOLLIHAR ROAD (BONN 2008)
PROJECT NO. 64
PART B - ST01W WATER I&ROVEMENTS
r rY
ix I
IV
V
SID QTY &
UNIT PRICE
BID ITEM
DESCRIPTION IN FIGURES
FX`I'ENSIGM
yTEM UNIT
5' Curb Inlet (Type C) (Complete) ,
D $ �33�
5
gl 38 EA
complete in place per each
$ •
5 ' Curb Inlet ('Type c) (Modified)
O $ i coo. �
3 +
B2 fi F1°,
(Complete }, complete in place per each
S
52 EA
5' Curb Inlet Extension (Type E) ,
$ r jy (p� . OCR
$ I, C)5
B3
complete in place per each
5 Storm Water Manhole, complete in place
$�'
$ L: a®
B4 15 EA
per each
Manhole
5' Storm Water Manhole (Modified) ,
$� OOOA
$ ppu . flc7
B5 2 EA
complete in place per each
Trench Safety Water inlets),
$
$ pp
g6 44 ,
complete in place per each
Trench Safety (Storm 'Water Manholes) ,
$ I S 00
$ ( Cjp
87 17 Eh
complete in place per each
Trench Safety (storm Water), complete in
$ I - o
$ �51,0 - 0
5,560 LF
place per linear foot
NB9
Dewatering, complete in place per linear
x.00
$ S`J_ _0 .. O
5, 560 LF
f oot. .
$
18 Reinforced concrete Pipe (Class III),
$ 10
$ 9 - p
- r
- 924 LF
complete in place per linear foot
-
29" Reinforced Concrete Pipe (Class III),
$ IZC
$ _ 9 0 P 9 bo .0
B11 758. LF
complete in place per linearffoot.
30" Reinforced Concrete Pipe (Class III ),
$ -LS. � d�
$ (� $7]`'j e�
B12 95 LF
, nea
complete in place per li r foot•
36" Reinforced Concrete Pipe (Class III),
$; 3_ Q`CK:)
$ �rDZ�, o0
B13 474 LF
complete in place per linear foot
42" Reinforced Concrete Pipe (Class III)
, 215. C)[)
$
$ `I "S. t7
'914 343 LF
complete in place per linea foot.
4 $" Reinforced Concrete Pipe (Class III)
, $ Z. 1 5.0D
$ j t Z L7 ,
Bl5 68. 8. LF
complete in place per lineal t-
54 Reinforced Concrete Pipe (Class 111) , s2 2-O.
$
Bi& 1, 249 LF
complete in place per linear foot•
I►�deadum rife. 2
nwilggp ram
xttad meat NO. +4
wMa 6 OF 24
Page 6 of 24
�
II
III
rV
i
UNIT PRICE
ElD =TZK
j2% ID
QTY &
DESCRIPTION
IN FILMS
LXTEMS10m
UNIT
Concrete Box Culvert (5'X5'}, complete in
$ yip
$ �t0i�.�
g17
67 LF
place per linea r foot•
Concrete Box Culvert (5'X5'), complete 'n
$ p.�
$ 3�1�i 0.0
-018
$50 LF
place per linear foot
concrete Box Culvert (6'X5'), complete in
$ �
$ •�
5319
112 LF
place per linear foot
Post Televised Inspection (Storm Water),
linear
+�
$ ' �
$ 9 �D .�
B20
5, 560 LF
complete in place per ot.
Sidewalk Drains, complete in place per
$
$ � �. O . �IDC7
B21
5 EA
linear .foot
l S � D 54P.S. on
PART B -
SUB -TOTAL STORM WATER ZMPROVEtV -1 TS (ITEMS
B1 TM B211
Aftudum No. 2
nEU'tszD rnOVOSnt FORM Attaftont No. 4
FAGS 7 A Cr 24 INSO 7 of 24
STAPLES STREET PHASE 2 BARRACUDA PLACE TO GOLLIHAIR ROAD (BONE] 2008)
PROJECT NO. 6469
PAR' -- C - - WASTEWATER I11PROVEMERTS
z iI II
BID =TM
UNIT PRICZ EXTE14SION
SID QTY & DESCRIPTION TN FIG=S
STEM UNIT
Cl
C2
C3
C4
C5
G6
C7
C8
C9
C10
C11
C12
C13
C14
Remove B" VCP & Replace with V PVC (SDR
$ ,L�J cx=�
It
228 LF
26}(10' --14' Depth), complete in place
per linear foot.
Remove 10" VCP & Replace with 10" PVC
in
$ 1 ZS-o® $
100 LF
complete _ p
(SDR 26) (18 . 20 Dept
place per linet•
Remove 12" VCP & Replace with 12" PVC
in
$ � r J'
$ ' 3C 9 .C)
V
62 LF
(SDR 2.6) (1 4' -18' Depth)„ complete
place per linear foot.
Remove 15" VCP & Replace with 15" PVC
$1105
$ �� Zoo. ��
80 LF
(SDR 26)(18' -20' Depth ), complete in
place per linear foot
Trench Safety (Wastewater), complete in
470 LF
place per linear' foot-
4 Dia. Wastewater Manhole (56VF)
3 FA
(Fiberglass), complete in place per
each
4' Dia. Wastewater Manhole (Extra Depth)
$ 2-y5 -o ®
$ 1`'>L.5
45 VF
(Fiberglass) , complete in place per
vertical foot.
Remove 4' Dia. Wastewater Manhole,
$ 1 Do.
$ Z 1 00. 00
3 EA
complete in place per each
—^
5' Dia. Wastewater Manhole (:�L6VF)
$ r--,
$
2 EA
(F1.berglaas), complete in place per
each
5' Dia. Wastewater Manhole (Extra Depth) $ � O
$ q 00
1
22 VF
(Fiberglass), complete in place per
vertical foot•
Trench Safety (Wastewater Manholes).
$
$ , - C10
5 EA
complete in place per each
By -pass pumping for 'Wastewater Manholes,
$ ? ��,
$ �o ®o 00
5 EA
complete in place per each
pre and post Televised Inspection
$ 3.50-
$ j . 00
470 LF
(Wastewater), complete in place per
linear foot.
Utility Pavement Repair, Complete in
$11.5a
$ n r J -(-P
582 SF
place per s are Toot -
Ad4gmdum No. 2
VZW Yom
Attsebment wo _ 4
VA= 6 o r 24
Page B of 24
PART C _ SUB - TOTAL WASTMMTrR IMPROVEMNTS (ITEMS C1 THRV C17) : $ I, k. SC> , 5 o p
AddegdUm Na . 2
Psvxssn—rRoRoBKL sons Attachment Ho . 4
gAm 9 o3p 24 gage 9 a� 24
ZII
ry
v
BIM i�
]BID
QTY &
DESCRIPTION
zrt�I� PRICE
�x�Nrsi
STEM
UNIT
IN FIGMS
EA
Wastewater Connections, complete in
$ ��5�
$ pin
C15
3
place per each
Adjust Wastewater Manholes, complete in
$ 3co.0
$ d O
C16
12 RA
place per each
Wastewater Utility Allowance, complete
$ 25,000.00
$ 25 000,00
C17
1 LS
in place per lump sum
"
PART C _ SUB - TOTAL WASTMMTrR IMPROVEMNTS (ITEMS C1 THRV C17) : $ I, k. SC> , 5 o p
AddegdUm Na . 2
Psvxssn—rRoRoBKL sons Attachment Ho . 4
gAm 9 o3p 24 gage 9 a� 24
STAPLES STREET PHASE 2 BARRACUDA PLACE TO GOLL'nn ROAD (BOND
2008 )
III
Iv I
PROJECT NO. 6469
ONIT PRICE
PART D - ADA ImpR4VEbffi
BID
QTY &
DESCRIPTION
ix
Yxz
N
V
UNIT PRICE
HID ITEM
BID
QTY
DESCRIPTION
IN FIG MS
EXTENSION
::.rTTim
UNIT
Concrete Shelter Pad, complete in place
�Q
Concrete Sidewalk, complete in place
$
---=��
Dl
g9,09D SF
per square ot-
Concrete Curb Ramp, complete in place
$ �, ,QQ
$ � 5® `1 39 .0
D2
2, 967 5F
per square foot
Reflectorized Pavement Marking Type
s�
$ Q .170
D3
1,920 LF
(White) 12" (Solid) (90zuil), complete
in place per linear foot
Reflectorized Pavement Marking Type I
$ 1
I i O r D. ®c)
1
D4
1,720 LF
{White) 24' (Solid) (90mil), Complete
-
in place per linear r foot.
PART D - SUB -TOTAL Ank IMMOVOENTS (ITEMS DI TiRtU D $ 3Lo3 1 $ . C®
FART E - RTA ne ROVMUNTS
I
II
III
Iv I
V
ONIT PRICE
BID ITEM
BID
QTY &
DESCRIPTION
IN FIGURES
E)[TEl�3I4N
STEM
UNIT
Concrete BUS Pad, complete in place per
s Ioo.po
$ ( r C)00. 4
E 1
690 SY
square yard .
