HomeMy WebLinkAboutC2012-025 - 1/31/2012 - ApprovedCITY OF CORPUS CHRISTI
AMENDMENT NO. 2
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas hereinafter called "CITY ", and LNV, Inc., hereinafter called "ENGINEER,"
agree to the following amendment to the Contract for Professional Services for Oso Water Reclamation
Plant Nutrient Removal Pro'ec# Ammonia Pro No. E09007) as authorized and amended by:
Original A/E Agreement
August 24, 2010 M2010 -197
$ 550,059.00
Amendment No. 1
January 16, 2012 Administrative Approval
$49,600.00
Exhibit "A ". . SECTION 1. SCOPE OF SERVICES PART A. BASIC SERVICES and PART B. ADDITIONAL
SERVICES, shall be amended as follows:
• Evaluation of Breakpoint Chlorination Pilot Facility Data
• Belt Press Facility & Odor Control Design & Bidding Integration
• Belt Press Facility Construction Observation
In the original contract, EXHIBIT "A ", SUMMARY OF FEES shall be modified and is attached as Amendment
No. 2 Exhibit "A" for a revised fee not to exceed $247,395.00 (Two Hundred Forty -Seven Thousand Three
Hundred Ninety Five Dollars and zero cents). for a total restated fee not to exceed $847,054 (Eight Hundred
Forty Seven Thousand Fifty Four Dollars and zero cents).
All other terms and conditions of August 24, 2010 contract between the City and Consultant will remain
in full force and effect.
CITY OF CORPUS CHRISTI
Oscar R. Martinez Date
Assistant City Manager
RECOMMENDED
kZ1 7 11—
Daniel Biles, P.E. Date
Interim Director of Engineering Services
ATTEST
Armando Chapa, City Secr6 ry
APPROVED AS TO FORM
Assistant City Att ney U Date
ENV, Inc..;
LNV, Inc.
• I7�Z�f
ysr8iNavigation, S. Leyendecker, P.E. Date
ident
Suite 300
Corpus Christi, TX 78408
(361) 883 -1984 Office; (361) 883 -1986 Fax
b _24 AU I HUKILLt
SECRETARY lam'
Project Number: E09007
Funding Source: 550950 - 4504 - 33110- EO9007
Encumbrance Number:
2012 -025
M2012 -028
01/31,12 07 -Oso WRP Nutrient Removal Project -Peer Review %Arnendment No. 2\Ccntmct for Professional Services - Amendment No. 2.dccx
INDEXED
LNV
engineers [ architects I contractors
January 16, 2012
Mr. Pete Anaya, P.E.
Director of Engineering Services
City of Corpus Christi
Engineering Services
P.O. Box 9277
Carpus Christi, TX 78469 -9277
Solutions Today with a
Vision for Tomorrow
Re: AMENDMENT NO. 2 TO PROFESSIONAL SERVICES CONTRACT
OSO WATER RECLAMATION PLANT NUTRIENT REMOVAL PROJECT (AMMONIA)
CITY PROJECT NO. E09007 (LNV PROJECT NO. 100140.002)
Dear Mr. Anaya:
In response to the City's request, we are proposing the following amendment for basic
and additional services associated with the Oso WRP Nutrient Removal Project
(Ammonia), City Project No. E09007.
Project Description:
The City of Corpus Christi, Texas, hereinafter called "City ", and LNV, Inc. hereinafter
called "Engineer ", agree to the following Contract for Basic and Additional Services
associated with the above referenced project.
The basic service effort includes providing preliminary, design, bid, and construction
phase engineering services associated with the original project, Oso WRP Belt Press
Facility project, and the Lift Station No.2 odor control improvements. These services
consisted of the detailed evaluation of all potential ammonia removal alternatives as
directed by the City, the design of the Lift Station No. 2 odor control improvements and
incorporation of this design into the Belt Press Facility bid package along with the
incorporation of the Breakpoint Chlorination Pilot facility plans and specs into the Belt
Press bid package as well. Tasks also include providing full service design coordination
with the approved equipment suppliers, design of a 24 -in RAS line for future use,
assembly of the required documents for two. (2) addenda and creation of special
provisions for substantial completion and performance incentives /disincentives. These
services were requested by the Operating Department.
The additional service effort includes construction observation services for the full
duration of the Belt Press Facility Project, coordination and modifications to the Oso
WRP Regulatory Compliance and Implementation plan based on the Belt Press Facility
design, sampling and data analysis associated with the pilot facilities, and creation of
the necessary land acquisition documents for the Oso WRP buffer zone as required by
the state.
