HomeMy WebLinkAboutC2012-397 - 10/24/2012 - NAAMENDMENT NO.2
TO CONTRACT FOR
PROFESSIONAL SERVICES
The City of Corpus Christi, Texas hereinafter called "CITY ", and Hargreaves Associates, hereinafter called "CONSULTANT',
agree to the following amendment to the Contract for Professional Services for Bayfront Development Plan Phase 3
Pro'ect No. 6511 as authorized and administratively amended by:
Original A/E Agreement December 13, 2011
Motion No. M2011 -292
$1,315,137.50
Amendment No. 1 September 28, 2012
Admin. Approved
$26,570.00
In the original contract, EXHIBIT "A ", SCOPE OF SERVICES, Concept Design Tasks, Reimbursable Expense for
Additional City Staff Meetings shall be amended to include additional services as shown on the attached Amendment No. 2
Exhibit "A ".
In the original contract, EXHIBIT "D ", SUMMARY OF FEES shall be amended as described in the attached Amendment No. 2
Exhibit "A" for a revised fee not to exceed $16,440.00 (Sixteen Thousand Four Hundred Forty Dollars and Zero Cents) for
a total restated fee not to exceed $1.358,147.50 (One Million Three Hundred Fifty Eight Thousand One Hundred Forty
Seven Dollars and Fifty Cents) ^
All other terms and conditions of the Contract and Amendments between the City and Consultant will remain in full force and
effect.
CITY OF CORPUS CHRISTI
O AIC- --- ; 7 7 P? e4 / - -
Oscar R. Martinez Date
Assistant City Manager
RECOMMENDED
/ol 6
aniel Biles, RE. Date
Director of Engineering
Operating Depaftme Date
A P P71 AST FORM
D
Office of Manageme t and Budg t Date
2012 -397 ate
Hargreaves Associates
10/24/12
HARGREAVES ASSOCIATES
/oll 17,
Marf Wargafet Jones ' Date
President
398 Kansas Street
San Francisco, CA 94103
(415) 865 -1811 Office
(415) 865 -1810 Fax
BAYFRONT DEVELOPMENT PLAN PHASE 3VAMENDMENT NO 2%AE AGREEMENT.doc
AMEND. NO. 2
Page 1 of 2
INDEXED
ATTEST
Armando Chapa, Date
City Secretary
Project Number: 6511
Funding Source: 550950 -3126- 00000 - 970678
Fund Name: Bayfront Development 09 GO C1P
Encumbrance Number:
ENTERED
OCT 82012
CONTRACT MANAGERS
K\Engineering DalaExchangeLANGIEWARK & RECZ511 BAYFRONT DEVELOPMENT PLAN PHASE MAMENDMENT NO 2LAE AGREEMENTA00
"�P�
AMEND. NO. 2
Page 2 of 2
ASSOCIATES
Aug. 27, 2012
Dan Biles
Department of Engineering Services
1201 Leopard Street
Corpus Christi, TX 78401
Re: Bayfront Development Plan Phase 3 Project No 6511
Request for Additional Services
HA Project #: CDB 1101
. 398 KANSAS STREET
SAN FRANCISCO, CA 94103
415865 i8n T
415865 1810 F
HARGREAVES.COM
Task 1. August 9 -10 Meetings — Review of Cost and Phasing Strategies and City Department
Meetings - $16,440*
Hargreaves Associates was asked to present the Destination Bayfront Concept Design to various
City Departments, including:
Utilities (Water, Wastewater, Solid Waste)
City Planning
Economic Development
Parks Department Operations & Maintenance Staff
Police & Fire
These meetings are those beyond the 2 focus group meetings specified in the original Contract.
Hargreaves Associates was also asked to focus the Executive Committee meeting on a review of
Cost and Phasing in lieu of the Schematic Design review originally scheduled for this time.
Fee breakdown:
Hargreaves Associates - $13,320
Lake Flato Architects - $3,120
* H R&.A effort towards this meeting has been covered by Additional Service Request #1. The
following are covered in the base contract: ETM's presentation of O &M and Governance and team
reimbursable expenses for the August trip.
Please call me to discuss any comments or questions regarding this proposal.
Thank you,
SAN FRANCISCO
CAMBRIDGE
NEW YORK
BERNWARD ENGELKE
MISTY MARCH
AMEND. NO. 2
EXHIBIT "A"
Pa e 1 of 3
GEORGE HARGREAVES
Dear pan,
MARY MARGARET JONES
GAVIN MCMILLAN
We are submitting this scope and fee to you for additional services related to additional City
KIRT RIEDFR
Department Meetings and Executive Committee meeting ocused on the review of Cost and Phasin
p g g g
CATHERINE MILLER
'
strategies. All terms and conditions of the original contract to which this is an additional service
KEN HAINES
PETERSEN
apply. Additional services are based on 2012 hourly rates and are described below:
;ACOB
BRIAN JENCEK
ALAN LEWIS
Scope of Services / Fees and Expenses — $16,440
LARA ROSE
Task 1. August 9 -10 Meetings — Review of Cost and Phasing Strategies and City Department
Meetings - $16,440*
Hargreaves Associates was asked to present the Destination Bayfront Concept Design to various
City Departments, including:
Utilities (Water, Wastewater, Solid Waste)
City Planning
Economic Development
Parks Department Operations & Maintenance Staff
Police & Fire
These meetings are those beyond the 2 focus group meetings specified in the original Contract.