Concrete Shelter Pad, complete in place
�Q
$ ,� �Q��,{
E2
204 Sy
per s yard
PART E - MM-TOTAL 1tTA I1�RVH•UIENTS (ITEM$ E7. THRU E2) : $
vi a�sEn- MPOSAL romd !►Lt PAGE 1C OF 24 24
PAl2T V — MSS IWROVEMENTS
T
i2
IIT
IV
v
SID
QTY &
UNIT PRICE
SID ITEM
ITEM
UNIT
DESCRIPTION
IN FIGURES
mmxlgsION
F1
8,220 LF
2" Fiber Optic Conduit, complete in
$ CC)
$ DO
Gl
place per linear foot
F2
8 EA
Fiber Optic Ground Box, complete in
$�aZ�,
$ .�
place per each
BART F - suB -TOTAL Dais I1 M OVED NIS (ITEMS P1 THRU F2) :
I
II
III
IV
V
SID
QTY &
UNIT PRICE
Ell) ITEM
ITEM
UNIT.
DESCRIPTION
IN FIGURES
EXTENSION
94 LF
Drill Shaft (TR SIG POLE) (30 IN),
$
$ 0�.D
Gl
complete in place per linear foot
G2
26 LF
Conduit (PVC) (SCHD 40) (2 "), complete
71
312.0
in place per linear foot
G3
354 LF
Conduit (PVC) ( SCHD 40 ) ( 3 11 ) , complete
$ 00
s O I 'S. 00
in place per linear toot
G4
42 LF
Conduit (PVC) (SCHD 40) (4 "), complete
$ ZI •00
$ $$Z .C)r->
In place per linear foot
--
396 LF
Elec. Condr. (No. 6) Bare, complete in
$ I
$ 5 cc)
G5
place per linear foot
G6
52 LF
Elec. Condr. (No. 6) Insulated
Elec.
$ 1.(d�
in .Place per linear foot
G7
},242 LF
Elec- Condr. (No. 12) Insulated,
$���
$ I '�
complete in place per linear ,foot.
G8
414 LF
Tray Cable (4 Condr.) (12 AWG), complete
$
$ `1 Z C)
in place per linear foot
G9
5 EA
Ground box TY D (162922) wlApron,
$ -�
complete in place per each
�_--
Gio
1 EA
Ele. Sxv. TY D 120/240 060 (NS) AL (E)
$ 2- L- 1 P
$ _ 2.!A � O
SP (0) , complete in place per each
Gil
1 EA
Install HWY TRF SIG (Isolated),
complete in place per each
Addendum No. 2
asvls�o- rxi»osAS. �rxrns Atracbmint No. 9
PAaz 11 Or 24
Page 12 of 24
PART G - SUB -TOTAL TRAFFIC SIC14AL IMPROVEMENTS (ITEMS G1 TRW 029):
Addeaduaa No . 2
Auvx81W PROPOSAL EOM achment Ito. 4
me a JL2 OP 24 Att Page 12 of 24
Iv
V
QTY &
PRICE
SI;D XTEM
DESCRIPTIpN
UNIT
xN FIGURES
EX`DENSIOII
FC12
Sack Plate (12 IN)(3 SEC), complete in
$ S5.00
7 EA
place per each
Back Plate (12 iN)(5 SEC ), complete in
$ + '� 00
3 E A place per each
-.LLD, —
Ped. Sig. Sec. (12 IN)LED(2
in
S�J� OO
$
�•
G14
S EA Indications) Countdown, complete
place per each
veh. Sig. Sec. (12 IN)LED(GRN ARW),
3
$ Z'
$ 5 p
GI5
EA complete in place per each
G16
10 EA Veh. Sig. Sec. (12 IN) LET) (GRN) ,
$ ZS.3 ,C)
-
S 2 , UO
complete in place per each
Veh. Sig. Sec. (12 IN)LED(YEL ARW),
$ ��$
$
G1 #
3 EA
complete in place per each
G18
1 0 EA Veh. Sig. Sec. (12 IN)LED(YEL),
$ J•o
S O Cj
complete in place per each
Veh. Sig. Sec. (12 IN) LED (RED) ,
G19
10 EA
complete in place per each
Trf. Sig. Cbl. (TY A) (14 RWG) (10
linear
$�S
$ lo L i c)
G20
72 LF Condr.), complete in place per
._
foot
Trf. Sig. Cbl. (TY A) (20 AWG) (10
linear
QQ
S ti.l
$ �"�•# O
G21
438 LF Condr.), complete in place per
foot
I EA Trf. . Sig. pl. Am. (S)1 ARM (28' LUM &
$- I� `„�
$ . U�
G
ILSN, complete in place per each.
fi
3 EA Trf. . Sig. pl . rim. (S)1 ARM (32') LUM 6
$ 5,
o $ _1S • 0 9 D o a
`-�
G23
ILSN, complete in place per each.
Ped. Pole Assembly, complete in place
$I 2I
$ --a ( 0 9 0, U0
G24
3 EA
per each
8 EA Ped Detect. (2 Inch Push Stn.),
y�
G25
complete in place per each
PTZ Camera Assembly, complete in place '3 (
$ 3�4 (
G26
1 EA
per each
—
ILSN (LED) (6S) , complete in place per�
$ • ��• U1 7
G27
4 EP. each
r _ - L
PTZ Communication Cable (COAXIAL),
�t�
$ 5.02
G25
26 LF
complete in place per linear -
Radar Advance Detection Device,
$��� Dm.
$ �Q�
G29
4 complete in place per each
— '�
PART G - SUB -TOTAL TRAFFIC SIC14AL IMPROVEMENTS (ITEMS G1 TRW 029):
Addeaduaa No . 2
Auvx81W PROPOSAL EOM achment Ito. 4
me a JL2 OP 24 Att Page 12 of 24
PART H - GA 1WROVRMENTS
z
xx
III xv V
BID
QTY &
UNIT PRICE $ID ITEM
ITEM
UNIT
DESCRIPTION
IN FIGURES EXTENSION
BID ITEM
ITEM
UNIT
H1
IN FIGURES
Adjust gas valves, complete in place per $ �J
Il
15 EA
each
SUBTOTAL GAS 1147 S OVMaNT8 - (ITEM H1) :
PART I - WATER nWROVMGNTS
•�I
Z
IT
IxI
IV
V
BID
QTY S
UNIT PRICE
BID ITEM
ITEM
UNIT
DESCRIPTION
IN FIGURES
EXTENSION
EN
Il
6" PVC Waterline (C900 DR 1$), complete
$-
$ ..- 176 5S -
321 LF
in place per linear foot
12
LF
'8" PVC Waterline IC900 DR 1$), complete
$
$ r(O�
2,161
in place per linear foot
—5�—
PVC Waterline (C905 DR 18) , complete
$ (L/ J
I3
221 LF
in place per linear foot
in
Remove & Replace 20" DIE Waterline,
$
(8'7�� —
I$
60 LF
complete in place per linear foot
6" Gate Valve, complete in place per
$ 7�3�
$"
I5
3 EA
leach
8" Gate Valve, complete in place per
$ to-10
$
I6
29
each
12 Gate Valve, complete in place per
x7
5 EA
each
�-�-
20" Gate Valve, complete in place per
++
$ `
18
2 ER
each
w
19
2 EA
6" 11 Bend, complete in place per each
_
$
$
in each
$
$ 2 14
110
21 EA
6" 45 Bend, complete place per
00
rRrrl 00
$ 0 �
I11
2 EA
8 11 Bend, complete in place per each
$
-/-
Addendum ND. 2
1tLv1ssD- PR0VosaL ram Att�ctlment 170. 4
RAm 13 OR 24 Page 13 of 24
x
IY
YII
O�
[
$ '�
V
]BID
QTY &
UNIT PRICE
DID ITEM
STEM
UNIT
DESCRIPTION IN P`IGURES
MTEwstoN
$
125
[-
4-3
112
3 EA
8", 22'x Send, complete in place per each
$
B" X 6" Reducer, complete in place per
$
$ -^
in each
6 EA
each
113
71 EA
8" 45 Bend, complete place per
" in each
s
�2(�VL�
12$
17 EA
&�
214
9 EA
12 45 Bend, complete in place per each
mP
�
Hydra -Stop for 20" DIP Waterline,
115
4 EA
24" 45 Bend, complete in place per each.