AMD. NO. 1
EXHIBIT "A"
Page 1 of 6
Scope of Services:
The Scope of Services for this contract shall be modified to include the following tasks:
A. Basic Services
1. Preliminary Phase
• Perform an evaluation of ammonia removal alternatives as directed by the
City, including conventional biological ammonia removal, IFAS, Nitrifying
Trickling Filters (NTF), Moving Bed Bioreactors (MBBR), air stripping, and ion
exchange. This shall be completed in addition to an evaluation of the
Breakpoint Chlorination process.
• Engineer will document the evaluation process in a technical memorandum.
The TM shall clearly identify the screening criteria used to evaluate each
process, shall identify whether a phased (near term & long term) approach
provides benefit to the City and ultimately determine the recommended
process.
2. Design Phase
• Oso WRP Belt Press Facility - Provide a full review of the Belt Press Facility
plans and specifications by others, providing review comments to AE,
coordination with equipment suppliers and Wastewater personnel, revising
existing project specifications to incorporate additional approved suppliers
and to encourage bidder participation, and development of the substantial
completion and performance incentive /disincentive special provisions.
• Oso WRP Lift Station #2 Odor Control [mprovements - Tasks include
interviews with plant personnel and equipment supplier to appropriately define
the issues with the existing odor control facility, to identify the original design
criteria, to gauge the severity of the problem and to ascertain the most
feasible alternatives for improving the existing system. Work also includes
development of project recommendations and scope of improvements, and
incorporation of the drawings and specifications into the Oso WRP Belt Press
Facility bid package by others.
• Meetings - Prepare for and conduct five (5) project design coordination
meetings approximately two (2) hours each with City personnel and/ or
equipment suppliers to confirm that the design of the proposed improvements
and specified equipment meets the City's expectations, will provide a good
application and will perform as intended. These meetings may be held at the
LNV Conference Room, City conference room or at the Oso WRP site..
AMD. NO. 1
EXHIBIT "A"
Page 2 of 6
3. Bid Phase
• Perform bid phase services for the Oso WRP Belt Press Facility, Breakpoint
Chlorination Pilot Facility and Lift Station #2 Odor Control improvements.
This work includes attending the Pre -Bid Meeting, Pre -Bid site visit, receiving
contractor's questions via email /facsimile, coordinating with project engineer
and architect to define a clear, thorough and responsive answer to each
question, and generate /issue all project addenda (2 separate documents)
required to modify the bid package and/or to clarify the Engineer's intent on
the construction documents.
4. Construction Phase
• Perform construction phase services for the Lift Station #2 Odor control
improvements. This will consist of reviewing submittals, performing regular
site visits to review for conformance with the contract documents, providing
interpretations and clarifications of the contract documents for the contract as
needed, and making the final inspection with City staff.
• Site Visits will consist of approximately six (6) trips at 1.5 hrs each.
B. Additional Services
1. Permitting — NONE
2. Topographic Survey —NONE
3. Environmental Issues —NONE
4. Construction Observation Services
• Engineer will provide a part -time (20 hrs /week) Project Representative (PR)
for the duration of construction for the Oso WRP Belt Press Facility project,
City Project 7423. Total project duration is 520 days (approximately 75
weeks) for a total of 1,500 hours.
5. Start -up Services — NONE
6. Warranty Phase -- NONE
7. Provide SCADA Documentation — NONE
S. Pilot Study — Breakpoint Chlorination — NONE
9. Oso WRP Regulatory Compliance & Implementation Plan
AMD. NO. 1
EXHIBIT "A"
Page 3 of 6
• This task was originally titled "Oso WRP Master Plan° and has been amended
and renamed as shown above.
• Work consists of coordinating the Oso WRP Regulatory Compliance &
Implementation Plan with the design of the proposed Belt Press Facility
project, reviewing engineering drawings and solids production calculations by
others, identifying and confirming the most beneficial footprint and location,
and coordinating the location of a proposed 24 -in RAS line for future use with
the plant re- rating.
10.0so WRP Process Modeling — NONE
11. Step Feed Pilot Study— NONE
12.Step Feed Pilot Sampling & Analysis
• This task includes the "turn -key" sampling and testing program for step feed
pilot study. The sampling will be performed every 3 -4 days for the.. 45 -day
duration of the pilot operation. DO & pH will be measured during each of the
11 sampling days at the midpoint of each basin (5 locations) only for the east
train. These locations will be identified in the field at a later date. Laboratory
testing will include approximately 33 tests for each of the constituents shown
in Table 5 -1.
• Sampling will be performed as per the following schedule:
• Composite samplers will be used, if possible, for influent and effluent of each
train as shown below. Each of the samples will be tested for the following
constituents.