Hargreaves Associates was also asked to focus the Executive Committee meeting on a review of
Cost and Phasing in lieu of the Schematic Design review originally scheduled for this time.
Fee breakdown:
Hargreaves Associates - $13,320
Lake Flato Architects - $3,120
* H R&.A effort towards this meeting has been covered by Additional Service Request #1. The
following are covered in the base contract: ETM's presentation of O &M and Governance and team
reimbursable expenses for the August trip.
Please call me to discuss any comments or questions regarding this proposal.
Thank you,
SAN FRANCISCO
CAMBRIDGE
NEW YORK
BERNWARD ENGELKE
MISTY MARCH
AMEND. NO. 2
EXHIBIT "A"
Pa e 1 of 3
Lara Rose
Principal
Additional services authorized by:
Signature:
Name Printed: Date:
AMEND. NQ. 2
EXHIBIT "A"
Pa e2of3
* August meetings for HR&A included in Previous Add Service
' August meetings for ETM included in Base Contract
M 3
_ Z
� �
argreaves Associates
O -
wn0
N
Destination Bayfront
Hargreaves Associates
Fee and Reimbursable Breakdown
HE
812712012
HR&A*
$
ETMI **
$
Lake Flato
$ 3,120.00
Turner Ramirez
$
3 6" 4Q
HE
812712012
Corpus Christi Destination Bayfront Fee Summary
ORIGINAL
CONTRACT
AMEND. NO. 1
AMEND. NO.2
TOTAL
CONCEPT DESIGN TASKS
COST
Task A
Site Analyses and programing
A -1
Data Collection /Site Analyses (Kickoff Meetings)
$39,960.00
$0.00
$0.00
$39,960.00
A -2
Shoreline Drive Coordination
$8,660.00
$0.00
$0.00
$8,660.00
A -3
South Central Development Plan Coordination
$6,260.00
$O.OD
$0.00
$6,260.00
A-4
Programming Validation
$31,780.00
$0.00
$0.00
$31,780.00
Sub - tDtal:
$86,660 -DO
$0.00
$0.00
$86,660.00
Task B
Concept Design and Graphics
8-1
Preliminary Concept Design + Draft Graphics {Advisory Group Stakeholders
Community Meeting #1)
$137,440.00
$0.00
$0.00
$137,440.00
B-2
Order of Magnitude Cost / Potential Phasing Concept Options
$15,050,00
$0.00
$0.00
$15,050.00
B-3
Final Concept Design + Final Graphics
$171,400.00
$0.D0
$0.00
$171,400.00
B-4
Order of Magnitude Cost / Potential Phasing Final Concept
$16,790.00
$0.00
$0.00
$16,790.00
Sub - total:
$340,680.00
$0.D0
$0.00
$340,680.00
Task
Supplementary Plans - Concept Design
C -1
Economic Opportunities Analysis
$17,780.00
$0.00
$0.00
$17,780.00
C -2
Ballpark 0 & M Budgets for Options and Final Concept
$12,100.00
$0.00
$0.00
$12,10D.D0
C -3
Park Naming Plan
$5,100.00
$0.00
$0.00
$5,100.00
C -4
Revenue Plan based on Concept Design
$20,926.00
$0.00
$0.00
$20,926.00
C -5
Capital Funding Plan based on Concept Design
$19,350.00
$0.00
$0.00
$19,350.00
C -6
Review/ Inputto Programming and Concept Design Options
$21,800.00
$0,00
$0.00
$21,800.00
C -7
Meetings /Team Coordination
$8,730.00
$0.00
$0.00
$8,730.00
Sub -total:
$105,786.00
$0.00
$0.00
$105,786.00
Task D
Sub - Consultant Management Fee
$12,700.00
$0.o0
$0.00
$12,700.00
Basic Services Total:
$545,826.00
$0.00
$0.00
$545,826.00
Itemized Additional Services
#1
Base Map Preparation / Surveying
TBD
TBD
TBD
TBD
##2
Physical Model a V =40' (Not Authorized at this time)
$40,500.00
$0.00
$0.00
$40,500.00
#a
Additional Trip / Client Group Meeting {time only, see reimbursables below)
TBD
TBD
TBD
TBD
#4
Additional Community Meeting {time only, see reimbursables below)
TBD
TBD
TBD
TBD
95
Additional Rendering
TBD
TBD
TBD
TBD
46
Master Plan of Adjacent Sites
TBD
TBD
TBD
TBD
47
CVB Luncheon and Economic Summit Presentations
$0.00
$16,070.00
$0.00
$16,070.00
Additional Services Total:
$40,500.00
$16,070.00
$0.00
$56,570.00
Reimbursable Expense Estimate
Reimbursable General Estimate -all Consultants
4 %Total Fee
Team Fee
Total
Total
Print, Copy Tele, FedEx, Misc, Regional Travel