2 EA
complete in place per each
8" X 6 Tapping Sleeve, complete in place
$ �
$ ZS
Ti6
1 EA
per each
2,015 LF
place per linear foot
8" X 0" Tapping Sleeve, complete in place
$ , �
$
217
1 EA
per each
use
20" X B" Tapping Sleeve, complete in
$ �jZ [,�
$ 104 -r -°
118
2 ZA
place per each
20" X 12" Tapping Sleeve, complete in
$� 4 ,JrQ�
I1
1
place per each
24" X 8" Tapping Sleeve, complete in
$
$
I20
1D EA
place per each
1 EA
24" X 12" Tapping Sleeve, complete in
77(05
5
Ill
place per each
122
1 EA
12" X 6 Tee, complete in place per each
$ ' f
$ _
in each
123
2 EA
12" X B" Tee, complete place per
in
$
$ JZQ�
I24
4 EA
8" X S^ Tee, complete place per each
RMMM- PROPOSRL POW
pp= 14 OF 24
Addendum ao _ 2
Attacimmat No. 4
Paga 14 of 24
"
O�
[
$ '�
+�
8 _
I25
3 EA
B" X 5 Tee, complete in place per each
_ ✓�
2 EA
8" X 4" Reducer, complete in place per
$
125
each
B" X 6" Reducer, complete in place per
$
$ -^
127
6 EA
each
" in each
s
�2(�VL�
12$
17 EA
6 Plug, complete place per
mP
�
Hydra -Stop for 20" DIP Waterline,
$
$
129
2 EA
complete in place per each
Remove 4" -12" 'Waterline, complete in
$ /
$
X30
2,015 LF
place per linear foot
RMMM- PROPOSRL POW
pp= 14 OF 24
Addendum ao _ 2
Attacimmat No. 4
Paga 14 of 24
0
PARS' I - SUB- -TOTAL WATER IMP ROVEKENT3 (IT MS 21 THRU 142) :
Rxvxs�- raQrrasaz.
NOM
pAre is or 24
�+ddaaaum I3o . 2
Attachimt No. 4
page Is of 2 4
IV v
BID
QTY &
UNIT? PRICE BM IrXIM
ITEM
UNIT
DESCRIPTION
IN FIGEMES EXIMNSXON
Fire Hydrant Assembly with B° X 6" Tee
4
131
11 EA
and 6" gate valve, complete in place per $ $ f C) --
each
132
1 EA
Fire hydrant Assembly with 6" X 6" Tee �� ��
and 6" gate valve, complete in place per $ 4 1" $
each
133
3 EA
Fire Hydrant Assembly with 6" gate valve, $ 7� $����
L
complete in place per each
139
7 EA
Water Service, complete in place per
$ l / .r $ � 0
each
135
6,824 5E
'
Utility Pavement Repair, complete in $ $ 6aZ3��
place per square foot
2' 63 LF
Trench Safety (Waterlines), complete in
$
I36
place per linear fact
15 EA
Waterline Connection (6 ", 8 ", 12" & 16 "), $
T37
complete in place per each
Air Release Valve Assembly, complete in ¢
$ $ 010
138
1 EA
" � f �
place per each
139
200 LF
Excavation Trench, comple rr�
Exploratory complete
$ �F $
in place per linear foot
Exploratory Excavation Spot, complete in $ Gro 0r��
140
14 EA
place per each `
141
33 EA
Adjust water Valves, complete in place $
per each
I42
1 ZS
Water Utility Allowance, complete in $20,DDO.OD 20,pp0.00
„
place per lump sum
PARS' I - SUB- -TOTAL WATER IMP ROVEKENT3 (IT MS 21 THRU 142) :
Rxvxs�- raQrrasaz.
NOM
pAre is or 24
�+ddaaaum I3o . 2
Attachimt No. 4
page Is of 2 4
X
STAPLES STREET PHASE 2 BARRACUDA PLACE TO GOLLIHAR ROAD (BOND 2008)
PROJECT NO. 5469
AL.TERMATF. NA. 3 - ATMERVAT'R TRAEPTO MUTR O1. PIJM & SE013ENCING
I
iI
IZI
IV V
BID
QTY &
QTY &
TWIT PRICE BIa ITEM
UNIT PRICE
SID ITEM
DESCRIPTION
UNIT
ITEM
UNIT
EX
IN FIGURES L XgJNSION
37 479
6„ Time Stabilized Subgrade (6$),
Additive /Deductive Alternate to construct
$ 5 �
5Y
`
the project in three (3) phases, as shown
in the plans in lieu of the Traffic
Flexibly Base (Complete in Place) ('Type A
Control & Sequencing included in the Base
1 37,479 BY
Grads 1) (6 , complete in place per
$
Bid. The limits for this sequencing
00 a®
A1-1
1 LS
consist of (1) Carmel Parkway to
$ $
Everhart (includes the Everhart
OQ
�0&45(
A2 -3
intersection up to Sta. 78 +00),(2)
(1 Bond Breaker, complete in place per
$
O
Barracuda to Carmel Parkway, and (3)
square yard
Everhart to Gollihar /Autotown, complete
Continuously Reinforced Concrete Pavement
in place per lump sum
�Q OJ
StMTOTAL ALTERNATE NO. 1 - (ITEM Al -1): $ 006cr_>
ALTERMTE NO. 2 - CONTINUOSI,Y REINFORCED CONCRETE PAVEMENT IN LIEU Off' MAKa
(SEODENCING /TRAFFIC CONTROL &AMli AS SHOWN FOR THE SAS.L BID)
I
II
III
IV
V
BID
QTY &
UNIT PRICE
SID ITEM
ITEM
UNIT
DESCRIPTION
IN FIGURES
EX
A2 -1
37 479
6„ Time Stabilized Subgrade (6$),
$ �1
$ 5 �
5Y
`
complete in place per square Yard
Flexibly Base (Complete in Place) ('Type A
A2 -2
1 37,479 BY
Grads 1) (6 , complete in place per
$
$
square yard
Type D Hot - Misr Asphalt Concrete Pavement
OQ
�0&45(
A2 -3
34,381 BY
(1 Bond Breaker, complete in place per
$
O
square yard
Continuously Reinforced Concrete Pavement
/���
�Q OJ
A2 -A
34,381 SY
(9 ") ('Type P), complete in place per
$
square yard
A2 -5
(34,381)
Delete Type D Asphalt Concrete Pavement
$
Ter
SY
(4 "), complete in place per square yard
-
A2 -6
(34,381)
Delete Seal Coat, complete in place per
$ 2
$t 6
BY
square re yard.
asvrssn - PROPOSAL POPM
PACE 16 OF 24
Addeudam No. 2
Attachftnt No. 4
Page 16 of 24
STAPLES STMT PHASE 2 BARRACUDA PLACE To GOLL'M ROAD (BOND
2008)
pROJLCT NO. 5469
zI
III
IV
v
{ SEQUENCING / TRAFFIC COWMOL SAME AS S"DM FOR THE ALTZ"hTE No . )
UNIT PRICE
B113 ITEM
BID
QTY &
AE$CRIPTION
1N PTGMS
EXTMgSl0N
='1'EM
UNIT
BID I',CM
BYD
QTY &
DESCRIPTION
IN gxGURES
Delete Flexible Base (Complete in
in
$. L�
$( ? r
A2
(37,479)
Place) (Type A Grade 1) (12 ) , complete
- - _
(6$),
SY
place per square yard
6" Lime Stabilized Subgrade
( 37 479J
Delete Geogrid Base Reinforcement (Type
$ 3 00
$ ( 112-437 )
A2 -$
r
5X
1), complete in place per square yard
Flexible Base (Cemplats In Plaae)(Type A
/J
-8) .
43 7, I 7
Grade 1) (61T) , complete in place par
$ _
SVSTOTAL ALTERNATE NO. 2 - (ITEM A3--1 THRU ITM A2
STAPLES STMT PHASE 2 BARRACUDA PLACE To GOLL'M ROAD (BOND
2008)
pROJLCT NO. 5469
A,LTEMATE go_ 3 - CONTINUOSLY p Mr07,tCED CONCRETE YAVEMNT IN LIEU OF
HMAc
{ SEQUENCING / TRAFFIC COWMOL SAME AS S"DM FOR THE ALTZ"hTE No . )
Z
ZZ
ITT
IV
V
UNIT PRICE
BID I',CM
BYD
QTY &
DESCRIPTION
IN gxGURES
E]C`1'EN'SZOY�
ITEM
UNIT
(6$),
6" Lime Stabilized Subgrade
$
A3 - 1
_
37,479 SY
complete in place per s are 2.rd.
Flexible Base (Cemplats In Plaae)(Type A
/J
A3
37,478 SY
Grade 1) (61T) , complete in place par
$ _
$
square Y�erd
Type D Hot -Mix Asphalt Concrete Pavement
+�Q
$ `_��/_ -�
A3 - 3
34,381 SY
(1 Bond Breaker, complete in place per
—
FI13
square Yard
Continuously Reinforced Concrete Pavement
/ l
�$
4 I J !
-4
3q, 3g1 gy
{g ") {Type P) , complete in place per
S
—
soars axd.
Pavement
dQ
�
(34, 381)
Delete Type D Asphalt Concrete
A3 -5
SY
(4 , complete in place per s are ard.
_
(3A•381)
Delete Seal Coat, complete in place per
$
o
A3 -6
SY
s oars ard.
Flexible Base (Complete
Delete in
A3 -7
537, 479)
, 4
Place) (Type A Grade 1) (12 "), complete in
$
place per scmare yard.