AMD. NO. 1
EXHIBIT "A"
Page 4of6
,
• Composite samplers will be used, if possible, for influent and effluent of each
train as shown below. Each of the samples will be tested for the following
constituents.
AMD. NO. 1
EXHIBIT "A"
Page 4of6
Table 1
`� Ts t lain
00
N
X.
0
law„ a
T X .;' X
13.Oso WRP Buffer Zone
• This work includes all tasks associated with aiding the City in obtaining a
revised and/or modified buffer zone around the perimeter of the Oso WRP.
The desired 150 -ft buffer zone would begin at the plant's existing fence line
but is currently located inside the fence line and as a result, limits the plant's
ability to construct new facilities on their property as older facilities are retired.
• Includes an investigation of the City's existing buffer zone documents,
surrounding land ownership, adjacent utility /drainage easements and/or right
of way documents, coordination with the City and adjacent land owners, and
preparation of the necessary buffer zone easement documents.
Schedule:
• All work will be completed by the Engineer no later than August 2013 which is the
scheduled completion of the Oso WRP. Belt Press Facility project.
Fees:
A. Fee for Additional . Services Authorized. The City will pay the Engineer a
total restated lump sum fee not to exceed $ 847,054.00 for provided
services specified in this contract. The fee will be full and total
compensation for services and for all expenses incurred in performing
these services. Engineer will submit monthly statements for basic services
rendered. Each statement will be based on the project percent completion
at the time of billing. City will make prompt monthly payments in response
to Engineer's monthly statements.
AMD. NO. 1
EXHIBIT "A"
Page 5 of 6
B. Summary of fees. See below.
SUMMARY OF A/E FEES
Please feel free to contact me, should you have any questions.
Sincerely,
LNV, INC.
TBPE Firm No. F -366
Dan S. Leyendecker, P.E.
President
AMD. NO. 1
EXHIBIT "A"
Page 6 of 6
ORIGINAL
CONTRACT
AMD. NO. 1
AMD.. NO. 2
TOTAL
BASIC SERVICES
1. Preliminary Phase
$ 97,454.00
$
$
14,896.60.
$ 112,344.00
2. Design Phase
$ 139,508.00
$
-
$
17,820:60
$ 157,328.00
3. Bid Phase
$ 8,077.00
$
-
$
... , 5 1 240.00
$ 13,317.00
4. Construction Phase
$ 33,929.00
$
-
$
1;760.00
$ 35,689.00
Subtotal Basic Services
$ 278,968.00
$
$
39 1 710.00
$ 318,678.00
ADDITIONAL SERVICES ALLOWANCE
1. Permitting
$ 8,924.00
$
$
-
$ 8,924.00
2. Topographic Survey
$ 8,670.00
$
$'
-
$ 8,670.00
3. Environmental Issues
4. Construction Observation Services
$ 49,748.00
$
$
142 `
$ 192,248.00
5. Start-Up Services
$ 19,124.00
$
$
-
$ 19,124.00
6. Warranty Phase
$ 5,612.00
$
$
. -
$ 5,612.00
7. Provide SCADA Documentation
$ 3,511.00
$
$
-
$ 3,511.00
8. Pilot Stud - Breakpoint Facility
$ 71,536.00
$
-
$
' -
$ 71,536.00
9. Oso WRP Reg. Compliance & Imp. Plan
$ 72,679.00
$
-
$
8 ;685:00
$ 81,364.00
10. Oso WRP Process Modeling
$ 31,287.00
$
-
$,,..
-
$ 31,287.00
11. Step Feed Pilot Study
49,600.00
$
-
$ 49,600.00
12. Step Feed Pilot Sampling & Analysis
$
$
-
$-
44,500:0:0;.
$ 44,500.00
13. Oso WRP Buffer Zone
$
$
-
$
12
$ 12,000.00
Subtotal Additional Services
$ 271,091.00
$
49,600.00
$
207
$ 528,376.00
TOTAL AUTHORIZED FEE
$ . 550,059.00
$
49;600.00,
$
247,895.00
$ 847,054.00
Council Approval
Admin Approval
Council Approval
Please feel free to contact me, should you have any questions.
Sincerely,
LNV, INC.
TBPE Firm No. F -366
Dan S. Leyendecker, P.E.
President
AMD. NO. 1
EXHIBIT "A"
Page 6 of 6
SUPPLIER NUMBER
TO BE ASSIGNED BY CrrY`
PURCHASING DIVISION
City of CITY OF CORPUS CHRISTI
DISCLOSURE OF INTEREST
City of Corpus Christi Ordinance 17112 as amended, requires all persons or firms seeking to do
business with the City to provide the following information. Every question must be answered.