4%
$ 533,126.00
$21,325.00
$0.00
$0.00
$21,325.00
Reimbursable Travel Estimate - Non -Local Consultants
Person Trips
$ / Person Trip
Total
Total
Hargreaves Associates (3 people typical per trip)
11
$1,750.00
$19,250.00
$0.00
$13,32(l.00
$32,570.00
HR &A (1 person typical per trip)
3
$1,750.00
$5,250.00
$0.00
$0,00
$5,250.00
ETM (1 Person typical per trip)
1
$1,750.00
$1,750.00
$0.00
$0.00
$1,750.00
Lake Flato (2 people typical per trip)
6
$500.00
$3,000.00
$0.00
$3,120.00
$6,120.00
TOTALTRAVEL:
$29,250.00
$0.00
$16,440.00
$45,690.00
Total Not -to -Exceed General + Travel Reimbursement Budget:
$50,575.00
$0.00
$16,440.00
$67,015 -DO
Total Concept Design Amount for Basic and Additional Services + Reimbursable Estimates:
$636,901.00
$16,070.00
$16,440.00
$669,411.00
12/1312011
M2011 -292
9128112
Admin Approval
Admin Approval
AMEND. NO. 2
EXHIBIT "D"
Pa e 7 of 2
Corpus Christi Destination Bayfront Fee Summary
ORIGINAL
CONTRACT
AMEND NO. 1
AMEND NO.2
TOTAL
SCHEMATIC DESIGN TASK$
Cost
T05k E
SthematiC Design Tasks
50% Schematic Design
E -1
Design Development/ Illustrative Graphics
$204,416.00
$0.00
$ 0.00
$204,416.00
Advisory Group/ Stakeholder/ Community Meetings # 3
E -2
50% Schematic Design Cost Estimate
$25,738.00
$0.00
$0.00
$25,738.00
100% Schematic Design
E -3
CAD Document Set/ Technical Memos
$227,396.00
$0.00
$0.00
$227,396.00
Advisory Group/ Stakeholder / Community Meetings #4
E-4
100% Schematic Design Cost Estimate
$31,600.00
$0.D0
$0.00
$31,600.00
Sub - Total:
$489,159.00
$0.00
$0.00
$489,150.00
Task F
Supplementary Plans - Schematic Design
F -1
Sustainable Opportunities Plan
$31,100.00
$0.00
$0.00
$31,100.00
F -2
Programming Plan
$27,500.00
$0.00
$0.00
$27,500.00
F -3
Master Implementation and Phasing Plan
$14,100.00
$0.00
$0.00
$14,100.00
F-4
Refined Capital Funding Plan based on SD
$9,390.00
$0.00
$0.00
$9,390.00
F -5
Refined Revenue Plan based on SD
$9,200.00
$0
$0.00
$9,200.00
F -6
Operations and Maintenance Budget
$17,970.00
$0.00
$0.00
$17,970.00
F -7
GDverance I Organizational Plan
$20,340.00
$0.00
$0.00
$20,340.00
F -8
Meetings /Team Coordination
$3,500.00
$0.00
$0.00
$3,500.00
Sub Total:
$133,100.00
$0.00
$0.00
$133,100.00
Task G
Sub - Consultant Management Fee
$15,096.50
$0.00
$0.00
$15,096.50
Basic Services Total:
$637,345.50
$0.00
$0.00
$637,346.50
Itemized Additional Services
TIRZ and Downtown Special Assessment Work
$0.00
$10,500.00
$0.00
$10,500.00
Additional Services Total
$0.00
$10,500.00
$0.00
$10,500.00
Reimbursable Expense Estimate
Reimbursable General Estimate- all Consultants
4 %Total Fee
Team Fee
Total
Print, Copy Tele, FedEx, Misc, Regional Travel
4%
$622,250.00
$24,890.00
$0.00
$0.00
$24,890.00
Reimbursable Travel Estimate - Non -Local Consultants
Person Trips
$ / Person Trip
Total
Hargreaves Associates (3 people typical per trip)
6
$1,750.00
$10,500.00
$0100
$0.00
$10,500.00
HR&A )1 person typical per trip)
0
$1,750.00
$0.00
$0.00
$0.00
$0.00
ETM (1 Person typical per trip)
2
$1,750.00
$3,500.00
$0.00
$0.00
$3,500.00
Lake Flato {2 people typical per trip)
4
$500.00
$2,000.00
$0.00
$0.00
$2,00040
TOTALTRAVEL:
$16,000.00
$0.00
$0.00
$16,000.00
Total Not -to- Exceed General +Travel Reimbursement Budget:
$40,890.00
$0.00
$0.00
$40,890.00
Total Schematic Design Amount tar Basic and Additional Services + Reimbursable Estimates:
$678,236.50
$10,500.00
$0.00
$1,358,147.50
Contract Value for Master Implementation and Phasing Plan Phase (Concept and Schematic Design Tasks):
$1,315,137.50
$26,570.00
$16,440.00
$1,358,147.50
12/13/2011
M2011 -292
9/28/12 Admin
Approval
Admin Approval
AMEND. NO. 2
EXHIBIT "D"
Pa e2of2