Adde taum No. 2
RMSM- PROPGBA . roRK
Attaalamt No. A
pAm 17 OF 24
Page 17 03= .24
I
Ix
III TV V
SID
QTY &
UNIT PRICE BID 7Tg�„
DESCRIPfiION
I TEM
UNIT
IN FIGURES EXT "sanN
A3 -8
(37,479)
Delete Geogrid Base Reinforcement (Type r
$ ® $( �1
SY
11 , complete in place per square yard
SUBTOTAL ALTERNATE NO. 3 - (ITEM A3 -1 TMW ITEM A3 - $ 4 I Z 7 - 75 6 30
30
STAPLES STREET PHASE 2 BARRACUDA PLACE TO GOLL,IHAR ROAD (BOND 2008)
PROJECT NO. 6469
Ar, No. d - mxPrnx n scMn Slr.R VOR CAPIML PARKWAY TO EVEMORT {MAC OPTIomi
Z
II
iii IV V
SID
QTY &
UNIT PRICE BID ITEM
DEBCRIPTZ4N
ITEM
UNIT
IN FIGURES EXTENSION
Compensation for an Accelerated
Construction Schedule to complete
construction from Carmel Parkway to the
Everhart intersection (includes the
EVerhart int63COOCt3.on up to Sts. 78 +00)
"^
A4 -1
1 LS
prior to Octobez� 14 2011. This includes ' /(��' $
$
all construction., including utilities,
concrete woxk & roadway items up to
drivable surface (2" HMAC), Liquidated
damages associated with this work shall
be 22,000.00 per calendar day, complete
SUBTOTAL ALTERNATE NO. 4 - (ITEM A4 -1) : $ tccco
Addendum No . 2
Rsvrssn pxoPasA?. row Attach
me�st No. �
P AM 18 of 24
Page 19 of 24
AT of M NO. 5 - FIMMTTM srRMirrM PnR rARMEi. MAMY Td. L% RHM1 T LCCNCRETE OPTICNI
=
II
III ry y
SIA
QTY &
MICE BID ITEM
fI
=TEM
UNIT
DESCRIPTION
IN Gti Z ZXTP
BID ITS!
ITEM!
Compensation for an Accelerated
DESCRIPTION
IN E'IGURE3
Construction schedule to complete
A6 - 1
569 LF
construction from Carmel Parkway to the
r0�
$
Everhart intersection (includes the
in place per linear foot
Everhart intersection up to Sta. 78 +00)
-�
1 L5
prior to Oatab_er 14, 2011 This includes $ $
8" PVC Waterline (0900 DR 18), complete
$ —
all construction, including utilities,
concrete work & roadway items up to final
riding surface (Continuously Reinforced
7 EA
6" Gate Valve, complete in place per
Concrete), Liquidated damages associated
with this work shall be $2,000.00 per
SUBTOTAL ALTERNATE NO. 5 - (ITEM AS-1)
STAPLES STREET PHASE 2 BARRACtMA PLACE TO GOLLIHAR ROAD (BM 200$)
PROJECT NO. 6469
ALTERNATE NO. 6 - WATER IMPROWMMS
I
II
III
TV
V
HID
Q'2Y &
UNIT PRICE
BID ITS!
ITEM!
UNIT
DESCRIPTION
IN E'IGURE3
IxTsNszox
A6 - 1
569 LF
6" p PVC Waterline (0900 DR 18), comp late
r0�
$
in place per linear foot
A6 -2 2
2,923 LF
8" PVC Waterline (0900 DR 18), complete
$ —
S G� ✓�
in place per linear foot
A6 -3
7 EA
6" Gate Valve, complete in place per
each
19 EA
8" Gate Valve, complete in place per
$� 070W
$
A6 -9
each
�J 4aD
C7Z `"
$ � 000
A6 - 5
40 EA
6 45 Bend, complete in place per each
$
A6_6
19 EA
8" 45 Bend, complete in place per each
$
�6 -7
4 EA
8" X 6" Cross, complete in place per
$
each
A6--8
I EA
12" X 8" Cross, complete in place per
$ 4 r 0 '—L?
S
each
76-19
r-A 6 -9
1 E74
8" X fi" Tapping Sleeve, complete in place
$ L
$
per each
PIMM U--PROP08AL POEM
PAGE 19 OF 24
Addaadum No_ 2
AttaCbftnt No. 4
P494 19 of 24
Y LI IST BY V
pin QTY & DESCRIPTION UNIT PRICE 13ID I1'Eb�
STEM UNIT IN FIGURES EXTENSTON
ALTE MMM No. 6 - SM -ToIAL WATER IWROVEMNTS (ITEMS A6 -1 THRU A -23) :
Addendua He. 2
Rsv=SeKD R popoSAL rOM Attaebiftt No. 4
pAm 20 OF 24 Paga 20 of 24
20" X. 6" Tapping Sleeve, complete in
1A
$
$ k '
p,fi -10
place per each
A6 -17
44 X 8" Tapping Sleeve, complete in
( - 3) EA
$
$ ���
place per each
{ - 1) EA 12" X 8" Tee, complete in place per each
$ Cr
$ �?
6 - 13
4 EA 8" X 8" Tee, complete in place per each
$
$
3 EA 8" X 6 Tee, complete in place per each
$
$
6" X 4" Reducer, complete in place per
$ �rf�
$ �i
A6 -15
1 EA
each
--�"`'
8" X 4" Reducer, complete in place per
$
$
A6 -1f
( -1) EA
each
A5 -17
1 EA 6 " - 12" Plug, complete in place per each
$
Remove 9" -12" Waterline, complete in
$�
A6 -18
Sl LF
place per linear foot
Eire Hydrant Assembly with 8" X 6" xee
t
A6 -19
10 EA and 6" gate valve, complete in place per
$�
$ �
each
Eire Hydrant Assembly with 6" gate valve,
3 EA
$
e r
$_
A6 -20
complete in place per each.
Utility Pavement Repair, complete in
$
$
A6 -21
6,808 SE place per square foot
Trench Safety (Waterlines), complete in
$
$
116 22
3,492 LF
place per linear foot
Waterline Connection (6 ", 6 ", 12" & 16 "),
$ jqO0
$ �r
A6 -23
3 EA complete in place per each
ALTE MMM No. 6 - SM -ToIAL WATER IWROVEMNTS (ITEMS A6 -1 THRU A -23) :
Addendua He. 2
Rsv=SeKD R popoSAL rOM Attaebiftt No. 4
pAm 20 OF 24 Paga 20 of 24
STAPLES STREET PHASE 2 BARRACUDA PLACE TO GOLLIHAR ROAD (BONA 2 0 08)
PROJECT NO. 5469
10- Va .
TOTAL BASE HID
(PART A + DART S + PART C + PART D +
PART E + PART F + PART G + PART H + PART I)
ALTERNATE NO. I
(I'T'EM A1-1)
ALTERNATE N0. 2
(ITEM A2 -1 THRU ITEM A2 - 8):
ALTERNATE N0. 3
(ITEM A3 -1 THRU A3 -8):
. ALTERNATE NO. 4
(ITEM A4 -1):
ALTERNATE NO. 5
(ITEM A5 -1):
ALTERNATE N0. 6
(ITEM A6 -1 THRU A6-23):
$ 20
66
$ � cuc --
The undersigned hereby declares that he has visited the site and has
carefully examined the plans, specifications and contract documents relating to
the work covered by his bid or bids, that he agrees to do the work, and that no
representations made by the City are in any sense a warranty but are mere
estimates for the guidance of the Contractor.
Upon notification of award of contract, we will within ten (10) calendar
days execute the formal contract and will deliver a Performance Bond (as required)
for the faithful performance of this contract and a Payment Bond (as required) to
insure payment for all labor and materials. The bid bond attached to this
proposal, in the amount of 5% of the highest amount bid, is to become the property
of the City of Corpus Christi in the event the contract and bonds are not executed
within the time above set forth as liquidated damages for the delay and additional
work caused thereby.
Minority/Minority Business Entexprise Participation: The apparent low
bidder shall, within five days of receipt of bids, submit to the City Engineer, in
writing, the names and addresses of MBE firms participating in the contract and a
description of the work to be performed and its dollar value for bid evaluation
purpose_
Number of Signed seta of boo ments: The contract and all bonds will be
prepared in not less than four counterpart (original signed) sets.
xavxs=- PROaasnz. VM
Addendum No. 2
PALE 21 OF 74 .Att achmgat No- 4
Rage 21 of 24
Time of Completion. The undersigned agrees to complete the work withirk-
The working t3z% for completion of the Project will be broken down as follows:
Doaariptlan
projeot Limits
Csleudas
IIV3 -dated
Day■ !
Damage$ /nay
Allota4
Base Sid
Barracuda to Gollihax /Autotown
43$
51,100
Altornate No. S
Part 1
Carmel Parkway to Everhart (in03.udQu
240
$1,loo
the Everhart i.nt:er9slotion up to
Ste. 78 +00)
Part 2
Barracuda to Carmel Parkway
1.05
51.100
Part 3
Evibrhart to Gollihar / Autotown
90
$1,100
Alternate No. 2
Barracuda to Gollihar /Autotown
Same as Base Hid shown
(Concrete Pavement)- Sequoncing /TCP as
above.
shown in Bane Did
Altarnate NO. 3
})utr9GUda to G.o].lihar /Alutotom
Same as Alternate No, 1
{Concrete Osvement)-- 9egnenczng /TCP as
shown above.