If the question is not applicable, answer with `NA ". See reverse side for Filing Requirements,
Certifications and definitions.
COMPANY NAME: LNV Engineering
P. O. BOX:
STREET ADDRESS: 801 Navigation, Suite 300 CITY: Cornus Christi
FIRM IS: 1. Corporation X 2. Partnership ❑
4. Association ❑ S. Other
ZIP: 78408
3. Sole Owner ❑
DISCLOSURE QUESTIONS
If additional space is necessary, please use the reverse side of this page or attach separate sheet:.
1. State the names of each "employee" of the City of Corpus Christi having an "ownership
interest" constituting 3% or more of the ownership in the above named "firm.'
Name Job Title and City Department (if known)
NIA
2. State the names of each "official" of the City of Corpus Christi having an "ownership interest"
constituting 3% or more of the ownership in the above named "firm."
Name Title
NIA
3. State the names of each "board member" of the City of Corpus Christi having an "ownership
interest" constituting 3% or more of the ownership In the above named "firm."
Name Board, Commission or Committee
Dan S. Le endecker Marina Advisory Board
4. State the names of each employee or officer of a "consultant" for the City of Corpus Christi
who worked on any matter related to the subject of this contract and has an "ownership
interest" constituting 3% or more of the ownership in the above named "firm."
Name Consultant
NIA
If a parson w ho regitc is ofl citil- action can a mattQ knows that the requested ,,R;tion will coailer all
economic hetnfit tau any C."ivy official or employee that is distinguishable fi°om the ellia i that tfae
action will have on nacmber.� of the public in ,# rneral or a substatttiai segmeni thereof, you sli al'l
disclose that fact in n signed writing to the Cit official. employee or body that fitt.s I eeejj
requested to ai,t in the .matter. unless t.fie, ntcrest of tltc City talficatal car entlalovcc in the €nattQ..l is
a parent. The clisclosurc sli:tll also be glade in a slgncd writirig .filed �ttli the City Sccre.tir -v
- Pthics Orciinance ` winn 2 -349
CERTd 1` tC A"d'`l ON
1 o €rtifv that all inibrniatiun provided is tme a coiTect as of date of thk, saatett ent_ ft it l
have, not .know -ingly withheld disclosure of atav iufoi [witioll r_equk,. and that s fipple ment,1l
statements will be prompO siibmitted to the C. iv}- oC (' >rpus Christi, Texas as c;lr,in, ' i occ:iir.
Certifying Person: D-an S. Leyondecker, :P. 1 . Title: Presiden
_-.__.._
_. ..... ._... _._....... _._..__....___..
Signature of Certil"yin) t)srtr
Petso
_... .._.
a, - Board ine €nber. "' 'A nacrnber of any board, commission- or corm nitice appointed by the
CitV Council of the City Corpus Christi, Texas.
la. ".12conannic: Benefit. ". An aciioii that is likely to affect an economic i €atcrest if" it is likel-y- to
have an ct:1•ect,on that inicrest that is distinguish €iblt^ fron.) its effect on aracmbers of Ehe ptl
in general ai °a subsea €ttiatiscg:ment thereof'.
- Employee,'' .1rnv person employed by the G. y oi'C:rarptas Christi, 7TeNas rather on a f ia.11 or
part basis. but teat as an itadepe iident coma oior_
d_ '`1~irim" Ann antfta operated I'c " economic ifmn. M)etfier professional, €ndw,, - irial or
commercial, rind 'Wltedte:r ustablislied to produce or deal with a product or s rci::e_ ineluzdino
tint not limited to, entities open red ira the form of scale; proprietoNhip, trs scif- ploy -ed
person, partnertihip, C(VPOratiera. stock -conipan y, joint venture;, receivership Err en act. and
entities which 101• purl)oseS oftavition are treated as nrm prolif ovggnIzations.
v. - Official. -, The Mayor, mcin.bers of the City Council. City N-la'a~a Deputy City
Manager, Assi -. t wnt City Managers. Departnacrtt. jud Division Head , -rnd NSunic,ilatal Colin
Judges of the Cite cal' C arpus Christi, Texas,
i" : fnTerest." L.cg.af tar equit itne;ae,t.. rvlict.licr actitially or consiruc;tively held,
iti a frrni, including -,V11en such interest is hold through. an went. trust.. estaw.. or hc+ldino
entity. " Conmructivcly lie ld " refena to holdings or control established thrc wdi vniiii- trusts.
proxies_ car special terms of venture or parme ship zt.wree;ments,
"Consultant." Any person or first, such as engineers and architects, hired by the City of:
Carpus Christi for the purpose; of professional consultation and recommendation,