Shown in Alternate V, 1
A1tpcnate NO- 4
Carmel Parkway to Everhart. (iVICIUd"
160 $2,000
the Everhart intereaction up to
Sta. 78400) - Expedited Schedule
tMC ( t'iON
Alternate llo. 5
Carmel Parkway to Everhart (inaXud8b
180
the Everhart i.nte =section up to
Sta. 70 +00) - Fxpadtted Schedule
Car�creto Pavement 0 " nn:�
lllternate No. 6
Barracuda to G0111har /Autotown - Water
Included in na.ae Bid
Idne Imp rovements
1.
from the date designated by a Work Order.
The undersigned further declares that he will provide all necessary tools
and apparatus, do all the work and furnish all materials and do everything
required to carry out the above mentioned work covered by this proposal., in strict
accordance with the contract documents and the requirements pertaining thereto,
for the sum or suM above set forth.
Receipt of the following addenda is acknowledged (addenda rnumber):
Addendum # 1 - 02/03/11 Addendum #2 - 02/10/11
Respectfully submitted:
N Terry Willi
Lai " 1 1111�J , ,ry
(SEAL - IF BIDDER T5
a Corporation) Address 2081 F rnbush Lane
U . Box) (street)
ston, Texas 77073
(City) ' (State)
Telephone-. 281 - 821 - 9091
l3 TE: Do not detach bid from other papers.
Fill in with ink and submit complete
with attached papers.
xsvls$n- YmoEOSAI.
FOWW
Wevieed August 2000
Adt1GXdU% No. 2
Attachment No. 4
gage xa of 24
Contractor shall indemnify, sage harmless and defend
the City of Corpus Christi in accordance vi th General
Provision P -6 -11 and Special Provision A -26 of the General
and Special Provisions and Requirements for Municipal
Construction Contracts of the City of Corpus Christi,
Texas.
The Contractor will commence work within ten (10) calendar days
from date they receive written work order and will complete same
within 435 CALENDAR DAYS after construction is begun. Should
-- Contractor default, Contractor may be liable for liquidated damages
as set forth in the Contract Documents.
City will pay Contractor in current funds for performance of the
contract in accordance with the Contract Documents as the work
progresses.
Signed in 4 parts at Corpus Christi, Texas on the date shown
above.
Page 2 of 3
Rev. Jun -2010
AT
City Secretary
APPROVED AS TO LEGAL, RM:
By: c.
Asst. City Attorney
; (If orporation)
(Seal Below)
(Note- If Person signing for
corporation is not President,
attach copy of authorization
to sign)
L.
5 .
CITY OF ORPUS C I&SI
By:
Juan Peral.es, Ar.,P.E.
Assistant City Manager
Engineering /Development Services
By:
Pete Anaya, P. E. r m—
Director of Engineering Services
CONTRACTOR
Texas Ste lin onstruct,ion Co.
By.
Tit 1 e : Williamson, President
20810 FERNBUSH LANE
(Address)
HOUSTON, TX 77073
(City) (State)(ZIP)
281/821 -9091 * 281/821 -2995
(Phone) (Fax)
( -n�v AUTHORIZED
ly COUNCIL—OaLaf/
4
SECR A
Page 3 of 3
Rev. Jun -2010
P E R F O R M A N C E B O N D
Bond No. 105534476
STATE OF TEXAS §
COUNTY OF NUECES §
KNOW ALL BY THESE PRESENTS:
8
THAT Texas Sterling Construction Co. of HARRIS County, Texas,
hereinafter called "Principal ", and Travelers Casualty and ly a
corporation organized under the laws of the State of CT ,
-- and duly authorized to do business in the State of Texas,
hereinafter called "Surety ", are held and firmly bound unto the
City of Corpus Christi, a municipal corporation of Nueces County,
Texas, hereinafter called "City ", in the penal sum of SIX MILLION,
THREE HUNDRED THIRTEEN THOUSAND, TWO HUNDRED FIFTY —THREE AND 50/100
($ 6,313,253.50 ) DOLLARS, lawful money of the United States, to be
paid in Nueces County, Texas, for the payment of which sum well and
truly to be made we bind ourselves, our heirs, executors,
administrators and successors, jointly and severally, firmly by
these presents:
THE CONDITION OF THIS OBLIGATION IS SUCH THAT: Whereas, the
principal entered into a certain contract with the City of Corpus
Christi, dated the 8TH of MARCH , 20 11 , a copy of which is
hereto attached and made a part hereof, for the construction of:
STAPLES STREET, PHASE 2 BARRACUDA PLACE
TO GOLLIHAR ROAD(BOND 2008)
PROJECT NO. 6469
(TOTAL BASE BID: $6,313,253.50)
NOW, THEREFORE, if the principal shall faithfully perform said
work in accordance with the plans, specifications and contract
documents, including any changes, extensions, or guaranties, and if
the principal shall repair and /or replace all defects due to faulty
materials and /or workmanship that appear within a period of one (1)
year from the date of completion and acceptance of improvements by
the City, then this obligation shall be void; otherwise to remain
in full force and effect.
PROVIDED FURTHER, that if any legal action be filed on this
bond, venue shall lie in Nueces County, Texas.
And that said surety for value received hereby stipulates that
no change, extension of time, alteration or addition to the terms
of the contract, or to the work performed thereunder, or the plans,
specifications, drawings, etc., accompanying the same shall in
anywise affect its obligation on this bond, and it does hereby
waive notice of any such change, extension, of time, alteration or
addition to the terms of the contract, or to the work to be
performed thereunder.
Performance Bond
Page 1 of 2
This bond is given to meet the requirements of Article 5160,
Vernon's Civil Statutes of Texas, and other applicable statutes of
the State of Texas.
The undersigned agent is hereby designated by the Surety
herein as the Agent Resident in Nueces County to whom any requisite
notices may be delivered and on whom service of process may be had
in matters arising out of such suretyship, as provided by Art.
7.19 -1, Vernon's Texas Insurance Code.
IN WITNESS WHEREOF, this instrument is executed in 9 copies,
each one of which shall be deemed an original, this the 16th
day of March 20 11
PRINCIPAL
By:
Terry
(Print Name
ATTEST
tle)
President
(Print Name & Title
SURETY
Travelers Casualty and Surety Compan
By: Kathleen M. Irelan, Attorney -in -Fact
Attorney -in -fact
Kathle M. Irelan
(Print Name)
The Resident Agent: of the Surety in Nueces County, Texas for
delivery of notice and. service of process is:
Agency:
Cop-tact Person:
Address:
Phone
Keetch & Associates
Mr. Kev Keetch
e.0 B
�8�0
Carpus Christi TX 78463 -3280
361 -883 -3803
(NOTE: Date of P 4zfi - ,. Ante L=- must not uc pzlor tc, lot's of C. ,ntiuct) "Re , Ji�e2�
Performance Ponce
Page 2 o_
J
P A Y M E N T B O N D
Bond No. 105534476
STATE OF TEXAS §
COUNTY OF NUECES §
KNOW ALL BY THESE PRESENTS:
THAT Texas Sterling___ Construction Co. of HARRIS County, Texas,
hereinafter called "Principal ", and Trav Casualty and Surety Company
a corporation organized under the laws of the State of CT
and duly authorized to do business in the State of Texas,
hereinafter called "Surety ", are held and firmly bound unto the
City of Corpus Christi, a municipal corporation of Nueces County,
Texas, hereinafter called "City ", and unto all persons, firms and
corporations supplying labor and materials in prosecution of the
work referred to in the attached contract, in the penal sum of SIX
MILLION, THREE HUNDRED THIRTEEN THOUSAND, TWO HUNDRED FIFTY - -THREE
AND 50/100 ($ 6,313,253.50 ) DOLLARS, lawful money of the United
States, to be paid in Nueces County, Texas, for the payment of
which sum well and truly to be made we bind ourselves, our heirs,
executors, administrators and successors, jointly and severally,
firmly by these presents:
THE CONDITION OF THIS OBLIGATION IS SUCH THAT: Whereas, the
principal entered into a certain contract with the City of Corpus
Christi, dated the 8TH day MARCH , 20 11 , a copy of which is
-- hereto attached and made a part hereof, for the construction of:
STAPLES STREET, PHASE 2 BARRACUDA PLACE
TO GOLLIHAR ROAD (BOND 2008)
PROJECT NO. 6469
(TOTAL BASE BID: $6,313,253.50)
NOW, THEREFORE, if the principal shall faithfully perform its
duties and make prompt payment to all persons, • firms,
subcontractors, corporations and claimants supplying labor and
material in the prosecution of- the work provided for in said
contract and any and all duly authorized modification of said
contract that may hereinafter be made, notice of which modification
to the surety is hereby expressly waived, then this obligation
shall be void; otherwise to remain in full force and effect.
PROVIDED FURTHER, that if any legal action be filed upon this
bond, venue shall lie in Nueces County, Texas.
And that said surety for value received hereby stipulates that
no change, extension of time, alteration or addition to the terms
of the contract, or to the work performed thereunder, or the plans,
specifications, drawings, etc., accompanying the same shall in
anywise affect its obligation on this bond, and it does hereby
waive notice of any such change, extension of time, alteration or
addition to the terms of the contract, or to the work to be
performed thereunder.
Payment Bond
Page 1 of 2
This bond is given
Vernon's Civil Statutes
the State of Texas. Th
as used herein are in
Article.
to meet the requirements of Article 5160,
of Texas, and other applicable statutes of
e terms "Claimant ", "Labor" and "Material ",
accordance with and as defined in said
The undersigned agent is hereby designated by the Surety
herein as the Agent Resident in Nueces County to whom any requisite
notices may be delivered and on whom service of process may be had
in matters arising out of such suretyship, as provided by Art.
7.19 -1, Vernon's Texas Insurance Code.
IN WITNESS WHEREOF, this instrument is executed in 4 copies,
each one of which shall be deemed an original, this the 16th
day of Ma rch 20 11
PRINCIPAL
Texas Sterlinq C
G�
ATTEST
inn r n
(Print Name & Title)
SURETY
Travelers Casualty and Sure! Compan
By: Kathleen M. Irelan. Attorney -in -Fact
Attorney -in -fact
Kathleen M. Irelan
(Print Dame)
The Resident Agent of the Surety in Nueces County, Texas for
delivery of notice and service of process is:
Agency: Keetch & Associates
Contact Person: Mr. Kevin Keetch
Address
t Corpus Christi TX 78463 -3280
Phone Number: 361 -883 -3803
(NOTE: Date of Payment Bond must not be prior to date of contract)
Payment Bond
Page 2 of 2
(Revised 3/08)
(Print Name & Title)
x
IMPORTANT NOTICE
To obtain information or make a complaint
You may call Travelers Casualty and Surety Company of America and its affiliates' toll-
free telephone number for information or to make a complaint at:
1- 800 -328 -2189
You may contact the Texas Department of Insurance to obtain information on
companies, coverages, rights or complaints at
1- 800 -252 -3439
You may write the Texas Department of Insurance:
P. O. Box 149
Austin, TX 78714 -9'1 04
Fax: (512) 475 -1771
Web: httg:llwwwr.tdi,state.ix.us
E-mail. ConsurnerProtection (cDtdi.state.tx.es
PREMIUM OR CLAIM DISPUTES:
Should you have a dispute concerning your premium or about a claim you should
contact your Agent or Travelers first If the dispute is not resolved, you may contact the
Texas DepailmentofInsurance-
ATTACH THIS NOTICE TO YOUR BOND:
This notice is for information only and does not be come a part or conditi on of the
attached document and is given to comply with Texas legal and regulatory requirements.
(pN -042-8) Ed. 7 CA 8.07
TRAVELER
POWER OF ATTORNEY
Farmington Casualty Company
Fidelity and Guaranty Insurance Company
Fidelity and Guaranty Insurance Underwriters, Inc.
Seaboard Surety Company
St. Paul Fire and Marine Insurance Company
Attorney - In - Fact No. 221694
St. Paul Guardian Insurance Company
St. Paul Mercury Insurance Company
Travelers Casualty and Surety Company
Travelers Casualty and Surety Company of America
United States Fidelity and Guaranty Company
KNOW ALL MEN BY THESE PRESENTS: That Seaboard Surety Company is a corporation duly organized under the laws of
the State of New York, that St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company and St. Paul
Mercury Insurance Company are corporations duly organized under the laws of the State of Minnesota, that Farmington Casualty
Company, Travelers Casualty and Surety Company, and Travelers Casualty and Surety Company of America are corporations
duly organized under the laws of the State of Connecticut, that United States Fidelity and Guaranty Company is a corporation
duly organized under the laws of the State of Maryland, that Fidelity and Guaranty Insurance Company is a corporation duly
organized under the laws of the State of Iowa, and that Fidelity and Guaranty Insurance Underwriters, Inc. is a corporation duly
organized under the laws of the State of Wisconsin (herein collectively called the "Companies ") and that the Companies do
hereby make, constitute and appoint Alan P Chandler, Chad Teague, Ian J Donald, Jeffrey A Chandler, Kathleen M.Irelan,
Robert Trobec of the City of Troy, State of MI, their true and lawful Attorneys) -in -Fact, each in their separate capacity if more
than one is named above, to sign, execute, seal and acknowledge any and all bonds, recognizances, conditional undertakings, and
other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of
persons, guaranteeing the performance of contracts and executing or guaranteeing bonds and undertakings required or permitted
in any actions or proceedings allowed by law.
IN WITNESS WHEREOF, the Companies have caused this instrument to be signed and their corporate seals to be hereto
affixed, this 16th day of March, 2011.
Farmington Casualty Company
Fidelity and Guaranty Insurance Company
Fidelity and Guaranty Insurance Underwriters, Inc.
Seaboard Surety Compan y
St. Paul Fire and Marine Insurance Company
State of Ohio
City of Independence ss.
St. Paul Guardian Insurance Company
St. rcury Insurance Company
a elers asualty and Surety Company
4�� rd s Casualty and Surety Company of America
- ta de Guar Company
Pau aska, 'dent
On this the 16th day of March, 2011 before me personally appeared Paul W. Nebraska, who acknowledged himself to be the
Assistant Secretary of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty
Insurance Underwriters, Inc., Seaboard Surety Company, St. Paul Fire and Marine Insurance Company, St. Paul Guardian
Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety Company, Travelers Casualty and
Surety Company of America, and United States Fidelity and Guaranty Company, and that himself, as such, being authorized so to
do, executed the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a
duly authorized officer.
In Witness Whereof, I hereunto set my hand and official seal.
My Commission expires the 22nd day of June, 2012.
Rae Soucek, Notary Public
SUPPLIER NUMBER
_ PURC1iASNGD1 —
` CITY OF CORPUS CHRISTI
el" ° � DISCLOSURE OF INTEREST
corpus
Christi
Clky of Corpus Christi Ordinance 171 12, as amended, requires all perSone or firms seeking to d
bus #tress with the City to provide the fallowing. Information. i=ve ' question must bo answered. If
the question Is not appplicebfo, answer with "l4A". See reverse 400 for Piling Requirements,
Certifications and definitions.
COMPANY NAME: Texas Sterling Construction Co.
P. . 0. BOX:
STREET ADDRESS: 20810 Fernbush Lane
FIRM IS: 1. Corporation
4. Association Li
CITY: Houston
2. Partnership q
5. Other U
ZIP: 77073..
3. Sole Owner 0
pISCLOSURIr QUESTIONS
If additional space Is necessary, please use tits reverse side of this page or attach separate sheet.
1. State the names of each "employee" of the City of Corppos Christi harrino. ark
Interest" constituting 3% or more of the own4ibip In the above named ` " firth"
Name Job Title and City Department (if known)
N/A
2. State the names of each "official" of the City of Corpus Christi having an "ownership interest"
constituting 3% or more of the ownership in the above named "firm."
Name Title
N/A
3. State the names of each "board member" of the City of Corpus Christi having an "ownership
Interest" constituting 3% or more of the ownership In the above named "firm."
Name Board, Commission or Committee
4. State the names of each employee or officer of a "con sultant" for the Clt� of Corpus Christi who
worked on any matter related to the subject of this contract and has an `ownership Interest"
constituting 3 or more of the ownership In the above named "firm."
Name Consultant
N/A
Addendum No. 2
Attachmont Ko. 4
page 23 at 24
REVISED- PROPOSAL rORM
PAGE 23 Or 24
FILING REQUIREMENTS
If a person who requests official aotlon on a matter lthows that the. re. jested action will confer air
economic benefit oh any City official or eniplpy�ee that is dietingulsha a frarn the effect that the,
aeti+an will have an merrnbers of the ,public in eheral or a substariftl sea th�ereaf, you sholi
disclose that #actin.a signed wilting to th+� C O"Idal ennployee or 160 y that has been requested
T act in the matter, unfe�s tfZe interestof lire ity pfficlal or employee In the matter la apparent.
The disclosure shall also be rruade In a signet writing flied with the City Secretary 1�thits
Ordinance Section 2-349 (d)]
CERTIFiCATI
I certlfy that all information provided is true and corredt as Of the date of thls statement, t1hat i
statements will�bep ompt y subml� d to the Clty of Co p s Ch requested; sti s as changes vccur�
Certifying Person: Terry Williamson Title: President
_ (type or Pint) •.
Signature of Certifying ate: 02/16/11
Person:
DEFINITIONS
a. `Board member." A member of any board, commission, or committee appointed by the
City Council of the City of Corpus Christi, Texas.
b. , Economic benefit % An action that Is likely to affect an economic interest if it Is likely to have
an effect on that Interest that Is distinguishable from its effect on members of the public in
general or a suibstantial segment thereof.
c.
"Employee.' Any person employed by the City of Corpus Christi, Texas either on a full or part.
time basis, but not as an Independent contractor.
d. "Firm." Any entity rporated for economic gain, whether professional, industrial or
came nerclal, and whether established to pfoduce or deal with a product or service, Including
but not limited to, entities operated. In tiro form of solo proprieto.rshlo,, as self employed
person, .partrterahlpr corporation, jolr►t stook comp;arkY, 16 ver+ture, rece or trust, and
entities which for porpoises of taxation lire treated as no pr*fl -organizations.
e. , offlcial." The Mayor, members of the City Council, City Manager, Deputy City Manager,
Assistant City Managers, Department and Division Heads, and Municipal Court Judges of the
City of Corpus Christi, Texas.
f, "OwnershipIntorest." Legal or equitable interest, whether actually or canstructiv,eiy
held, in a firm, InoWding when such interest is held through an argent, trust, estate, or holding
entity. 'Constructively held" refers to holdings or control established through voting trusts,
proxies, or special terms of venture or partnership agreerrierits."
g. "Consultant." Any person or firm, such as engineers and architects, hired by the City of
Corpus Christi for the purpose of professional consultation and recommendation.
L um No. 2
7 ND 24 of F4
Revis8D FORM
PA(m 24 or 24
ACORD CERTIFICATE OF LIABILITY INSURANCE
03/22/zo
3/22/20D
ll
PRODUCER 1- 248 -828 -3377
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
Valenti Trobec Chandler Inc.
1175 West Long Lake Road
Suite 200
ON N TH
THIS CERTIFICATE DOES NOT p CERTIFICATE
EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
INSURERS AFFORDING COVERAGE
Tray, MX 48098
jackie Wilson 225
INSURED
Texas Sterling Construction Co
{NSURERA:Twin City Fire Insurance Cc
INSVRERB:Twin City Fire Insurance Co
$ 1,000,000
20810 Fernbush
INSURER C: COMMERCE & INDUSTRY INS CO
INSURER D: Hartford Ins Cc of the Midwest
Houston, TX 77073
INSURER E: TRAVELERS COMMERCIAL CAS CO
$2,000,000
C'nVF=RO[ytS
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR I TYPE OF INSUR CE POLICY NUMBER POLICY EFFECTIVE POLICY EXPIRATION
DATE IMMMDNY)
LIMITS
A GENERALUABILITY 350QUO580 03/01111 03/01/12
EACH OCCURRENCE
$ 1,000,000
X COMMERCIAL GENERAL LIABILITY
CLAIMS MADE Fil OCCUR
FIRE DAMAGE (Anyone fire)
MED EXP {Any one person}
$300,000
$ 10,000
X X CU & Waiver of Sub.
PERSONAL & ADV INJURY
$ 1,000,000
X Blanket Add'1 Insured
GENERAL AGGREGATE
$2,000,000
GEN'LAGGREGA TELIMITAPPLIESPER:
PRODUCTS- COMPIOPAGG
$2,000,000
OLICY X
P PRO- ! LOC
H
AUTOMOBILELIABILRY
X
:,` /
Yl
ANY AUTO
3SUENQUO581
03/01/11 03/01/12
COMBINED SINGLE LIMIT
(Ea accident)
$ 1,000,000
BODILY INJURY
(Per person)
$
ALL OWNED AUTOS
SCHEDULED AUTOS
X
BODILY INJURY
(Per accident)
$
HIREDAUTOS
NON- OWNEDAUTOS
X
PROPERTY DAMAGE
(Per accident)
$
GARAGE L"ILITY
AUTO ONLY - EA ACCIDENT
$
OTHER THAN EA ACC
$
ANY AUTO
$
AUTO ONLY: AGG
C
EXCESS LIABILITY
9781111
03/01/11 03/01/12
EACH OCCURRENCE
$25,000,00 0
X OCCUR 171 CLAIMS MADE
AGGREGATE
$25,000,000
$
DEDUCTIBLE
$
RETENTION $
D
WORKERS COMPENSATION D
35WNQU0582
03/01/11 03/01/12
X WCSTATU- OTH- ER
EMPLOYERS' LIABILITY
E.L. EACH ACCIDENT
$1,000,000
E.L. DISEASE - EA EMPLOYEE
$1,000,000
E.L. DISEASE - POLICY LIMIT
$ 1,000,000
OTHER
E
Contractors Equipment
QT6302810n798
03/01/11 03/01/12
Leased and Rented
s2,000,000
s
s
DESCRIPTION OF OPERATIONSILOCATIONSNEHICLESIEXCLUSIONS ADDED BY ENDORSEMENTISPECIAL PROVISIONS
Project: Staples Street Phase 2, Barracuda Place to Gollihar Road (Bond 2008 ), Project No. 6469
/
City of Corpus Christi is named as additiional insured on the liability policies above. The cancellation 4f
clause below is amended to include 30 day notice of any material change to these policies. These provisions
are pursuant to a written contract between the insured and the City of Carpus Christi.
r - , r - m I Ir n A I C rnuL i r-m I ADDITIONAL INSURED: INSURER LETTER:. GANGtLLA I IL7N
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
Corpus Christi, City of DATE THEREOF, THE ISSUING INSURER WILL BAW0 MAIL 30 DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, t
Dept of Engineering Services
P 0 Box 9277 x] OMXtXl�CId6Kx161mr ]CdR�D><8R7�I4RX
X $ K41&= XXXXXXXXXXXXXXXXXXXXXXX XXXXXXXXXS XXXXxxxx
Corpus Christi, TX 78469 -9277 AU7HORCL£DREPRESEN7A71VE
USA 1�cw�_/ �■
ACORD 25 - (7197) knanning ACORD CORPORATION IRRR
LUL1.3 a03
J
POLICY NUMBER: 35 C QUO580
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
ADDITIONAL INSURED BY CONTRACT OR AGREEMENT
OPTION II
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
SCHEDULE
Name Of Additional Insured Person(s)
Or Organization(s):
Designated Project(s) or Locations)
Of Covered Operations
ALL
ALL
Information required to complete this Schedule, if not shown above, will be shown in the Declarations_
A. Section 11 - Who Is An Insured is amended to
include as an additional insured the person(s) or
organization(s) shown in the Schedule above with
whom you agreed in a written contract or written
agreement to provide insurance such as is
afforded under this policy, but only to the extent
that such person or organization is liable for
"bodily injury", "property damage" or "personal
and advertising injury" caused by:
1. Your acts or omissions or the acts or
omissions of those acting on your behalf:
a. In the performance of your ongoing
operations for such additional insured at
the project(s) or location(s) designated in
the Schedule;
b. In connection with your premises owned
by or rented to you and shown in the
Schedule; or
c, In connection with "your work" for the
additional insured at the project(s) or
location(s) designated in the Schedule
Form HS 24 81 06 05
and included within the "products - completed
operations hazard:, but only if:
(1) The written contract or agreement
requires you to provide such coverage
to such additional insured at the
project(s) or location(s) designated in
the Schedule; and
(2) This Coverage Part provides
coverage for "bodily injury' or
"property damage" included within the
"products- completed operations
hazard ".
2. The acts or omissions of the additional
insured in connection with their general
supervision of your operations at the projects
or locations designated in the Schedule.
B. The insurance afforded to these additional
insureds applies only:
1. If the 'occurrence" or offense takes place
subsequent to the execution of such written
contract or written agreement; and
Page 1 of 3
(c) 2005, The Hartford
(includes copyrighted material of Insurance Services Office, Inc. with its permission.)
2 While such written contract or written
b. Notify us as soon as practicable,
agreement is in force, or until the end of the
policy period," whichever is earlier,
The additional insured must see to it that we
receive written notice of the claim or "suit" as
C. With respect to the insurance afforded to these
soon as practicable.
additional insureds under this endorsement, the
following additional exclusion applies:
3. Assistance And Cooperation Of The
This insurance does not apply to "bodily injury",
Insured
"property damage" or "personal and advertising
The additional insured must:
injury" arising out of the rendering of or the failure
a. Immediately send us copies of any
to render any professional architectural,
demands, notices, summonses or legal
engineering or surveying services by or for you,
papers received in connection with the
including;
claim or "suit ";
1. The preparing, approving, or failing to
b. Authorize us to obtain records and other
prepare or approve maps, shop drawings,
information;
opinions, reports, surveys, field orders,
c. Cooperate with us in the investigation or
change orders, designs or specifications; and
settlement of the claim or defense against
2. Supervisory, inspection, architectural or
the "suit "; and
engineering activities.
d. Assist us, upon our request, in the
D. How Limits Apply To Additional Insureds
enforcement of any right against any person
The most we will pay on behalf of the additional
or organization which may be liable to the
insured shown in the Schedule is the lesser of;
insured because of injury or damage to
which this insurance may also apply.
1. The limits of insurance specified in the written
contract or written agreement; or
4. Obligations At The Additional Insureds
Own Gast
2. The Limits of Insurance shown in the
Declarations.
No additional insured will, except at that
Such amount shall be a part of and not in addition
insured's own cost, voluntarily make a
payment, assume any obligation, or incur any
to Limits of Insurance shown in the Declarations
expense, other than for first aid, without our
and described in this Section.
consent.
E. Duties Of Additional Insureds In The Event Of
5. Additional Insureds Other Insurance
Occurrence, Offense, Claim Or Suit
if we cover a claim or "suit" under this
The Duties Condition in Section IV - Conditions
Coverage part that may also be covered by
is replaced by the following and applies to the
other insurance available to the additional
additional insured shown in the Schedule:
insured, such additional insured must submit
1. Notice Of Occurrence Or Offense
such claim or "suit" to the other insurer for
The additional insured must see to it that we
defense and indemnity.
are notified as soon as practicable of an
However, this provision does not apply to the
"occurrence" or an offense which may result in
extent that you have agreed in a written
a claim. To the extent possible, notice should
contract or written agreement that this
include:
insurance is primary and non - contributory
a. How, when and where the "occurrence" or
with the additional insured's own insurance.
offense took place;
6. Knowledge Of An Occurrence, Offense,
b. The names and addresses of any injured
Claim Or Suit
persons and witnesses; and
Paragraphs 1. and 2. applies to the additional
c. The nature and location of any injury or
insured only when such "occurrence",
"suit"
damage arising out of the "occurrence or
offense, claim or is known to;
offense.
a. The additional insured that is an
2. Notice Of Claim
individual;
If a claim is made or "suit" is brought against
b. Any partner, if the additional insured is a
the additional insured, the additional insured
partnership;
must:
c. Any manager, if the additional insured is a
a. Immediately record the specifics of the
limited liability company;
claim or "suit" and the date received; and
d. Any "executive officer" or insurance
manager, if the additional insured is a
corporation;
Page 2 of 3
Form HS 24 8106 65
e. Any trustee, if the additional insured is a
the extent not subject to Exclusion g, of
trust; or
Section I -- Coverage A -- Bodily injury
f. Any elected or appointed official, if the
And Property Damage Liability;
additional insured is a political subdivision
e. Property Damage to Borrowed
or public entity.
Equipment Or Use Of Elevators
F. Other insurance
If the loss arises out of "property damage"
With respect to insurance provided to the
to borrowed equipment or the use of
additional insured shown in the Schedule, the
elevators to the extent not subject to
Other Insurance Condition Section IV -
Exclusion j. of Section I - Coverage A -
Conditions is replaced by the following:
Bodily Injury And Property Damage
1, Primary Insurance
Liability; or
a. Primary Insurance When Required By
f. When You Are Added As An Additional
Contract
Insured To Other Insurance
This insurance is primary if you have
That is any other insurance available to
agreed in a written contract or written
you covering liability for damages arising
agreement that this insurance be primary,
out of the premises or operations, or
If other insurance is also primary, we will
products and completed operations, for
share with all that other insurance by the
which you have been added as an
method described in 3. below,
additional insured by that insurance.
b. Primary And Non - Contributory To
When this insurance is excess, we will have
Other Insurance When Required By
no duly under Coverages A or B to defend
Contract
the insured against any "suit" if any other
If you have agreed in a written contract or
insurer has a duty to defend the insured
against that "suit". If no other insurer defends,
written agreement that this insurance is
we will undertake to do so, but we will be
primary and non - contributory with the
entitled to the insured's rights against all
additional insured's own insurance, this
those other insurers.
insurance is primary and we will not seek
contribution from that other Insurance.
When this insurance is excess over other
Paragraphs a. and b. do not apply to other
insurance, we will pay only our share of the
amount of the loss, if any, that exceeds the
insurance to which the additional insured has
sum of:
been added as an additional insured or to
other insurance described in paragraph 2.
a. The total amount that all such other
below,
insurance would pay for the loss in the
2. Excess Insurance
absence of this insurance; and
b. The total of all deductible and self - insured
This insurance is excess over any of the other
amounts under all that other insurance.
insurance, whether primary, excess,
contingent or on any other basis:
We will share the remaining loss, if any, with
a. Your Work
any other insurance that is not described in
this Excess insurance provision and was not
That is Fire, Extended Coverage,
bought specifically to apply in excess of the
Builder's Risk, Installation Risk or similar
Limits of insurance shown in the Declarations
coverage for "your work';
of this Coverage Part.
b. Premises Rented To You
3. Method Of Sharing
That is fire. lightning or explosion
If all of the other insurance permits
insurance for premises rented to you or
contribution by equal shares, we will follow
temporarily occupied by you with
this method also. Under this approach each
permission of the owner;
insurer contributes equal amounts until it has
c. Tenant Liability
paid its applicable limit of insurance or none of
That is insurance purchased you to
the loss remains, whichever comes first.
cover your liability as a tenant ant for
If any of the other insurance does riot permit
"property damage" to premises rented to
contribution by equal shares, we will
you or temporarily occupied by you with
contribute by limits. Under this method, each
permission of the owner;
insurer's share is based on the ratio of its
d. Aircraft, Auto Or Watercraft
applicable limit of insurance to the total
applicable limits of insurance of all insurers.
If the loss arises out of the maintenance
or use of aircraft, "autos" or watercraft to
Form HS 24 81 06 05
Page 3 of 3
POLICY NUMBER: 35UENQUO581
COMMERCIAL AUTO
CA 20 48 02 99
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
/DESIGNATED INSURED
This endorsement modifies insurance provided under the following:
BUSINESS AUTO COVERAGE FORM
GARAGE COVERAGE FORM
MOTOR CARRIER COVERAGE FORM
TRUCKERS COVERAGE FORM
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified
by this endorsement.
This endorsement identifies person(s) or organization(s) who are "Insureds' under the Who Is An Insured Provision of
the Coverage Form. This endorsement does not alter coverage provided in the Coverage Form.
This endorsement changes the policy effective on the inception date of the policy unless another date is indicated
below.
Endorsement effective
Named Insured
Texas Sterling Construction Co. V
Ccun1!Z : y .
�E,
Irtumurizeta rceprasenearrve)
SCHEDULE
Name of Person(s) or Organization(s):
City of Corpus Christi, Texas
(if no entry appears above, Information required to complete this endorsement will be shown in the Declarations as
applicable to the endorsement.)
Each person or organization shown in the Schedule is an "insured' for Liability Coverage, but only to the extent that
person or organization qualifies as an "insured" under the Who Is An Insured Provision contained in Section Ii orthe
Coverage Form.
CA 20 48 02 99 Copyright, Insurance Services Office, Inc., 1990 Page 1 of 1
POLICYNUMBER: 35CQU058A V
Ftll
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
V / NOTICE OF CANCELLATION
TO DESIGNATED PERSON(S) OR ORGANIZATION(S)
OTHER THAN THE NAMED INSURED
This policy is subject to the following condiWm
Number of Days Notice 3 0 V/
I Name of Person(s) or Organization(s)
SCHEDULE
r. i
Carpus Christi, City of
Mailing Address
1201 Leopard St.
Corpus Christi TX. 78.401
If this policy is cancelled, we agree that the person(s) or organization(s) listed in the Schedule above will be
notified at least:
a. 15 days before the effective date of canceliation if we cancel for non - payment of premium; or
b. The number of days shown in the Schedule above before the effective date of cancellation if we cancel for
any other reason.
In no event, however, will notice of cancellation be less than the minimum number of days required by the
jurisdiction to which this endorsement applies.
If notice is mailed, proof of mailing to the address shown in the Schedule above will be sufficient proof of notice.
Form IH 03 03 06 08 Page 1 of 9
0 2008, The Hartford
POLICYNUMBER: 35LJFNQU0581 V
KIM
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
V NOTICE OF CANCELLATION
TO DESIGNATED PERSON(S) OR ORGANIZATION(S)
OTHER THAN THE NAMED INSURED
This policy is subject to the following conditions•:
SCHEDULE
Number of Days Notice 30 •. /
Name of Person(s) or Organization(s)
Carpus Christi, City of
Mailing Address
1201 Leopard St.
Corpus Christi TX 78401•
If this policy is cancelled, we agree that the person(s) or organization(s) listed in the Schedule above will be
notified at least:
a. 15 days before the effective date of cancellation if we cancel for non - payment of premium; or
b. The number of days shown in the Schedule above before the effective date of cancellation if we cancel for
any other reason.
In no event, however, will notice of cancellation be less than the minimum number of days required by the
jurisdiction to which this endorsement applies,
If notice is mailed, proof of malling to the address shown in the Schedule above will be sufficient proof of notice.
Form IH 03 03 06 08 Page 1 of 1
0 2008, The Hartford
/ f
Policy Number 35WNQUO582
THE HARTFORD
This endorsement forms a part of the policy as numbered Named Insured and Address
above, ]sued by THE HARTFORD INSURANCE GROUP
company designated therein, and takes effect as of the
effective date of said policy unless another effective date
Is stated herein.
£B OV& Date Effective flour Is Vw same as stated
In the bealairwtions w he u a
Endo No.
WRITTEN NOTICE OF CANCELLATION
V
This policy shall not be cancelled or materially changed without first giving 3 0 days prior wdtten notice to:
Name: Corpus Christi, City of
Address: 1201 Leopard St., Corpus Christi, Tx 78401
Nothing herein contained shall be held to vary, weive, alter, or extend any of the terms, conditions, agromnents or declarations of
the policy, other than as herein stated.
This endorsement shall not be binding unless countersignad by a duly authorized agent of the company; provided that if this
endorsement takes effect as of the effea5ve date of the pollcy and, at issue of said policy, forms a part thereof, countersignature f
on the declarations page of said policy by a duly authorized agent of the company shall constitute valid countersignature of this
endorsement.
Form WC 99 04 63 (ed. IV98) Printed In USA Countersigned by .._
Authorized Agent